Addendum 1 - Specs Changes.pdf
PDF 124 KB Posted
- Attached to
- Convert Bldg 91157 from Storage Warehouse to Testing Lab Federal contract opportunity
- Solicitation number
- FA441721B0003
About this file
This solicitation and supporting documents outline requirements for a federal contract to convert Building 91157 at Hurlburt Field, Florida from a storage warehouse to a materials testing laboratory. The Department of the Air Force Special Operations Command is seeking a contractor to repair and renovate the building, including replacing an existing lift station, cutting and patching concrete and asphalt, and installing a new 2-inch water service. Bids are due by September 2, 2021. The selected contractor will be responsible for excavation, backfill, compaction, and subgrade preparation work in accordance with provided specifications. The renovation requires installing a new sewer system, concrete cutting and patching, and boring under existing pavement to install steel pipeline casings for utilities. The contractor must properly dispose of all excavated materials and protect existing utilities during construction.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA441721B0003 - Questions and Answers - Part 2.pdf | ||
| Addendum 1 - Drawings Changes.pdf | ||
| Attachment 7 - Drawings - Revised (Addendum 1).pdf | ||
| Solicitation Amendment 2 - FA441721B00030002 SF 30.pdf | ||
| Attachment 6 - Specifications - Revised (Addendum 1).pdf | ||
| CE Response - Site Visit Questions.pdf | ||
| Site Visit Sign In Sheet - 25 August 2021.pdf | ||
| Memo for Record - FA441721B0003 Pre-Proposal Conference_Site Visit - 25 August 2021.pdf | ||
| FA441721B0003 - Questions and Answers - Part 1.pdf | ||
| Solicitation Amendment 1 - FA441721B0003 SF 30.pdf | ||
| Attachment 1 - Specifications.pdf | ||
| Attachment 5 - Financial Institution Reference Sheet.pdf | ||
| Attachment 3 - Working Time Analysis.pdf | ||
| Attachment 4 - DBA Wage Determination FL20210217.pdf | ||
| Solicitation - FA441721B0003.pdf | ||
| Attachment 2 - Drawings.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT NO. CP1031923
Repair-Convert Bldg 91157 from Storage Warehouse to Testing Lab
ADDENDUM #1 2 Sep. 2021
1. Replace drawing sheets C201 with revised drawing sheet C201 dated 9-1-21. A portion of the new sewer system has been installed by government and is no longer required under this contract. Location of existing lift station added. Cutting and patching of existing concrete and asphalt has been added for installation of 2” water service.
2. Replace drawing sheets C502 with revised drawing sheet C502 dated 9-1-21.
Concrete cut & patch detail added.
3. Replace section 31 00 00 Earthwork with revised section 31 00 00 dated 9/1/2021.
END OF ADDENDUM
Repair-Convert Bldg. 91157 from Storage CP1031923 Warehouse to Material Testing Lab-Replace Existing Lift St Hurlburt Field, FL
SECTION 31 00 00
EARTHWORK
PART 1 GENERAL
1.1 CRITERIA FOR BIDDING
Base bids on the following criteria:
a. Surface elevations are as indicated.
b. Pipes or other artificial obstructions, except those indicated, will not be encountered.
c. Ground water will be encountered at depths varying from three (3) to six (6) feet below existing grade.
d. Material character is indicated by the boring logs.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only. Publications used shall be the most current issue.
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS
(AASHTO)
AASHTO T 180 (2019) Standard Method of Test for Moisture-Density Relations of Soils Using a 4.54-kg (10-lb) Rammer and a 457-mm (18-in.) Drop
AASHTO T 224 (2010) Standard Method of Test for Correction for Coarse Particles in the Soil Compaction Test
AMERICAN WATER WORKS ASSOCIATION (AWWA)
AWWA C600 (2017) Installation of Ductile-Iron Mains and Their Appurtenances
AMERICAN WELDING SOCIETY (AWS)
AWS D1.1/D1.1M (2020) Structural Welding Code - Steel
ASTM INTERNATIONAL (ASTM)
ASTM C136 (2006) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates
ASTM D1140 (2017) Standard Test Methods for Determining the Amount of Material Finer than 75-µm (No. 200) Sieve in Soils by Washing
SECTION 31 00 00 R Page 1
Revised 9/1/2021
ASTM D1556 (2007) Density and Unit Weight of Soil in Place by the Sand-Cone Method
ASTM D1557 (2012; E 2015) Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3)
ASTM D2167 (2015) Density and Unit Weight of Soil in Place by the Rubber Balloon Method
ASTM D2487 (2017; E 2020) Standard Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System)
ASTM D4318 (2017; E 2018) Standard Test Methods for Liquid Limit, Plastic Limit, and Plasticity Index of Soils
ASTM D4944 (2018) Standard Test Method for Field Determination of Water (Moisture) Content of Soil by the Calcium Carbide Gas Pressure Tester Method
ASTM D6938 (2017a) Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)
ASTM D7928 (2017) Standard Test Method for Particle-Size Distribution (Gradation) of Fine-Grained Soils Using the Sedimentation (Hydrometer) Analysis
1.3 DEFINITIONS
1.3.1 Satisfactory Materials
Satisfactory materials comprise any materials classified by ASTM D2487 as
GW, GP, GM, GP-GM, GW-GM, GC, GP-GC, GM-GC, SW, SP, SM, SP-SM.
Satisfactory materials for grading comprise stones less than 8 inches. To be considered satisfactory, any offsite soils imported for use as backfill shall be tested and certified as meeting local, state, and federal regulation for clean fill prior to bringing to the site. Provide at least one borrow site testing from each borrow site used.
1.3.2 Unsatisfactory Materials
Materials which do not comply with the requirements for satisfactory materials are unsatisfactory. Unsatisfactory materials also include man-made fills; trash; refuse; backfills from previous construction; and material classified as satisfactory which contains root and other organic matter or frozen material. Notify the Contracting Officer when encountering any contaminated materials.
SECTION 31 00 00 R Page 2
1.3.3 Cohesionless and Cohesive Materials
Cohesionless materials include materials classified in ASTM D2487 as GW, GP, SW, and SP. Cohesive materials include materials classified as GC, SC, ML, CL, MH, and CH. Materials classified as GM and SM will be identified as cohesionless only when the fines are nonplastic. Perform testing, required for classifying materials, in accordance with ASTM D4318, ASTM C136, ASTM D1140 and ASTM D7928.
1.3.4 Degree of Compaction
Degree of compaction required, except as noted in the second sentence, is expressed as a percentage of the maximum density obtained by the test procedure presented in ASTM D1557 abbreviated as a percent of laboratory maximum density. Since ASTM D1557 applies only to soils that have 30 percent or less by weight of their particles retained on the 3/4 inch sieve, express the degree of compaction for material having more than 30 percent by weight of their particles retained on the 3/4 inch sieve as a percentage of the maximum density in accordance with AASHTO T 180 and corrected with AASHTO T 224 . To maintain the same percentage of coarse material, use the "remove and replace" procedure as described in NOTE 8 of Paragraph 7.2 in AASHTO T 180 .
1.3.5 Hard/Unyielding Materials
Hard/Unyielding materials comprise weathered rock, dense consolidated deposits, or conglomerate materials which are not included in the definition of "rock" with stones greater than 3 inch in any dimension or as defined by the pipe manufacturer, whichever is smaller. These materials usually require the use of heavy excavation equipment, ripper teeth, or jack hammers for removal.
1.3.6 Unstable Material
Unstable materials are too wet to properly support the utility pipe, conduit, or appurtenant structure.
1.3.7 Select Granular Material
1.3.7.1 General Requirements
Select granular material consist of materials classified as GW, GP, SW, or SP, by ASTM D2487 where indicated. The liquid limit of such material must not exceed 15 percent when tested in accordance with ASTM D4318. The plasticity index must not be greater than 12 percent when tested in accordance with ASTM D4318, and not more than 30 percent by weight may be finer than No. 200 sieve, and not more than 65 percent by weight finer than a No. 40 sieve when tested in accordance with ASTM C136.
1.3.8 Initial Backfill Material
Initial backfill consists of select granular material or satisfactory materials free from rocks 3 inches or larger in any dimension or free from rocks of such size as recommended by the pipe manufacturer, whichever is smaller. When the pipe is coated or wrapped for corrosion protection, free the initial backfill material of stones larger than 1 inch in any dimension or as recommended by the pipe manufacturer, whichever is smaller.
SECTION 31 00 00 R Page 3
1.4 SYSTEM DESCRIPTION
Subsurface soil boring logs are included on plan sheet C002. These data represent the best subsurface information available; however, variations may exist in the subsurface between boring locations.
1.4.1 Classification of Excavation
No consideration will be given to the nature of the materials, and all excavation will be designated as unclassified excavation.
1.4.2 Blasting
Blasting will not be permitted.
1.4.3 Dewatering Work Plan
Submit procedures for accomplishing dewatering work.
1.5 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Dewatering Work Plan
SD-03 Product Data
Utilization of Excavated Soils
SD-06 Test Reports
Testing
Borrow Site Testing Within 24 hours of conclusion of physical tests, submit digital copies of test results, including calibration curves and results of calibration tests, and certification that imported material is free of contamination and meets all local, state, and federal regulations for clean fill.
SD-07 Certificates
Testing
Qualifications of the Corps validated commercial testing laboratory or the contractor's validated testing facilities.
PART 2 PRODUCTS
2.1 BURIED WARNING AND IDENTIFICATION TAPE
Provide metallic core or metallic-faced, acid- and alkali-resistant, polyethylene plastic warning tape manufactured specifically for warning and
SECTION 31 00 00R Page 4 identification of buried utility lines. Provide tape on rolls, 3 inches minimum width, color coded as specified below for the intended utility with warning and identification imprinted in bold black letters continuously over the entire tape length. Warning and identification to read, "CAUTION, BURIED (intended service) LINE BELOW" or similar wording. Provide permanent color and printing, unaffected by moisture or soil.
Warning Tape Color Codes
Red Electric
Yellow Gas
Orange Telephone and Other Communications
Blue Water Systems
Green Sewer Systems
2.1.1 Warning Tape for Metallic Piping
Provide acid and alkali-resistant polyethylene plastic tape conforming to the width, color, and printing requirements specified above, with a minimum thickness of 0.003 inch and a minimum strength of 1500 psi lengthwise, and 1250 psi crosswise, with a maximum 350 percent elongation.
2.1.2 Detectable Warning Tape for Non-Metallic Piping
Provide polyethylene plastic tape conforming to the width, color, and printing requirements specified above, with a minimum thickness of 0.004 inch, and a minimum strength of 1500 psi lengthwise and 1250 psi crosswise. Manufacture tape with integral wires, foil backing, or other means of enabling detection by a metal detector when tape is buried up to 3 feet deep. Encase metallic element of the tape in a protective jacket or provide with other means of corrosion protection.
PART 3 EXECUTION
3.1 GENERAL EXCAVATION
Perform excavation of every type of material encountered within the limits of the project to the lines, grades, and elevations indicated and as specified. Perform the grading in accordance with the typical sections shown and the tolerances specified in paragraph FINISHING. Transport satisfactory excavated materials and place in fill or embankment within the limits of the work. Excavate unsatisfactory materials encountered within the limits of the work below grade and replace with satisfactory materials as directed. Include such excavated material and the satisfactory material ordered as replacement in excavation. Dispose surplus satisfactory excavated material not required for fill or embankment in areas approved for surplus material storage or designated waste areas. Dispose unsatisfactory excavated material in designated waste or spoil areas.
SECTION 31 00 00R Page 5
During construction, perform excavation and fill in a manner and sequence that will provide proper drainage at all times. Excavate material required for fill or embankment in excess of that produced by excavation within the grading limits from the borrow areas indicated or from other approved areas selected by the Contractor as specified.
3.1.1 Drainage
Provide for the collection and disposal of surface and subsurface water encountered during construction. Completely drain construction site during periods of construction to keep soil materials sufficiently dry. It is the responsibility of the Contractor to assess the soil and ground water conditions presented by the plans and specifications and to employ necessary measures to permit construction to proceed.
3.1.2 Dewatering
Control groundwater flowing toward or into excavations to prevent sloughing of excavation slopes and walls, boils, uplift and heave in the excavation and to eliminate interference with orderly progress of construction. Do not permit French drains, sumps, ditches or trenches within 3 feet of the foundation of any structure, except with specific written approval, and after specific contractual provisions for restoration of the foundation area have been made. Take control measures by the time the excavation reaches the water level in order to maintain the integrity of the in situ material. While the excavation is open, maintain the water level continuously, at least 2 foot below the working level. Operate dewatering system continuously until construction work below existing water levels is complete.
3.1.3 Trench Excavation Requirements
Excavate the trench as recommended by the manufacturer of the pipe to be installed. Slope trench walls below the top of the pipe, or make vertical, and of such width as recommended in the manufacturer's printed installation manual. Provide vertical trench walls where no manufacturer's printed installation manual is available. Shore trench walls more than 5 feet high, cut back to a stable slope, or provide with equivalent means of protection for employees who may be exposed to moving ground or cave in.
Shore vertical trench walls more than 4 feet high. Excavate trench walls which are cut back to at least the angle of repose of the soil. Give special attention to slopes which may be adversely affected by weather or moisture content. Do not exceed the trench width below the pipe top of 24 inches plus pipe outside diameter (O.D.) for pipes of less than 24 inches inside diameter, and do not exceed 36 inches plus pipe outside diameter for sizes larger than 24 inches inside diameter. Where recommended trench widths are exceeded, provide redesign, stronger pipe, or special installation procedures by the Contractor. The Contractor is responsible for the cost of redesign, stronger pipe, or special installation procedures without any additional cost to the Government.
3.1.3.1 Bottom Preparation
Grade the bottoms of trenches accurately to provide uniform bearing and support for the bottom quadrant of each section of the pipe. Excavate bell holes to the necessary size at each joint or coupling to eliminate point bearing. Remove stones of 3 inch or greater in any dimension, or as recommended by the pipe manufacturer, whichever is smaller, to avoid point bearing.
SECTION 31 00 00R Page 6
3.1.3.2 Removal of Unyielding Material
Where unyielding material is encountered in the bottom of the trench, remove such material 12 inch below the required grade and replaced with suitable materials as provided in paragraph BACKFILLING AND COMPACTION.
3.1.3.3 Removal of Unstable Material
Where unstable material is encountered in the bottom of the trench, remove such material to the depth directed and replace it to the proper grade with select granular material as provided in paragraph BACKFILLING AND COMPACTION. When removal of unstable material is required due to the Contractor's fault or neglect in performing the work, the Contractor is responsible for excavating the resulting material and replacing it without additional cost to the Government.
3.1.3.4 Excavation for Appurtenances
Provide excavation for manholes, catch-basins, inlets, or similar structures sufficient to leave at least 12 inches clear between the outer structure surfaces and the face of the excavation or support members.
Specify removal of unstable material. When concrete or masonry is to be placed in an excavated area, take special care not to disturb the bottom of the excavation. Do not excavate to the final grade level until just before the concrete or masonry is to be placed.
3.1.3.5 Jacking, Boring, and Tunneling
Unless otherwise indicated, provide excavation by open cut except that sections of a trench may be jacked, bored, or tunneled if, in the opinion of the Contracting Officer, the pipe, cable, or duct can be safely and properly installed and backfill can be properly compacted in such sections.
3.1.4 Underground Utilities
The Contractor is responsible for movement of construction machinery and equipment over pipes and utilities during construction. Perform work adjacent to utilities as indicated in accordance with procedures outlined by utility provider. For work immediately adjacent to or for excavations exposing a utility or other buried obstruction, excavate by hand. Start hand excavation on each side of the indicated obstruction and continue until the obstruction is uncovered or until clearance for the new grade is assured. Support uncovered lines or other existing work affected by the contract excavation until approval for backfill is granted by the Contracting Officer. Report damage to utility lines or subsurface construction immediately to the Contracting Officer.
3.1.5 Structural Excavation
Ensure that footing subgrades have been inspected and approved by the Contracting Officer prior to concrete placement.
3.2 SELECTION OF BORROW MATERIAL
Select borrow material to meet the requirements and conditions of the particular fill or embankment for which it is to be used. Obtain borrow material from approved private sources. Unless otherwise provided in the contract, the Contractor is responsible for obtaining the right to procure
SECTION 31 00 00R Page 7 material, pay royalties and other charges involved, and bear the expense of developing the sources, including rights-of-way for hauling from the owners.
Unless specifically provided, do not obtain borrow within the limits of the project site without prior written approval. Consider necessary clearing, grubbing, and satisfactory drainage of borrow pits and the disposal of debris thereon related operations to the borrow excavation.
3.3 SHORING
3.3.1 General Requirements
Finish shoring, including sheet piling, and install as necessary to protect workmen, banks, adjacent paving, structures, and utilities. Remove shoring, bracing, and sheeting as excavations are backfilled, in a manner to prevent caving.
3.4 FINAL GRADE OF SURFACES TO SUPPORT CONCRETE
Do not excavate to final grade until just before concrete is to be placed.
Roughen the level surfaces, and cut the sloped surfaces, as indicated, into rough steps or benches to provide a satisfactory bond. Protect all surfaces from erosion resulting from ponding or water flow.
3.5 GROUND SURFACE PREPARATION
3.5.1 General Requirements
Remove and replace unsatisfactory material with satisfactory materials, as directed by the Contracting Officer, in surfaces to receive fill or in excavated areas. Scarify the surface to a depth of 6 inches before the fill is started. Plow, step, bench, or break up sloped surfaces steeper than 1 vertical to 4 horizontal so that the fill material will bond with the existing material. When subgrades are less than the specified density, break up the ground surface to a minimum depth of 6 inches, pulverizing, and compacting to the specified density. When the subgrade is part fill and part excavation or natural ground, scarify the excavated or natural ground portion to a depth of 12 inches and compact it as specified for the adjacent fill.
3.5.2 Frozen Material
Do not place material on surfaces that are muddy, frozen, or contain frost. Finish compaction by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, or other approved equipment well suited to the soil being compacted. Moisten material as necessary to provide the moisture content that will readily facilitate obtaining the specified compaction with the equipment used.
3.6 UTILIZATION OF EXCAVATED SOILS
3.6.1 Soil Reuse
Satisfactory materials may be re-used on the job site. Unsatisfactory materials shall be disposed off-site in a legal manner and replaced with satisfactory borrow materials.
SECTION 31 00 00R Page 8
3.7 BURIED TAPE AND DETECTION WIRE
3.7.1 Buried Warning and Identification Tape
Provide buried utility lines with utility identification tape. Bury tape 12 inches below finished grade; under pavements and slabs, bury tape 6 inches below top of subgrade.
3.7.2 Buried Detection Wire
Bury detection wire directly above non-metallic piping at a distance not to exceed 12 inches above the top of pipe. Extend the wire continuously and unbroken, from manhole to manhole. Terminate the ends of the wire inside the manholes at each end of the pipe, with a minimum of 3 feet of wire, coiled, remaining accessible in each manhole. Furnish insulated wire over it's entire length. Install wires at manholes between the top of the corbel and the frame, and extend up through the chimney seal between the frame and the chimney seal. For force mains, terminate the wire in the valve pit at the pump station end of the pipe.
3.8 BACKFILLING AND COMPACTION
Place backfill adjacent to any and all types of structures, and compact to at least 95 percent laboratory maximum density for cohesionless materials, to prevent wedging action or eccentric loading upon or against the structure. Prepare ground surface on which backfill is to be placed and provide compaction requirements for backfill materials in conformance with the applicable portions of paragraphs GROUND SURFACE PREPARATION. Finish compaction by pneumatic-tired rollers, steel-wheeled rollers, vibratory compactors, or other approved equipment.
3.8.1 Trench Backfill
Backfill trenches to the grade shown.
3.8.1.1 Replacement of Unyielding Material
Replace unyielding material removed from the bottom of the trench with select granular material or initial backfill material.
3.8.1.2 Replacement of Unstable Material
Replace unstable material removed from the bottom of the trench or excavation with select granular material placed in layers not exceeding 6 inches loose thickness.
3.8.1.3 Bedding and Initial Backfill
Place initial backfill material,(in compacted lifts of 8" or less for mechanical compaction and 4" or less for manual compaction), and compact it with approved tampers to a height of at least one foot above the utility pipe or conduit. Bring up the backfill evenly on both sides of the pipe for the full length of the pipe. Take care to ensure thorough compaction of the fill under the haunches of the pipe. Except as specified otherwise in the individual piping section, provide bedding for buried piping in accordance with AWWA C600, Type 4, except as specified herein. Compact backfill to top of pipe to 95 percent of ASTM D1557 maximum density.
Provide plastic piping with bedding to spring line of pipe. Provide materials as follows:
SECTION 31 00 00R Page 9
3.8.1.3.1 Class I
Angular, 0.25 to 1.5 inch, graded stone, including a number of fill materials that have regional significance such as coral, slag, cinders, crushed stone, and crushed shells.
3.8.1.3.2 Class II
Coarse sands and gravels with maximum particle size of 1.5 inch, including various graded sands and gravels containing small percentages of fines, generally granular and noncohesive, either wet or dry. Soil Types GW, GP, SW, and SP are included in this class as specified in ASTM D2487.
3.8.1.4 Final Backfill
Fill the remainder of the trench, except for special materials for roadways, railroads and airfields, with satisfactory material. Place backfill material and compact as follows:
3.8.1.4.1 Roadways
Place backfill up to the required elevation as specified. Do not permit water flooding or jetting methods of compaction.
3.8.2 Backfill for Appurtenances
After the manhole, catchbasin, inlet, or similar structure has been constructed and the concrete has been allowed to cure for 7 days, place backfill in such a manner that the structure is not be damaged by the shock of falling earth. Deposit the backfill material, compact it as specified for final backfill, and bring up the backfill evenly on all sides of the structure to prevent eccentric loading and excessive stress.
3.9 SPECIAL REQUIREMENTS
Special requirements for both excavation and backfill relating to the specific utilities are as follows:
3.9.1 Electrical Distribution System
Provide a minimum cover of 24 inches from the finished grade to direct burial cable and conduit or duct line, unless otherwise indicated.
3.9.2 Pipeline Casing
Provide new smooth wall steel pipeline casing under new existing pavement by the boring and jacking method of installation. Provide each new pipeline casing, where indicated and to the lengths and dimensions shown, complete and suitable for use with the new piped utility as indicated.
Install pipeline casing by dry boring and jacking method as follows:
3.9.2.1 Bore Holes
Mechanically bore holes and case through the soil with a cutting head on a continuous auger mounted inside the casing pipe. Weld lengths of pipe together in accordance with AWS D1.1/D1.1M . Do not use water or other fluids in connection with the boring operation.
SECTION 31 00 00 R Page 10
3.9.2.2 Cleaning
Clean inside of the pipeline casing of dirt, weld splatters, and other foreign matter which would interfere with insertion of the piped utilities by attaching a pipe cleaning plug to the boring rig and passing it through the pipe.
3.9.2.3 End Seals
After installation of piped utilities in pipeline casing, provide watertight end seals at each end of pipeline casing between pipeline casing and piping utilities.
3.10 SUBGRADE PREPARATION
3.10.1 Construction
Shape subgrade to line, grade, and cross section, and compact as specified. Include plowing, disking, and any moistening or aerating required to obtain specified compaction for this operation. Remove soft or otherwise unsatisfactory material and replace with satisfactory excavated material or other approved material as directed. Bring up low areas resulting from removal of unsatisfactory material to required grade with satisfactory materials, and shape the entire subgrade to line, grade, and cross section and compact as specified. The surface of the subgrade for roadways shall not show deviations greater than 1/2 inch when tested with a 12-foot straightedge applied both parallel and at right angles to the centerline of the area. Do not vary the elevation of the finish subgrade more than 0.05 foot from the established grade and cross section.
3.10.2 Compaction
Finish compaction by pneumatic-tired rollers, steel-wheeled rollers, vibratory compactors, or other approved equipment. Except for paved areas compact each layer of the embankment to at least 90 percent of laboratory maximum density.
3.10.2.1 Subgrade for Pavements and Building Pads
Compact subgrade for pavements and building pads to at least 98 percentage laboratory maximum density for the depth below the surface of the pavement shown. When more than one soil classification is present in the subgrade, thoroughly blend, reshape, and compact the top 12 inch of subgrade.
3.11 FINISHING
Finish the surface of excavations, and subgrades to a smooth and compact surface in accordance with the lines, grades, and cross sections or elevations shown. Provide the degree of finish for graded areas within 0.1 foot of the grades and elevations indicated except that the degree of finish for subgrades specified in paragraph SUBGRADE PREPARATION. Finish gutters and ditches in a manner that will result in effective drainage.
Finish the surface of areas to be turfed from settlement or washing to a smoothness suitable for the application of turfing materials. Repair graded, topsoiled, or backfilled areas prior to acceptance of the work, and re-established grades to the required elevations and slopes.
SECTION 31 00 00 R Page 11
3.11.1 Subgrade and Embankments
During construction, keep excavations shaped and drained. Maintain ditches and drains along subgrade to drain effectively at all times. Do not disturb the finished subgrade by traffic or other operation. Protect and maintain the finished subgrade in a satisfactory condition until ballast, subbase, base, or pavement is placed. Do not permit the storage or stockpiling of materials on the finished subgrade. Do not lay subbase, base course, ballast, or pavement until the subgrade has been checked and approved, and in no case place subbase, base, surfacing, pavement, or ballast on a muddy, spongy, or frozen subgrade.
3.11.2 Grading Around Structures
Construct areas within 5 feet outside of each building and structure line true-to-grade, shape to drain, and maintain free of trash and debris until final inspection has been completed and the work has been accepted.
3.12 TESTING
Perform testing by a Corps validated commercial testing laboratory or the Contractor's validated testing facility. Submit qualifications of the Corps validated commercial testing laboratory or the Contractor's validated testing facilities. If the Contractor elects to establish testing facilities, do not permit work requiring testing until the Contractor's facilities have been inspected, Corps validated and approved by the Contracting Officer.
a. Determine field in-place density in accordance with ASTM D1556 ASTM D2167 or ASTM D6938. When ASTM D6938 is used, check the calibration curves and adjust using only the sand cone method as described in ASTM D1556. ASTM D6938 results in a wet unit weight of soil in determining the moisture content of the soil when using this method.
b. Check the calibration curves furnished with the moisture gauges along with density calibration checks as described in ASTM D6938; check the calibration of both the density and moisture gauges at the beginning of a job on each different type of material encountered and at intervals as directed by the Contracting Officer. When test results indicate, as determined by the Contracting Officer, that compaction is not as specified, remove the material, replace and recompact to meet specification requirements.
c. Perform tests on recompacted areas to determine conformance with specification requirements. The following number of tests, if performed at the appropriate time, will be the minimum acceptable for each type operation.
3.12.1 Fill and Backfill Material Gradation
One test per 1000 cubic yards stockpiled or in-place source material. Test each visually different material separately. Determine gradation of fill and backfill material in accordance with ASTM C136 or ASTM D1140.
3.12.2 In-Place Densities
a. One test per 2500 square feet, or fraction thereof, of each lift of fill or backfill areas compacted by other than hand-operated machines.
SECTION 31 00 00 R Page 12
b. One test per 1000 square feet, or fraction thereof, of each lift of fill or backfill areas compacted by hand-operated machines.
c. Refer to Geotechnical Report for testing requirement within the limits of the building.
3.12.3 Check Tests on In-Place Densities
If ASTM D6938 is used, check in-place densities by ASTM D1556 as follows:
a. One check test per lift for each 5000 square feet, or fraction thereof, of each lift of fill or backfill compacted by other than hand-operated machines.
b. One check test per lift for each 2000 square feet, of fill or backfill areas compacted by hand-operated machines.
3.12.4 Moisture Contents
In the stockpile, excavation, or borrow areas, perform a minimum of two tests per day per type of material or source of material being placed during stable weather conditions. During unstable weather, perform tests as dictated by local conditions and approved by the Contracting Officer.
Determine soil moisture per ASTM D4944.
3.12.5 Optimum Moisture and Laboratory Maximum Density
Perform tests for each type material or source of material including borrow material to determine the optimum moisture and laboratory maximum density values per ASTM D1557. One representative test per 1000 cubic yards of fill and backfill, or when any change in material occurs which may affect the optimum moisture content or laboratory maximum density.
3.12.6 Tolerance Tests for Subgrades
Perform continuous checks on the degree of finish specified in paragraph SUBGRADE PREPARATION during construction of the subgrades.
3.12.7 Displacement of Sewers
After other required tests have been performed and the trench backfill compacted to 1, foot above the top of the pipe, inspect the pipe to determine whether significant displacement has occurred. Conduct this inspection in the presence of the Contracting Officer. Inspect pipe by shining a light or laser between manholes or manhole locations, or by the use of television cameras passed through the pipe. If, in the judgment of the Contracting Officer, the interior of the pipe shows poor alignment or any other defects that would cause improper functioning of the system, replace or repair the defects as directed at no additional cost to the Government.
3.13 DISPOSITION OF SURPLUS MATERIAL
Dispose surplus soil materials off government property in a legal manner.
-- End of Section --
SECTION 31 00 00 R Page 13
File details come from the government source that posted it. Updated .