This document provides a working time analysis for contract CP1031923 to repair and convert Building 91157 from a storage warehouse to a material testing laboratory and replace an existing lift station for the Department of the Air Force Special Operations Command. The analysis outlines a 120 calendar day performance period comprised of five items including mobilization, design submittal and review, securing materials and equipment and performing demolition and preparatory structural and electrical work to receive a hoist system, performing gravity sewer and lift station removal and replacement, and correcting punch list items. Allowable calendar days range from 5 days for mobilization to 59 days for performing gravity sewer and lift station removal and replacement.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WORKING TIME ANALYSIS
CP1031923 REPAIR – CONVERT BLDG 91157 FROM STORAGE WAREHOUSE TO
MATERIAL TESTING LAB + REPLACE EXISTING LIFT STATION
ITEM NO: DESCRIPTION ALLOWABLE CALENDAR DAYS
1. Mobilization 5
2. Design Submittal & Review Process 14
3. Secure Material/Equipment – Perform Demolition & 28 Structural/Electrical Preparatory Work to Receive Hoist System
4. Perform Gravity Sewer & Lift Station Removal & Replacement 59
5. Correct Punch List ltems 14
TOTAL ALLOWABLE CONTRACT TIME 120