01_10_10_Design_Requirements_24_Aug_15.docx
DOCX document 49 KB Posted
- Attached to
- Design/Build Mezzanine Bldg 90005 Federal contract opportunity
- Solicitation number
- FA4417-15-R-0041
About this file
01 10 10 Design Requirements 24 Aug 15
View the file
Other files for this federal contract opportunity
Show all 34
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DESIGN-BUILD FTEV 15-1077 Repair Mezzanine Bldg 90005 Hurlburt Field, Florida 35% Design Submittal – RFP Package
SECTION 01 10 10
DESIGN REQUIREMENTS
TABLE OF CONTENTS
1. DESCRIPTION OF FACILITY
2. DESIGN REQUIREMENTS
3. GENERAL REQUIREMENTS AND DEFINITIONS
4. PERMIT REQUIREMENTS
5. ANTI-TERRORISM FORCE PROTECTION REQUIREMENTS
6. SITEWORK and LANDSCAPING
7. NARRATIVES ON AREAS AND FUNCTIONAL REQUIREMENTS
8. ARCHITECTURAL DESIGN
9. INTERIOR DESIGN
10. STRUCTURAL DESIGN
11. HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
12. PLUMBING
13. FIRE SUPPRESSION
14. ELECTRICAL SYSTEMS
15. ELECTRONIC SYSTEMS
16. CORROSION CONTROL AND CATHODIC PROTECTION
17. ENVIRONMENTAL CONSIDERATIONS
SECTION 01 10 10
DESIGN REQUIREMENTS
1. DESCRIPTION OF FACILITY
1.1 The Contractor shall design and construct FTEV 15-1077 Repair Mezzanine Bldg 90005 at Hurlburt Field to result in a complete and usable facility based on Design Requirements and Technical Specifications contained within this solicitation.
1.2 This project is required to provide a renovation of an approximately 5,000 sq ft area on a second floor mezzanine located in Building 90005. The renovation project will include installation new flooring, modular furniture, electrical power circuits, and communication conduits. The existing break area and male/female rest rooms will also be completely gutted and renovated. A new passenger elevator will also be installed replacing a freight elevator. Demolition of existing freight elevator, communication cable trays/cables, electrical circuits, furniture, portion of wall, and carpet is also required. The Contractor shall design and construct these facilities in accordance with the design requirements and technical criteria established in this document.
1.2.1 Base Bid. The Base Bid includes design and construction of all work required for the project except for the elevator. The Base Bid includes required demolition of existing features as shown on the site plans or required for construction of the Base Bid. The Base Bid includes the design of all Bid Options.
1.2.2 Bid Option Number 1 includes the removal of an existing freight elevator and installation of a new elevator to include facility and electrical upgrades.
1.2.3 Bid Option Number 2 includes the purchase, installation and testing of “data walls” in the locations shown on the drawings.
2. DESIGN REQUIREMENTS
2.1 The information provided in this Request for Proposal (RFP) is intended to guide design and construction by establishing existing conditions and desired character, appearance, and function of the project. The criteria drawings have been coordinated with and approved by the using agency. Minor modifications will be allowed in the criteria drawings consistent with meeting required space and functional requirements.
2.2 The Contractor shall prepare complete construction documents for all work designed as required by the RFP. The construction documents to be prepared include, but are not limited to construction drawings, specifications, submittals, and design analysis as required in SECTION 01 10 12 DESIGN AFTER AWARD. The project shall be designed and constructed in accordance with the criteria contained in the RFP using industry standard materials and efficient practices. The building design and the materials selected shall be high quality, durable and easily maintained. The Contractor shall be responsible for the professional quality, code compliance, technical accuracy and coordination of all designs, drawings, specifications and other documents or publications upon which the design and construction are based. The design and construction of this facility shall conform to the drawings, specifications and design requirements issued in this solicitation. In case of a conflict in design requirements, the most stringent requirements govern.
2.2.1 Hurlburt Standard Specification and Unified Facility Guide Specifications (UFGS) are referenced in various sections below. When Hurlburt Standard Specifications are unavailable, UFGS shall be utilized. The referenced specifications shall be edited by the Contractor and provided as submittals at the stages shown in Section 01 10 12. The referenced specifications are anticipated requirements - specifications shall be deleted and/or additional specifications shall be added by the Contractor as necessary to complete the design. As a minimum, the specifications for this project are expected to include the sections listed in Appendix A – Projected Hurlburt Specifications. The full collection of Hurlburt Standard Specification are located in Appendix B.
2.2.2 Operations and maintenance (O&M) portions of the specifications shall be edited by the respective Designers of Record in the design phase. O&M requirements and submittals in the specifications shall not be edited out. Submittals, operating procedures, schematics, as-built drawings, manuals, software, and computer hardware required for system operation incorporated in the design phase are critical to operation of the new facility on completion.
2.3 The intent of this RFP is to describe the requirements for appearance, function, and equipment, materials, and types of construction in sufficient detail to enable design and engineering to be completed by the Contractor.
2.4 All design and construction document drawings and specifications shall be prepared to comply with the RFP. The RFP describes the design work that shall not be changed, and shall be included in the construction documents. All remaining design work shall be performed by the Contractor based on the design criteria as required by the RFP. No deviations from the criteria will be allowed unless prior approval is obtained from the COR. All questions or problems encountered by the Contractor in the following criteria shall be promptly submitted with recommendations to the Contracting Officer's Representative (COR) for approval.
2.4.1 Section 01 10 10 - DESIGN REQUIREMENTS defines the design and performance requirements. Applicable building codes and standards shall be used as the minimum criteria to develop the construction documents for areas of work not specifically defined.
2.4.2 Section 01 10 12 - DESIGN AFTER AWARD defines the format and submittal requirements in which the design and the construction documents shall be prepared by the Contractor.
2.5 Construction documents shall be sufficient to afford a clear understanding of the construction work required. The work shall be organized in a manner that will assure thorough coordination between the various details on the drawings, and between the drawings and the specifications. The Contractor shall cross-check all work until all conflicts have been reconciled.
2.6 Conflicts in RFP Criteria. Where the various elements of the RFP are in conflict, the following priority shall be used to establish precedence, unless specifically noted otherwise:
1. Section 01 10 10 - DESIGN REQUIREMENTS
2. Criteria Drawings
2.7 The architectural character of the building, interior design, siting, and landscaping shall be consistent with the [installation design guide and/or other references.
2.8 The Contractor's Designers of Record shall develop construction document technical specifications for all areas of work. The design of architectural, interior, structural, mechanical, fire protection, electrical, environmental, civil, and other engineering features of the work shall be accomplished, reviewed, and approved by architects, engineers, and interior designers registered to practice in their respective professional fields in a State or possession of the United States, in Puerto Rico, or in the District of Columbia.
3. GENERAL REQUIREMENTS AND DEFINITIONS
3.1 Proposed Construction Description
3.1.1 Demolition
3.1.1.1 Communication systems demolition
Contractor shall remove and dispose of existing communication cable trays and cable along the walls and suspended from the ceiling. Remove associated rods and hardware attached to roof joints. Cables will be removed back to equipment racks located in the rooms. Replace ceiling tiles with holes from removal of cable tray and any damage caused by removal process. Patch and paint walls to match existing finishes to include sealing wall penetrations. Contractor to remove associated wall mounted equipment and turn over to government.
3.1.1.2 Electrical system demolition
Contractor shall remove and dispose of all conduit and wire associated with electrical power feeds from the UPS to existing furniture. Walls will be patched and ceiling tiles replaced affected by the removal of the electrical system. Existing breakers in the UPS units shall remain.
3.1.1.3 Wall demolition
Contractor shall remove and dispose of approximately 40’ of non-load bearing wall in center of room. Floors, remaining walls and suspended ceiling shall be repaired to create a consistent look.
3.1.1.4 Furniture removal
Contractor shall remove and dispose of existing furniture including, but not limited to, desks, chairs, and low walls between desks.
3.1.1.5 Carpet demolition
Contractor shall remove and dispose of existing carpet tile where the new raised floor will be installed and the break area will be renovated.
3.1.1.6 Restroom demolition
Contractor shall remove and dispose of existing urinals, water closets, toilet partitions, lavatories, cabinets, toilet accessories, and finishes from existing men’s and women’s restrooms for new men’s and women’s restrooms renovation.
3.1.1.7 Other demolition
Contractor shall accomplish all other demolition required to complete the project.
3.1.2 Construction
3.1.2.1 Raised floor
Contractor shall purchase and install low profile access flooring meeting Hurlburt Standard Specification 09 69 00. Installation shall include the unipanel, sound attenuation blanket, base connectors, supports, caps, edge trims, ramps and all other pieces to create a full finished flooring system.
Contractor shall install a higher raised floor where the six WOC desks are located. The higher raised floor will be raised an additional 6 inches above room floor level. The construction may require a different elevated flooring material than the rest of the room. The floor shall include a trim around the structure to enclose the elevated section.
3.1.2.2 Furniture
Contractor shall purchase and install 100 six foot wide, 30 inch deep desks with chairs as shown on the attached final layout drawing. The chairs basis of design shall be “Herman Miller Aeron Chair Basic Carbon.” The desks shall be 72” wide and 32” deep with laminate work surface, concealed power/data cable tray with power/data mounting board, cable access cover, and slat wall back panel with 12” wide laminate top cap similar to Wall Street Trading Desk model “Linear Desk – Slatwall” or approved equal. Desks must be compatible with existing monitor stands. Include end panels on row ends (approximately 46). A basis of design has been included Attachment A.
3.1.2.3 Electric power
The expected maximum electrical load at each desk will support two desktop computers, four monitors, two telephones, and two fiber optic converter boxes (approximately 2000 watts). Contractor shall install four 4-outlet 120V electrical outlet boxes at each desk location. It is anticipated that one 20 amp circuit will be required per desk. Electrical circuits shall be fed from existing UPS 20 amp circuit breakers. The existing UPS equipment includes a Liebert Model PPA150C and Liebert Model PPA075C each with 84 twenty amp breakers to be used to feed the desk circuits. All circuits shall run concealed under the floor through the raised floor trenches and up through the furniture back walls into the furniture cable trays. Circuits may be run concealed through walls and/or above ceilings as required. Power poles running from ceiling to furniture is not allowed. All electric boxes and outlets shall be labelled to show source of power (breaker number and UPS).
3.1.2.4 Communications
The Government will install fiber optic cables running from each desk to a fiber optic patch panel located as shown on drawing. All fiber optic cables will run concealed under the floor through the raised floor trenches and up through the furniture back walls into the furniture cable trays. Circuits may be run concealed through walls and/or above ceilings as required, but power poles running from ceiling to furniture is not allowed. The contractor will include a time in the construction schedule and access to the construction site to allow the government to install the fiber optic cable after the raised floor is installed, but before the carpet and furniture is installed.
The contractor shall install a 4” PVC conduit from fiber patch panel to NIPRNET server room on 1st floor. The contractor shall also install a fully exposed 4” sealed PDS conduit from the patch panel to the SIPRNET connection on the first floor. A 2” sealed PDS conduit shall be installed from the fiber patch panels to the rear mezzanine computer room. The approximate locations of the runs are shown on the drawings. PDS (Protective Distribution System) conduit shall be designed and installed in accordance with UFGS (Unified Facilities Guide Specifications) Section 27 05 29.00 10.
3.1.2.5 Carpet
Contractor shall install new carpet tile and cove base on new raised floor.
3.1.2.6 Bathrooms and Break Area
Contractor shall renovate existing male and female bathrooms. Existing male bathroom will be expanded into female bathroom space. New male bathroom will have three toilets (one handicap accessible), four urinals, and three sinks. New female bathroom will have two toilets (one handicap accessible) and two sinks. Restrooms must provide accessible plumbing fixtures and routes IAW ABA Standards for Federal Facilities. Demolition will completely remove all fixtures, partitions, wall tile, floor tile and drywall. Contractor is responsible for disposal of all material. New construction includes, but is not limited to, new fire rated drywall, 12”x12” ceramic floor tile with epoxy grout, toilet room accessories, mirrors, countertops, sinks, automated faucets, automated fixtures, partitions, lights, exhaust fans, and paint. Replace existing doors with handicap accessible doors.
The contractor shall also construct a new break area. Construct an approximately 21’ long wall, with 8 foot perpendicular walls at the location shown on the drawing to be used as a data display wall. The wall shall run from the concrete floor to above the suspended ceiling. The wall shall be structurally braced from the roof joints. Four electric outlets shall be installed to accommodate future large screen monitors.
Provide a snack bar, 12 foot long base cabinet with solid surface counter top with 4” high backsplash and double compartment stainless steel sink and overhead cabinet. Provide an accessible water cooler in this area. Electrical circuits for the new 240V popcorn machine, microwave oven, refrigerator, and other appliances shall be installed along the snack bar wall. The flooring in the break area shall be 12”x12” ceramic floor tile.
Tankless water heaters shall be used for the hot water.
3.1.2.7 Raise Ceiling and Create Data Wall
Contractor shall raise an area of approximately 60’ x 40’ of the suspended ceiling system at a height to accommodate user audio/visual data wall. Existing equipment and fixtures currently in the ceiling including, but not limited to, light fixtures, speakers, HVAC registers and fire protection system will need to be raised along with the ceiling. There is a large HVAC distribution duct above the ceiling near the wall and the construction effort is not intended to disturb this large duct. The height of the ceiling can be adjusted as needed in order to avoid this duct. The existing wall will need to be refinished where the ceiling was previously.
The wall used to support the data wall will be evaluated and strengthened or height increased if needed. Additional outlets for 12 large monitors supporting the data wall shall also be installed.
3.1.2.8 Enclose Multi-purpose room
Contractor shall construct walls to completely enclose the Multi-purpose room. The walls shall run from the concrete floor to above the suspended ceiling. The walls shall be structurally braced from the roof joists. Fire alarms systems and sprinkler head layouts shall be redesigned for the addition of the wall. Reconfigure the existing HVAC supply to meet new heat load calculations for the room and adjust airflow as required. Two 6’ wide by 3’ high sliding windows/doors shall be installed in the longer wall. Each window shall slide open to allow verbal communications between the two rooms when opened.
3.1.2.9 OPTION 1: New Elevator
Contractor shall design and install a new passenger elevator, replacing the existing freight elevator. The existing freight elevator shall be removed and disposed of by the contractor. The elevator shaft shall be modified to meet current code. Electric power shall be modified as necessary for the new elevator. A new secure access door and security hardware shall be installed on the first floor to control access to the elevator. The basis of design for the elevator shall be an “Otis HydroFit Machine-Roomless, Low Rise Holeless Hydraulic.”
3.1.2.10 OPTION 2: Data Walls
Contractor shall design and install four “data walls” in the locations indicated on the plans. Each data wall shall consist of four (4) 55” monitors capable of utilizing at least 6 video feeds with the ability to configure the display utilizing a 10” touchscreen panel. The 10" touch screen controller must be a wired model such as Crestron TSW-1052 (or approved equal). The data wall system shall be complete and usable system including all necessary components capable of utilizing at least 6 video feeds on the four data walls. Each of the 4 data walls shall be in dependently capable of displaying any or all of the 6 video feeds. The 6 video feeds will originate from a location yet to be determined along the wall with the 3 data walls. The location of the feeds will be finalized during the completion of the design. The AV Cabinet location has not yet been determined. It is expected to be along the wall with the 3 data walls. Audio capability shall be provided an amplifier such as Crestron AMO-3210T (or approved equal) with at least 12 two-way in ceiling white speakers spaced throughout rooms 212 and 211. A basis of design has been included in Attachment B.
A one-year on-site maintenance and emergency service contract shall be included.
3.2 General Construction Requirements
3.2.1 Government Furnished Contractor Installed Equipment (GFCI) is NONE.
3.2.2 Contractor Furnished Contractor Installed Equipment (CFCI) is as shown on the criteria plans.
3.2.3 Staging Area. The construction routes and potential Contractor staging areas are depicted on the Base Location and Vicinity Map.
3.2.4 Project Site Access. Access to the site is depicted on the Base Location and Vicinity Map.
3.2.5 Borrow and Spoil Areas. Not required.
3.2.6 Furniture, Fixtures and Equipment (FFE).
Provide a furniture plan to include furniture specifications, configurations, and layouts.
3.3 Definitions of Terms
The following frequently used terms are defined hereinafter to establish a common understanding when the term is used in this solicitation.
3.3.1 Net Area (occupiable area): The gross square feet less building infrastructure and support members such as exterior walls, electrical and communications spaces, mechanical spaces, fixed corridors, restrooms, stairwells, janitor closets, vestibules, etc. Covered walks, enclosed walkways, terraces, balconies and patios shall not be counted as net area. Net area is the physical space, which is available for use by the occupant to support the occupant's mission.
3.3.2 Gross Area: All floor area measured from the outer surface of the exterior wall to the outer surface of the exterior wall. Covered (but not enclosed) loading docks, walks, terraces, porte-cocheres, balconies and patios shall be counted as one-half of the total square feet. Uncovered walks, terraces, balconies and patios shall not be counted.
4. PERMIT REQUIREMENTS
4.1 Permits. No environmental permits are expected to be required.
5. ANTI-TERRORISM FORCE PROTECTION REQUIREMENTS
5.1 Not required.
6. SITEWORK
6.1 Not required.
7. NARRATIVES ON AREAS AND FUNCTIONAL REQUIREMENTS
7.1 The paragraphs in this section are included to aid the Contractor in understanding the requirements all the functional areas within the project. To aid in the design, the net square footage totals shown on the criteria drawings, and general functional requirements given below shall be fully coordinated. All materials and equipment are Contractor Furnished and Contractor Installed (CFCI) unless otherwise indicated. General types of furnishings and equipment for each room are shown in the concept drawings to assist in establishing anticipated individual room areas.
7.2 Second Floor Mezzanine, Building 90005. The second floor mezzanine area is classified as an open storage area for Secret information. The design and renovation of the mezzanine will need to incorporate security requirements to maintain this level of security. The construction area will be cleared of all classified material during the construction time frame, so no security clearances or escorts will be required during this period.
8. ARCHITECTURAL DESIGN
8.1 Architectural Theme. There is no architectural theme for this project.
8.2 Codes and References.
Hurlburt Standard Specifications, UGFS Specifications, and International Building Code
8.3 Life Safety Code Analysis. AS required by UFC 3-600-01.
8.5 Materials and Details
8.5.1 Exterior – no exterior work
8.5.2 Interior
8.5.2.1 Partitions. Standard interior construction. Some walls will require additional structural support for loads.
8.5.2.2 Flooring. Raised flooring and carpet tile.
8.5.2.3 Ceilings. New and repair/patch to match existing.
8.5.2.4 Doors. Solid core wood in hollow metal frames.
8.5.2.5 Windows. Interior operable interior window.
8.5.2.6 Finish Hardware. Manufacturer’s standard, heavy duty hardware.
8.5.2.7 Accessories. Restroom does not require soap or hand towels dispensers. To be installed by Government after construction.
8.5.2.8 Cabinetry. Break Area and restrooms to have plastic laminate clad wood with solid surface countertops.
8.5.2.10 Elevator. The new elevator shall meet ADA requirements.
9. INTERIOR DESIGN
9.1 Structural Interior Design (SID). The SID includes the selection and sampling of all applied finishes to complete the building exterior and interior architectural features.
9.1.1 Design Requirements. The Contractor shall use this criteria and the drawings for the development of the SID interior finishes, materials, and colors. The SID submittals shall run concurrent with the architectural submittal. The Contractor shall update the color boards and the UFGS to reflect any of the Government comments or discontinued manufacturer colors indicated. The SID finishes accepted at the Final design phase (defined in Section 01 10 12) shall be the SID finishes installed during the construction phase of the project.
9.1.2 SID Room Finish Narrative. Each interior space shall be finished in accordance with this narrative. This narrative provides initial guidance only. As the design becomes more defined after award of the contract, the Contractor shall provide a comprehensive room finish schedule.
9.1.2.3 Signage and Visual Communication Boards. Restroom signs are required.
9.1.2.4 Color Schedule. Product and color are shown as being specific to one manufacturer to establish design intent. An equivalent product and color by another manufacturer may be submitted for approval. Manufacturers and materials specified are not intended to limit the selection of equivalent products and colors from other manufacturers.
9.1.2.4.1 Interior Floor Finishes
9.1.2.4.1.1 Open area shall be raised floor with carpet tile. Bathroom shall be ceramic tile.
9.1.2.4.3 Interior Wall Finishes
9.1.2.4.3.1 Paint walls in open area to match existing. Paint walls in bathroom to match open area.
9.1.2.4.4 Interior Ceiling Finishes
9.1.2.4.4.1 Existing suspended ceiling shall be left in place. Repair ceiling tiles and grid from efforts to remove existing electrical poles and communication trays. Approximately 20% of the ceiling needs to be re-leveled. The ceiling in the bathrooms shall be moisture resistant gypsum board.
9.1.2.4.5 Interior Trim Finishes - NONE
9.1.2.4.6 Interior Window Treatment - NONE
9.1.2.4.7 Interior Miscellaneous Finishes
9.1.2.4.7.1 The bathroom shall include toilet partitions, urinal screens, and solid surface countertops. The break area shall include solid surface countertops.
9.2 Not used
9.3 Furniture, Fixtures and Equipment (FFE). The Contractor is responsible for developing a FFE package which is the furniture and equipment package based on guidance and customer [point of contact] in the Base Bid. The Contractor shall show a line drawing of the furniture specified. Provide critical dimensions on the floor plan to verify the specified furniture and equipment fit within the design.
9.3.1 Procurement and Installation. Procurement and installation of the all moveable furnishings designed under the base price proposal shall be purchased by the Contractor and installed within the specified construction contract completion date for the building.
9.3.2 Supplies/Services to be Obtained. The products required include all furniture and furnishings needed to provide a fully integrated, fully operational, complete and useable facility upon the beneficial completion date of the contract. The services required include all effort associated with ordering, receiving, storing, staging, installing, adjustments/leveling, trash removal/disposal, and touch-ups and/or repair or replacement of damaged furniture or their components (either in part or whole) and/or repair or replacement of damaged building surfaces.
9.3.3 Estimated Value. Not Used.
10. STRUCTURAL DESIGN
10.1 Codes and References.
Hurlburt Standard Specifications, UGFS Specifications, and International Building Code.
10.2 General Design Requirements
10.2.1 Structural design is anticipated to be limited to reinforcing walls for the installation of monitors.
11. HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
11.1 Codes and References.
Hurlburt Standard Specifications, UGFS Specifications, and International Building Code.
11.2 Design.
11.2.8 Hot Water System. Tankless hot water systems shall be used for the bathrooms.
11.2.9 Exhaust System(s). A new bathroom exhaust system shall be installed
11.2.11 Piping systems.
No changes required.
11.2.12 Diffusers, Registers, Grilles, and Louvers.
Utilize existing and provide new as needed.
11.2.15 Testing, Adjusting, and Balancing (TAB).
Rebalance as needed.
11.2.16 Controls. Relocate thermostats if required.
12. PLUMBING
12.1 Codes and References.
Hurlburt Standard Specifications, UGFS Specifications, and International Building Code.
12.2 Plumbing Design Criteria. Plumbing system shall be designed and installed in accordance with the Specifications. Modify water and sewer piping as needed.
12.1.1 Domestic Hot Water. Tankless hot water systems shall be used for the bathrooms.
12.2.2 Gas Connections. Not required.
12.2.4 Plumbing Fixtures. New toilets, urinals, sinks, and faucets shall be installed.
13. FIRE SUPPRESSION
13.1 Codes and References.
Hurlburt Standard Specifications, UGFS Specifications, and International Building Code.
13.2 General.
Provide a fire detection/suppression system for each facility that meets OSHA regulations, NFPA codes and UFC 3-600-01. Relocation of existing heads and installation of new heads may be required due to wall construction/relocation.
13.3 Equipment
13.3.1 Fire extinguisher cabinets. Utilize existing.
13.4 Drawings.
Detail drawings shall conform to the requirements established for working plans as prescribed in NFPA 13. All contract requirements that exceed the minimum requirements of NFPA 13 shall be incorporated into the design.
14. ELECTRICAL SYSTEMS
14.1 Codes and References.
Hurlburt Standard Specifications, UGFS Specifications, and International Building Code.
14.2 Exterior Electrical Requirements – No exterior electrical work is required.
14.3 Electrical Interior. New electrical circuits shall be run from the existing UPS units to the desks.
14.4 Lighting Fixtures. Lighting in the open area is not expected to change. Lighting in the bathrooms shall be new.
15. ELECTRONIC SYSTEMS
15.1 Codes and References.
Hurlburt Standard Specifications, UGFS Specifications, and International Building Code.
15.2 Exterior Electronic Systems. No exterior electronic work required.
15.3 Interior Electronic Systems:
15.3.1 Fire Detection and Alarm System. System may need to be modified to enclose Multi-Purpose room and install of new walls.
15.4 Telephone and LAN Systems(Interior). Telephone and LAN cables to desks shall be installed by the government and will be coordinated with the construction contractor.
15.5 Cable Television. NONE
15.6 Mass Notification System. System may need to be modified to enclose Multi-Purpose room and install of new walls.
15.7 Electronic Entry System. No work required.
15.8 Intrusion Detection System. Installation of the new elevator may require modificaitons to the Intrusion Detection System.
16. CORROSION CONTROL AND CATHODIC PROTECTION - NONE
17. ENVIRONMENTAL CONSIDERATIONS
17.1 Codes and References.
Hurlburt Standard Specifications, UGFS Specifications, and International Building Code.
17.2 Environmental Protection. NONE
17.3 Existing Hazardous Materials. NONE
17.4 Installation Restoration Program. Not applicable.
17.5 Hazardous Materials. See Hurlburt Specifications.
17.6 Contractor Generated Hazardous Waste. See Hurlburt Specifications.
17.7 Asbestos Materials and Lead Based Paints. None known. Testing is not required.
--End of Section-- SECTION 01 10 10 (updated 24 Aug 15) Page 7