12-RFI_Answer_Log_10-15-19.pdf

PDF 80 KB Posted

Attached to
FY19 Multiple Award Paving Contract (MAPC) Federal contract opportunity
Solicitation number
FA440719R0002
Issued by
Department of the Air Force Air Mobility Command

About this file

This document contains responses to requests for information (RFIs) regarding solicitation number FA440719R0002, the FY19 Multiple Award Paving Contract (MAPC) opportunity issued by the Department of the Air Force Air Mobility Command. The RFI responses clarify that past performance information sheets are due on October 18, 2019 by 10:00 am local time and should be included in Volume 2 of proposals. Responses also provide guidance that if proposing an additive, alternative, or betterment, offerors should provide a brief description on column 0002AA of the price schedule and may reference a supporting attachment. The document advises that all other solicitation requirements remain unchanged.

12- RFI Answer Log 10-15-19

View the file

Other files for this federal contract opportunity

Other files attached to FY19 Multiple Award Paving Contract (MAPC), newest first.
File Type Posted
09G-_SG1420_Security_Gate_O&M_Manual.pdf PDF
09-_SOW_Sample_Project_v2.pdf PDF
09A-_Map-Repair,_Reconstruct_Symington_Dr-McClelland_St_v2.pdf PDF
09E-_Price_Schedule_v2.pdf PDF
Solicitation_Amendment_FA440719RA0020002_SF_30.pdf PDF
09F-_Electrical_SOW.pdf PDF
Solicitation_Amendment_-_FA440719RA0020002.pdf PDF
12-_RFI_Answer_Log_v2_10-30-19.pdf PDF
10-PPI_v2.pdf PDF
01-1442_Continuation_Sheet_Final_v2.pdf PDF
Solicitation_Amendment_FA440719RA0020001.pdf PDF
09B-_Map_Stormwater_North.pdf PDF
09A-_Map-Repair,_Reconstruct_Symington_Dr-McClelland_St.pdf PDF
06-SAFB_Climatic_Data.pdf PDF
08-TO_Procedures_Final.pdf PDF
01-1442_Continuation_Sheet_Final.pdf PDF
09E-_Price_Schedule_Final.pdf PDF
09-_SOW_Sample_Project_Final.pdf PDF
09C-_Urban_Forest_Mgt_Plan_2010_pg_24-25.pdf PDF
Solicitation_-_FA440719RA002.pdf PDF
05-SAFB_Map.pdf PDF
02-MAPC_Gen_Rqmts_Final.pdf PDF
11-PPQ.pdf PDF
03_-_IL20190017_WDOL_Heavy_and_Highway.pdf PDF
04-NAF_General_Procedures.pdf PDF
09D-_Map_Stormwater_South.pdf PDF
10-PPI.pdf PDF
FBO_-_Pre-solicitation_Notice.pdf PDF
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI # Date Recv'd Date Sent to CES RFI Response

Date Answered

1 10-Oct-19 Attachment 01, Continuation Sheet, states the PPI is due on 18 October but references attachment 11.

This has been corrected. The PPI is due on 18 October, however in order to not confuse anyone with attachments we have changed to reflect the document named (10-PPI).

10-Oct-19

2 10-Oct-19 Past Performance Information sheet referenceces technical subfactors under letter H but there are no technical factors/subfactors in section M

"For each of the applicable sub-factors under the Technical factor in Section M, illustrate how your experience on this program applies to that sub-factor." which was previously H. on the PPI has been removed.

10-Oct-19

3 10-Oct-19 Past Performance Information sheet under letter I. is not clear on whether or not it is referencing the past project or the sample project.

Previously labled I. on the PPI, which is now labeled as H, has been updated to reflect the information to be provided.

10-Oct-19

4 10-Oct-19 Past Performance Information sheet under letter J. is not clear on whether or not it is referencing the past project or the sample project.

Previously labled J. on the PPI, which is now labeled as I., has been updated to reflect the information to be provided.

10-Oct-19

5 10-Oct-19 Since no work plan is to be provided, how should a proposed Additive, Alternative, or Betterment be reported

If chosing to propose a additive, alternative, or betterment, please supply a brief description on column 0002AA of the price schedule.

With this you may also reference an attachment in your proposal where you may supply more detail.

10-Oct-19

6 15-Oct-19

Document 01 – 1442 Continuation Sheet Final indicates that Past Performance Information Sheets in accordance with Section L are to be submitted no later than 10/18/19 at 10am local time. Section L also indicates the Past Performance Information Sheets are to be included in

Volume 2 of the proposal.

Past Performance Information Sheets are to be submitted on 18 Oct at the time listed in document 01. They also should be included in again in Volume 2 of the proposal in accordance with section L.

15-Oct-19

7 15-Oct-19

Please clarify if the Past Performance Information Sheets need to be submitted on 10/18/19 before 10am or if they can be submitted with the full proposal by 11/4/19 at 3:30 pm per

SF1442. If they are to be submitted by 10/18/19 do we submit them again as part of our full submittal by 11/4/19?

See response to RFI #1.

15-Oct-19