RFI B155 Roofing Questions_Answers.docx

DOCX document 16 KB Posted

Attached to
Repair LRS Hazmat Roof, B155
Solicitation number
FA302226R0014
Issued by

About this file

This is a Questions and Answers document responding to inquiries submitted during the Request for Information (RFI) phase of solicitation FA302226R0014 for roof repair and replacement at Building 155 (B155) operated by the Department of the Air Force Air Education and Training Command.

The document addresses five contractor questions regarding site visit activities, existing roof composition assumptions, and access to architectural drawings. The government clarified that no destructive testing or core cuts of the existing roof system are permitted prior to contract award. Regarding existing roof composition, contractors should assume a minimum of 5 inches of rigid insulation, a plywood or concrete board cover board, and a vapor barrier for demolition planning purposes. All architectural drawings and related documentation, including demolition and new roof plans, are located in "Attachment 2 - SOW Attachments.pdf" in SAM.gov. To access these controlled unclassified information (CUI) documents, contractors must complete CUI training slides and return a signed CUI Acknowledgment form to the Point of Contact; access will be granted upon government review of the signed acknowledgment. This Q&A document serves as clarification for the larger solicitation requiring design and replacement of the building's roof with a TPO single ply membrane roofing system, replacement of overhangs, installation of insulation meeting ASHRAE requirements, and gutter systems, with the extended RFI due date of 17 June 2026 and proposal due date of 26 June 2026.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. We would like to know whether it will be possible for our site visit attendees to conduct a core cut of the existing roof system.

No destructive testing prior to award

2. whether an existing roof composition (roof layers and decking) is already available.

Assume the existing roof has at minimum 5” of rigid insulation, a plywood or concrete board cover board, and some sort of vapor barrier for demolition.

3. Does the government have any existing drawings of the building and roof structure?

The drawings are in “Attachment 2 - SOW Attachments.pdf” in SAM.gov to obtain access, please complete CUI training slides and return the CUI Acknowledgment form first. Once we receive the signed acknowledgment, we will grant you access to the drawings.

4. Can the Government provide these drawings?

The drawings are in “Attachment 2 - SOW Attachments.pdf” in SAM.gov to obtain access, please complete CUI training slides and return the CUI Acknowledgment form first. Once we receive the signed acknowledgment, we will grant you access to the drawings.

5. I don’t see the architectural drawings for demo and the new roof. Am I just not looking in the right spot?

The drawings are in “Attachment 2 - SOW Attachments.pdf” in SAM.gov to obtain access, please complete CUI training slides and return the CUI Acknowledgment form first. Once we receive the signed acknowledgment, we will grant you access to the drawings.