This is a pricing template file (Form 66.xlsx) associated with a roof replacement solicitation for Building 155 at an Air Force facility. The file itself is a spreadsheet template and does not contain substantive information about required products or services beyond serving as the pricing submission format for this opportunity.

The related solicitation (FA302226R0014) requires contractors to provide complete design and replacement of the roof for Building 155, including replacement of roof overhangs covering the exhaust louver on the rear and the entrance/roll-up door on the front. The scope encompasses all plant, labor, equipment, transportation, and tools necessary to eliminate weather-borne water leaks, remove ponding, and meet ASHRAE insulation zoning requirements. The new roof system must be TPO single-ply membrane with replacement of built-up roof components down to decking, insulation, gutter system with downspouts, roof curbing, and roof coping. A mandatory site visit is scheduled for June 2, 2026 at 9:00 AM CST, with registration required by May 26, 2026. Contractors must complete CUI (Controlled Unclassified Information) training and submit signed acknowledgment forms to gain access to drawings and associated documentation. The solicitation is issued by the Department of the Air Force Air Education and Training Command.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

General

Project No:Project Title:Date:
EEPZ254668Repair LRS Hazmat Roof20-Apr-26
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
1Work/Construction/phasing PlanBASICX
2As-Built DrawingsBASICX
3Progress ScheduleBASICX
4Guarantees and WarrantiesBASICX
5Superintendent's Qualifications and ExperienceBASICX

AF Form 66 (Substitute) GENERAL Page&Pof&N

SCHEDULE OF MATERIAL SUBMITTALS

Environmental

Project No:Project Title:Date:
EEPZ254668Repair LRS Hazmat Roof20-Apr-26
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
6Appropriate SDSBASIC
7Hazardous waste reportBASIC
8Hazardous Material Report (AF Form 3000)BASIC
9Recycled Material Report/Construction Debris reportBASIC
10Storm Water Pollution Prevention Plan with Best Management Practices IdentifiedBASIC
11Weekly Inspection Reports for ProjectsBASIC
12State Licenses for workers and supervisors (Asbestos)BASIC
13State license for the firm (Asbestos)BASIC
1410 Day Notification (Demolition and Asbestos)BASIC
15Work PlanBASIC
16Copy of ACM DisposalManifestBASIC

AF Form 66 (Substitute) Environmental Page&Pof &N

SCHEDULE OF MATERIAL SUBMITTALS

Architectural

Project No:Project Title:Date:
EEPZ254668Repair LRS Hazmat Roof20-Apr-26
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
Roof PlanXXX
CopingXXX
FlashingXXX
TPO Single Ply MembraneXXX
AdhesiveXXX

AF Form 66 (Substitute) Architectural Page&Pof&N

Civil

Project No:Project Title:Date:
EEPZ254668Repair LRS Hazmat Roof20-Apr-26
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
Structural SteelX

AF Form 66 (Substitute) CIVIL Page&Pof &N

Mechanical

Project No:Project Title:Date:
EEPZ254668Repair LRS Hazmat Roof20-Apr-26
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
NONE

AF Form 66 (Substitute) Mechanical Page&Pof&N

Electrical

Project No:Project Title:Date:
EEPZ254668Repair LRS Hazmat Roof20-Apr-26
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
NONE

AF Form 66 (Substitute) Electrical Page&Pof &N

Special Systems

Project No:Project Title:Date:
EEPZ254668Repair LRS Hazmat Roof20-Apr-26
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
Sample Roof WarrentyXX

AF Form 66 (Substitute) Special Systems Page&Pof &N

Other&Misc

Project No:Project Title:Date:
EEPZ254668Repair LRS Hazmat Roof20-Apr-26
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
Airfield Waiver
Prepared by CE but contractor must supply:
1. Site Plan/Area of Work
2. Type of Equipment to be used
3. Maximum height of equipment
4. Work Hours (24/7, nights, non-flying, etc).
5. Work Schedule

Height of equipment on the airfield

AF Form 66 (Substitute) Other and Misc Page&Pof &N

HAZMAT Tracking Sheet

Contractor Hazardous Materials Usage Tracking Form
Return this form to Contracting/Project Manager with Manufacturers original SDS
EEPZ254668Repair LRS Hazmat RoofContract #
Start Date:End Date:Cotractor:
Product Name as seen on SDS
Process (How is material used)Part #ManufacturerType of
ContainerSize of ContainerTotal

Quantity

UsedEESOH MSN
1
Process:
2
Process:
3
Process:
4
Process:
5
Process:
6
Process:
7
Process:
8
Process:
9
Process:
10
Process:
11
Process:
12
Process:
13
Process:
14
Process:
15
Process:
16
Process:
17
Process:
18
Process:
19
Process:
20
Process:
21
Process:
22
Process:
23
Process:
24
Process:
25
Process:
26
Process:
27
Process:
28
Process:

Example and Instructions

WORKSHEET INSTRUCTIONS
BLOCKDESCRIPTIONINFORMATION REQUIRED
AProject NumberProject number or Opportunity number assigned to the project by Civil Engineering.
BProject TitleThe title of the project.
CContract NumberThe contract number or delivery order assigned by contracting.
DProduct NameThe name of the product as listed on the SDS.
EProcessA Brief description of the work performed with each material.
FPart #The part number as listed on the SDS.
GManufacturerThe name of the Manufacturer of the product (not the distributor)
HType of ContainerThe type of container that the product comes in. Example: can, barrel, bottle, container, cylinder, drum, etc…
ISize of ContainerSize as listed on container. Example: oz, lbs, Liter, Quart, Gallon, etc…
JTotal Quantity UsedThis will be the amount that you anticipate using for the first submission. At the conclusion of the project you will need to provide a final list with updated quantities.
KEESOH MSNThis is the Material Stock Number assigned for EESOH-MIS tracking. (The Air Force Hazardous Materials Manager will provide this number)

NOTE: Complete the HAZMAT Tracking Sheet located on the first TAB of this Excel spreadsheet with all hazardous materials to be used during the duration of the construction project. Once completed, save the sheet as a .pdf file and submit to the contracting officer with an AF Form 3000 Submittal form. This data will need to be submitted prior to construction start. When construction is complete, you will submit a final revised report with updated quanties.

image1.emf

File details come from the government source that posted it. Updated .