This document contains questions and answers regarding a federal contract solicitation for runway friction improvement work at Joint Base San Antonio-Randolph in Texas. The solicitation seeks a contractor to provide management, tools, materials, equipment and labor to repair the west runway. The work includes grading, diamond grinding, joint sealing, concrete repair, striping and other tasks. The period of performance is 120 calendar days with award estimated between $1,000,000 to $5,000,000. Funding has not been obligated and the solicitation may be cancelled if funds do not become available. The Air Force is the contracting agency and work must be completed by April 2022.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question Answer SOW Revision
Y/N If Revised; paragraph and page number
Specs call out cut material is 2,000 c.y. will there be a change order for anything more than that?
The anticipated amount of cut materail is 2,000 CY. Approximate square footage of excavation is 390,100 SF. Please be advised that this is only a best guess based on 2011 TNRIS LiDAR data, and is not based on ground survey data.
Yes Sec 01 11 00.10
Para 1.3.2.2
For the purposes of the scope of work it indicates 2,000 cubic yards of cut. Generally this does not sound like a great deal of grading but when considering the amount of surface area this is occurring over it is a much larger area. It is recommended that the square footage of area to receive grading be indicated rather than the cubic yards of actual cut to ensure those not in attendance at the site visit understand the significant area that is being graded.
The anticipated amount of cut materail is 2,000 CY. Approximate square footage of excavation is 390,100 SF. Please be advised that this is only a best guess based on 2011 TNRIS LiDAR data, and is not based on ground survey data.
Yes Sec 01 11 00.10
Para 1.3.2.2
Please specify a secure area to stage equipment The Contractor will be allowed to stage equipment on the airfield near the fence just north of the West Tower. The contractor may also stage equipment at the location near the high school where spoils may be stockpiled.
Yes Sec 01 11 00.10
Pare 1.3.1
Per the solicitation, none of the equipment used in the grinding Scope is to exceed 12 ft. the machines and support equipment required to complete the grinding exceed that height requirement. Railing on the top of the grinders and tankers, provided for the safety of our operators, make the height of this equipment closer to 14Ft.
Can the allowance be raised to accommodate the proper equipment needed to complete the diamond grinding scope of work?
The additional height will be allowed. The equipment must be removed prior to airfield opening and flying operations.
No
Will contractor need to provide any traffic control? This project is not anticipated to impact traffic, therefore a Traffic Control Plan will not be required.
No
What is the distance of water source available to be used by contractor for wet grinding? i.e. fire hydrant.
A hydrant is located on the north corner of the intersection of I St and 5th West. It is located appox 150 feet outside of the gate to the flightline. A backflow preventer with a current Test and Maintenance report is required. A copy of BPAT License and a current guage certification along with a photo ID of tester is required.
Yes Sec 01 11 00.10
Para 1.3.2.9
Is there a High pressure water source on-site that can be used to supply water for the grinding operation?
A hydrant is located on the north corner of the intersection of I St and 5th West. It is located appox 150 feet outside of the gate to the flightline. A backflow preventer with a current Test and Maintenance report is required. A copy of BPAT License and a current guage certification along with a photo ID of tester is required.
Yes Sec 01 11 00.10
Para 1.3.2.9
During the site visit it was indicated that an onsite water source would be available for use for this project. Can the government provide a diagram/map indicating the location of this water source relative to the work area?
A hydrant is located on the north corner of the intersection of I St and 5th West. It is located appox 150 feet outside of the gate to the flightline. A backflow preventer with a current Test and Maintenance report is required. A copy of BPAT License and a current guage certification along with a photo ID of tester is required.
Yes Sec 01 11 00.10
Para 1.3.2.9
Section 01 11 00.10 Paragraph 1.3.2.2 requires hydromulching of the graded areas upon completion of the work.
During the site visit we discussed whether watering to establishment would be required as this is not alluded to in the RFP. This watering would have to take place for an extended period after completion of work. Please confirm whether the contractor is required to provide watering or whether natural growth will be permitted?
Contractor is to hydromulch graded areas in accordance with Specifications Section 32 05 33 – Landscape establishment and Section 32 92 19 - Seeding. The turf will be considered established when there is 95 percent ground cover per Section 1.1.2 in Section 32 05 33. Minimum acceptance of turf may include scattered bare spots, none of which are larger than 1 square foot. The contractor will be responsible for watering to establishment. Watering must be done when the airfield is closed. Desired seed mixture will include seed native to the area or currently found on the airfield. This may include Bermudagrass, Buffalograss and Ryegrass. All earth work shall be planned and conducted to minimize the duration of exposure of unprotected soils.
Yes Sec 01 11 00.10
Para 1.3.2.2
After grading, contractor is directed to hydro mulch disturbed area. Who is responsible for watering of hydro mulch as there is not a nearby water source to provide temporary sprinklers.
Contractor is to hydromulch graded areas in accordance with Specifications Section 32 05 33 – Landscape establishment and Section 32 92 19 - Seeding. The turf will be considered established when there is 95 percent ground cover per Section 1.1.2 in Section 32 05 33. Minimum acceptance of turf may include scattered bare spots, none of which are larger than 1 square foot. The contractor will be responsible for watering to establishment. Watering must be done when the airfield is closed. Desired seed mixture will include seed native to the area or currently found on the airfield. This may include Bermudagrass, Buffalograss and Ryegrass. All earth work shall be planned and conducted to minimize the duration of exposure of unprotected soils.
Yes Sec 01 11 00.10
Para 1.3.2.2
Are we to water to establish (Hydro mulch) grass? And what type of mix will be required?
Contractor is to hydromulch graded areas in accordance with Specifications Section 32 05 33 – Landscape establishment and Section 32 92 19 - Seeding. The turf will be considered established when there is 95 percent ground cover per Section 1.1.2 in Section 32 05 33. Minimum acceptance of turf may include scattered bare spots, none of which are larger than 1 square foot. The contractor will be responsible for watering to establishment. Watering must be done when the airfield is closed. Desired seed mixture will include seed native to the area or currently found on the airfield. This may include Bermudagrass, Buffalograss and Ryegrass. All earth work shall be planned and conducted to minimize the duration of exposure of unprotected soils.
Yes Sec 01 11 00.10
Para 1.3.2.2
For the area to receive hydromulch please confirm that no topsoil will be required. If topsoil is required what thickness as this will impact the grading operation?
Addition of topsoil will not be permitted.
Contractor is to hydromulch graded areas in accordance with Specifications Section 32 05 33 – Landscape establishment and Section 32 92 19 - Seeding. The turf will be considered established when there is 95 percent ground cover per Section 1.1.2 in Section 32 05 33. Minimum acceptance of turf may include scattered bare spots, none of which are larger than 1 square foot. The contractor will be responsible for watering to establishment. Watering must be done when the airfield is closed. Desired seed mixture will include seed native to the area or currently found on the airfield. This may include Bermudagrass, Buffalograss and Ryegrass. All earth work shall be planned and conducted to minimize the duration of exposure of unprotected soils.
Yes Sec 01 11 00.10
Para 1.3.2.2
Per site visit it was mentioned that use of a fire hydrant creates certain responsibilities of contractor. Please provide guidelines for this procedure on JBSA.
A hydrant is located on the north corner of the intersection of I St and 5th West. It is located appox 150 feet outside of the gate to the flightline. A backflow preventer with a current Test and Maintenance report is required. A copy of BPAT License and a current guage certification along with a photo ID of tester is required. Please reference Section 01 57 20 - Environmental Protection, Section
3.3.2 Potable Water.
Yes Sec 01 11 00.10
Para 1.3.2.9
Is there any record of concrete age of this runway? PCI indicates reconstruction of the landing zones in 1995. No
Please confirm the work hours. Will it be from 1900 hrs. to 0700hrs?
Airfield hours are 0600-1900 Monday through Friday. Work hours shall be 1900- 0600 Monday through Friday. The airfield is closed weekends and holidays. Once per month, there will be flying on a Saturday. Contractor will be given at least 30 day notice of this date.
Yes Sec 01 14 00 Para 1.4.4.1
Section 01 11 00.10 Paragraph 1.6 states all work must be completed while the airfield is closed, normally nights 1900-0600, holidays and most weekends. Section 32 17 23 Paragraph 1.5.3 states that the Runway is closed All Day on Saturday and Sunday. Please confirm that it is acceptable to work during normal hours on Saturday and Sunday.
Airfield hours are 0600-1900 Monday through Friday. Work hours shall be 1900- 0600 Monday through Friday. The airfield is closed weekends and holidays. Once per month, there will be flying on a Saturday. Contractor will be given at least 30 day notice of this date.
Yes Sec 01 14 00 Para 1.4.4.1
Phasing Plan Page 13 of 13 Temp Const. Waiver General Notes indicates Phase 3 must be done when the airfield is closed. Our understanding was that all work had to be done when the airfield is closed. Please confirm.
All phases of work shall occur when the airfield is closed. No
In the SOW, a survey was provided for LBP on the runway. Discussion on site visit was that further testing determined there is no LBT present in the work area. Please confirm that no LBP exists and abatement will not be a requirement of the contract.
Environmental has confirmed that there is NO Lead Based Paint on the runway, to include the side stripes.
No
There will be significant amounts of concrete slurry produced during the diamond grinding operation that will require disposal. Is there a location on Randolph AFB where this concrete slurry can be disposed of, or will it be required to be removed from the base?
All waste must be removed off base. All concrete waste must be mainfested as Class 2 Construction Debris. If the concrete is clean, it is acceptable for the concrete to be recycled. Weight tickets will be required.
Yes Sec 01 11 00.10
Para 1.3.2.7
Please specify location to dispose of slurry generated by diamond cutting process.
All concrete waste must be mainfested as Class 2 Construction Debris. If the concrete is clean, it is acceptable for the concrete to be recycled. Weight tickets will be required.
Yes Sec 01 11 00.10
Para 1.3.2.7
Please provide direction for disposal on stock piling of spoils generated from grading.
Stock piling of spoils is permitted at an empty asphalt lot located just south of the high school on Perimeter Rd. It is located appox 1600 ft west from the center of the runway and measures appox 475 ft by 340 ft.
Yes Sec 01 11 00.10
Para 1.3.1
If spoils are to hauled off site, what is the protocol for tracking hauling off-site? i.e., weight tickets, testing, etc.
The contractor is responsible for the excavation to be tested. All of the excavated and cut material shall meet the testing requirements below:
a. RCRA 11 metals (method SW 7000 series, Totals analysis with TCLP extraction)
b. Organochlorine Pesticides/Polychlorinated Biphenyl (PCBs) (method SW 8081a/8080, total analysis with TCLP extraction)
c. Semi-Volatile Organic Compounds (SVOCs) (method SW 8270, Totals analysis with TCLP extraction)
d. Volatile Organic Compounds (VOCs) (method SW 8260 Totals analysis with TCLP extraction)to include BTEX
e. Total Petroleum Hydrocarbons (TPH) (TX method 1005)
f. Non-halogenated Organics (SW 8015, TCLP extraction)
g. Reactivity, Corrosivity, Ignitibility (RCI)
- The results will determine proper disposal.
- All materials will be reviewed by the Hazardous Waste Manager.
- Waste will be profiled and manifested according to the reesults.
An alternative option is for materials to recycled at an approved recycling facility that will accept a Waste Manifest and provide a certificate of recycling.
Yes Sec 01 11 00.10
Para 1.3.2.7
Is the friction testing the responsibility of the contractor or the government? The contractor will be responsible for friction testing. Yes Sec 01 11 00.10
Para 1.3.2.1
Will we have the room required to perform the friction analysis which will take several hundred feet to get up to speed.
There will be a closed safety area next to the area of grinding on each end of the runway. The north end safety area will be 1,500 ft long and the sound end will be 1,300 ft long.
No
Because of the age of existing joint sealant, it is uncertain how the existing sealant will fare through the diamond grinding process. Please provide a quantification for joint sealant replacement.
The 'old' section of the southern end of the West Runway has joint seal that is in poor condition. This is the section where the slabs measure 13' x 15'. It is extimated that 15,000 LF of joint seal will need replacing.
Yes Sec 01 11 00.10
Para 1.3.2.6
Section 01 11 00.10 Paragraph 1.3.2.6 requires Joint Seal Repair in the event the diamond grinding process causes damage to the existing joint seal. As discussed and observed at the site visit there is variation throughout the runway with the depth of the joint seal with some areas having joint seal already on top of the slab. As it was not possible to fully take off this condition during the site visit it is recommended that an allowance be accounted for in this bid. Will the government provide a linear footage of joint seal repair that the contractor should include in its bid?
The 'old' section of the southern end of the West Runway has joint seal that is in poor condition. This is the section where the slabs measure 13' x 15'. It is extimated that 15,000 LF of joint seal will need replacing.
Yes Sec 01 11 00.10
Para 1.3.2.6
What is considered damaged sealant?
Joint sealant will be considered damage when it meets the "High Severity" definition in the 2010 Airfield Concrete PCI Handbook. According to the Handbook, "Typical types of joint seal damage are (a) stripping of joint sealant, (b) extrusion of joint sealant, (c) weed growth, (d) hardening of the filler (oxidation), (e) loss of bond to the slab edges, and (f) lack or absence of sealant in the joint." High Severity is defined as, "Joint sealer is in generally poor condition over the entire surveyed section, with one or more of the above types of damage occurring to a severe degree. Sealant needs immediate replacement. Joint seal damage is at high severity if 10% or more of the joint sealer exceeds limiting criteria listed above, or if 10% or more of sealer is missing." The Airfield Manager and CE Pavements will be the responsible party for inspection and severity determination.
Yes Sec 01 11 00.10
Para 1.3.2.6
Because of the age of existing concrete, it is uncertain how these panels fare through the diamond grinding process. Please quantify the numbers of runway concrete panels to be replaced.
Per SOW Section 1.3.2.5 Slab Replacement, "it is anticipated that no more than 4 slabs will need replacement." To further clarify, it is assumed that 4 - 25ft by 25ft slabs will need to be replaced. Per SOW Section 1.3.2.4 Spall Repairs, "it is anticipated that no more than 50 square feet of pavement will need spall repairs."
Yes Sec 01 11 00.10
Para 1.3.2.5
Are we to grind just the 1/4” of the existing concrete even though we did see some panel that had moved 1/2” up or so? The grind machine will not adjust to those difference.
Each section of runway will have different requirements. Please reference attached Pavement Detail Map. Some areas of runway are at or below UFC minimums for slab thickness. In Section 4 (north end), do not remove an amount greater than 1/4 inch. In Section 8 (the northern end of the south end where slabs measure 13' x 15'), grinding may go to a depth no greater than 3/4 inch. In Section 10 (southern end of south end where slabs measure 25' x 25') grinding may not exceed 1/4 inch. Ensure transition from Section 8 to Section 10 is smooth, in accordance with Section 2.1.1.2 of Section 32 13 14.13 in the specifications.
Yes Sec 01 11 00.10
Para 1.3.2.1
How many square feet of concrete will require removal and replacement?
Per SOW Section 1.3.2.5 Slab Replacement, "it is anticipated that no more than 4 slabs will need replacement." To further clarify, it is assumed that 4 - 25ft by 25ft slabs will need to be replaced. Per SOW Section 1.3.2.4 Spall Repairs, "it is anticipated that no more than 50 square feet of pavement will need spall repairs."
Yes Sec 01 11 00.10
Para 1.3.2.5
The solicitation specifies a max grinding depth of ¼”. The amount of removal is determined by the existing profile of the concrete area to be ground. It will cut deeper in some areas, and shallower in others depending on the profile of the pavement. Will some areas ground deeper than ¼’ be acceptable?
Each section of runway will have different requirements. Please reference attached Pavement Detail Map. Some areas of runway are at or below UFC minimums for slab thickness. In Section 4 (north end), do not remove an amount greater than 1/4 inch. In Section 8 (the northern end of the south end where slabs measure 13' x 15'), grinding may go to a depth no greater than 3/4 inch. In Section 10 (southern end of south end where slabs measure 25' x 25') grinding may not exceed 1/4 inch. Ensure transition from Section 8 to Section 10 is smooth, in accordance with Section 2.1.1.2 of Section 32 13 14.13 in the specifications.
Yes Sec 01 11 00.10
Para 1.3.2.1
During the site visit it was observed that there are numerous different elevations of slabs on the runway and that more than ¼” will need to be removed in some areas with the diamond grinding to achieve 100% of the area textured. What will be acceptable, more removal depth or less area textured?
Each section of runway will have different requirements. Please reference attached Pavement Detail Map. Some areas of runway are at or below UFC minimums for slab thickness. In Section 4 (north end), do not remove an amount greater than 1/4 inch. In Section 8 (the northern end of the south end where slabs measure 13' x 15'), grinding may go to a depth no greater than 3/4 inch. In Section 10 (southern end of south end where slabs measure 25' x 25') grinding may not exceed 1/4 inch. Ensure transition from Section 8 to Section 10 is smooth, in accordance with Section 2.1.1.2 of Section 32 13 14.13 in the specifications.
Yes Sec 01 11 00.10
Para 1.3.2.1
Section 01 11 00.10 Paragraph 1.3.2.5 requires slab replacement in the event the diamond grinding process causes damage enough to warrant entire slab replacement. In this it states that no more than 4 slabs will need replacement. As discussed at the site visit it is not possible to anticipate the condition of the slabs to account for this in our bid outside of a pre-determined quantity. Please confirm that our bid should include 4 slabs to be replaced and anything beyond this would be handled via modification?
Per SOW Section 1.3.2.5 Slab Replacement, "it is anticipated that no more than 4 slabs will need replacement." To further clarify, it is assumed that 4 - 25ft by 25ft slabs will need to be replaced. Per SOW Section 1.3.2.4 Spall Repairs, "it is anticipated that no more than 50 square feet of pavement will need spall repairs."
Any quantity greater than this amount shall be handled via modification.
Yes Sec 01 11 00.10
Para 1.3.2.5
What is the typical slab dimensions?
North end - 25ft x 25ft Southern end of South end - 25ft x 25ft Northern end of South end - 15ft longitudinally x 13ft transversely
Yes Sec 01 11 00.10
Para 1.3.2.1
Will detail drawings be provided for concrete slab replacement areas?
As-builts have been requested, but have not been delivered yet. It is unknown if as-builts exist at this time. Pavement Rankings for the airfield are attached. North end slabs average appox 10.25 in of PCC and south end slabs average appox 11.00 in
PCC.
No
What are the sizes and depth of the concrete panels? Did notice that the south and north panels were of different sizes.
North end - 25ft x 25ft Southern end of South end - 25ft x 25ft Northern end of South end - 15ft longitudinally x 13ft transversely North end slabs average appox 10.25 in of PCC and south end slabs average appox
11.00 in PCC. Pavement details are attached.
Yes Sec 01 11 00.10
Para 1.3.2.1
Per site visit it was stated that not all islands between runways will be graded. Please provide direction as to which ones
Per SOW Section 1.3.2.2 Grading of West Runway Shoulders, "Grade infields between Taxiways G1 and G2, G2 and G3, G3 and G4, and G4 and G5. Grading between G5 and G6 is not included in this contract."
No
Can we have the s.f. of the areas to be graded? Approximately 390,100 SF Yes Sec 01 11 00.10
Para 1.3.2.2
Has the soil that will be excavated been tested? If not, will it need to be by us.
The contractor is responsible for the excavation to be tested. All of the excavated and cut material shall meet the testing requirements below:
a. RCRA 11 metals (method SW 7000 series, Totals analysis with TCLP extraction)
b. Organochlorine Pesticides/Polychlorinated Biphenyl (PCBs) (method SW 8081a/8080, total analysis with TCLP extraction)
c. Semi-Volatile Organic Compounds (SVOCs) (method SW 8270, Totals analysis with TCLP extraction)
d. Volatile Organic Compounds (VOCs) (method SW 8260 Totals analysis with TCLP extraction)to include BTEX
e. Total Petroleum Hydrocarbons (TPH) (TX method 1005)
f. Non-halogenated Organics (SW 8015, TCLP extraction)
g. Reactivity, Corrosivity, Ignitibility (RCI)
- The results will determine proper disposal.
- All materials will be reviewed by the Hazardous Waste Manager.
- Waste will be profiled and manifested according to the reesults.
An alternative option is for materials to recycled at an approved recycling facility that will accept a Waste Manifest and provide a certificate of recycling. If the procedures are followed to ensure clean soil, then it may be recycled once the results are cleared by our Hazardous waste Manager and the facility is approved for recycling. Manifesting is required so that we can track it and a weight ticket provided so we can show diversion from the landfill.
Yes Sec 01 11 00.10
Para 1.3.2.7
As discussed at the site visit, we are looking for clear direction on the disposal requirements related to clean soil from grading operations. JBSA Soil Management Plan promotes the recycling of Clean Soil. Additionally, Section 01 57 20 Paragraph 3.8.1.1 provides a DOD mandate to divert 60% of all non-hazardous solid waste for recycling.
Section 01 11 00.10 Paragraph 1.3.2.7 states, “Waste material shall be hauled off site to approved site following approved waste management plan for hauling of soil to land fill. As discussed, hauling the soil to the landfill is a significant cost to the project. There are many locations that will accept clean fill material for little to no cost, however the landfill will charge a significant cost for each load impacting the final price of the project. This also would be counter to the JBSA Soil Management Plan recommendation of recycling and keeping clean materials out of the landfill. We recommend recycling of clean soil to be permitted. Please advise if this is acceptable?
The contractor is responsible for the excavation to be tested. All of the excavated and cut material shall meet the testing requirements below:
a. RCRA 11 metals (method SW 7000 series, Totals analysis with TCLP extraction)
b. Organochlorine Pesticides/Polychlorinated Biphenyl (PCBs) (method SW 8081a/8080, total analysis with TCLP extraction)
c. Semi-Volatile Organic Compounds (SVOCs) (method SW 8270, Totals analysis with TCLP extraction)
d. Volatile Organic Compounds (VOCs) (method SW 8260 Totals analysis with TCLP extraction)to include BTEX
e. Total Petroleum Hydrocarbons (TPH) (TX method 1005)
f. Non-halogenated Organics (SW 8015, TCLP extraction)
g. Reactivity, Corrosivity, Ignitibility (RCI)
- The results will determine proper disposal.
- All materials will be reviewed by the Hazardous Waste Manager.
- Waste will be profiled and manifested according to the reesults.
An alternative option is for materials to recycled at an approved recycling facility that will accept a Waste Manifest and provide a certificate of recycling. If the procedures are followed to ensure clean soil, then it may be recycled once the results are cleared by our Hazardous waste Manager and the facility is approved for recycling. Manifesting is required so that we can track it and a weight ticket provided so we can show diversion from the landfill.
Yes Sec 01 11 00.10
Para 1.3.2.7
Has the striping been tested? Environmental has confirmed that there is NO Lead Based Paint on the runway, to include the side stripes.
No
Phasing Plan does not indicate when permanent striping replacement is to be performed. Please confirm that this should be performed as part of Phase 1d and 2d?
Permanent striping will be completed in phase 1d and 2d. After the grinding is perford
No
I understand that the pricing will be broken up into three Clin, will they all be lump sum? The project will not be broken into CLIN's. No
When will we be sent the sign in sheet?
The Government has categorized the information on the Site visit sign-in sheet to be CONTROLLED UNCLASSIFIED INFORMATION (CUI), information which must be protected under the Freedom of Information Act (5 U.S.C. 552) and/or the Privacy Act of 1974 (5 U.S.C. 552a). Therefore, a copy that redacts the phone number and email address will be published.
No
Can the Job walk attendance list be provided?
The Government has categorized the information on the Site visit sign-in sheet to be CONTROLLED UNCLASSIFIED INFORMATION (CUI), information which must be protected under the Freedom of Information Act (5 U.S.C. 552) and/or the Privacy Act of 1974 (5 U.S.C. 552a). Therefore, a copy that redacts the phone number and email address will be published.
No
Per the Phasing plan, Low profile Barrier is to be placed at the limits of the grinding areas. The Machines used to performed the grinding need at least 15-20 feet passed the area to be ground available. Will the barrier be allowed to be placed 20 feet beyond the grinding limits into the Closed Safety Area, so that the designated areas to be ground can be reached?
The low profile barriers will be allowed 20 feet beyond limits to accommodate machinery.
Yes Sec 01 11 00.10
Para 1.3.2.3
This solicitation allows for 120 to award a contract, and 120 days for performance of the contract. However Per the Solicitation, all runway work must completed prior to April 18, 2022 (the mandated shutdown for the Air Show). Should all 120 days be used prior to the award of a contract, that would be March 19,2022. That is only 30 days prior to the mandate completion date for April 18,2022. Will this requirement be waived should award of contract not allow for sufficient time to complete runway work by April 18.2022?
Pending receipt of funding, the Government anticipates awarding the resulting contract on or about 30 December 2021 with anticipation of issuing the NTP about middle of January 2022. The focus will on completing Phase 1 of work within 60 days of NTP. The Government will work with the successful awardee to ensure the project schedule does not conflict with the Airshow on April 23 – 24.
Yes Sec 01 11 00.10
Para 1.3.1
Are there any specific lighting requirements that will be required during our night work? CE has no specific requirements. Equipment must be removed from airfile prior to flying operations.
No
Attachment 2 Phasing Plan Phase 1a and 2a states it includes Turning off threshold lights. Please confirm that this is being done by Airfield Management as turning off of lights is not included in the Statement of Work.
Airfield Lighting will be notifed to "Lock Out Tag Out" the lights. Recommend the contractor be present at the vault to visually see the lights are locked out. Please coordinate this with CONS, PM or directly with Airfield Management.
Yes Sec 01 11 00.10
Para 1.3.2.3
How many runway edge lights are located in Phase 1a that must be covered? Appox 23. Exact number may vary slightly. All edge lights up to the temporary displaced threshold must be covered.
No
How many runway edge lights are located in Phase 2a that must be covered? Appox 32. Exact number may vary slightly. All edge lights up to the temporary displaced threshold must be covered.
No
How many distance remaining markers are in Phase 1a that must be covered? 4. All markers up to the temporary displaced threshold must be covered. No
How many distance remaining markets are in Phase 2a that must be covered? 6. All markers up to the temporary displaced threshold must be covered. No
Per the site visit it was indicated that none of the markings being impacted during this project were positive for lead based paint requiring abatement. Please confirm.
Environmental has confirmed that there is NO Lead Based Paint on the runway, to include the side stripes.
No
Please confirm or deny Lead Based Paint is present on the runway where grinding and painting activities are planned as depicted in the Grinding and Marking exhibit and LBP inventory report supplied in the solicitation.
Environmental has confirmed that there is NO Lead Based Paint on the runway, to include the side stripes.
No
Section 01 35 26 states that the SSHO can serve as Quality Control Manager and can also serve as Superintendent but cannot fulfill all three roles. Due to the limited number of work elements associated with this project it is requested that one person be permitted to fulfill all 3 roles. Please advise if this is acceptable or if 2 personnel fulfilling these roles will be required?
One person is not permitted to fufill all 3 roles. No
Attachment 2 Phasing Plan Phase 1a and 2a states it includes, “turn off 15R PAPIs. Please confirm that this is being done by Airfield Management as this is not indicated in the Statement of Work and we are not familiar with what a PAPI is and how it would be turned off.
PAPI lights will be turned off by Airfield Lighting. Please coordinate this with CONS, PM or directly with Airfield Management.
Yes Sec 01 11 00.10
Para 1.3.2.3
We are requesting a copy of utility maps for the runway for the areas where grading is to take place. Utility Maps will be provided. Electrical locates may be required. No
Can contractor employees park near the staging area as noted on the phasing plan?
Contractors may park out side the fence by the laydown area. Gate code will be given to individuals that complete the Airfield Driving/Controlled Area training.
Airfield vehicle pass will be given to individuals as needed.
Yes Sec 01 11 00.10
Para 1.3.1