Questions_and_Answers__06-30-2016_REVISED.pdf

PDF 38 KB Posted

Attached to
Draperies Federal contract opportunity
Solicitation number
FA3016-16-N-0113
Issued by
Department of the Air Force Air Education and Training Command

About this file

Q and A Revised 06/30/2016

View the file

Other files for this federal contract opportunity

Other files attached to Draperies, newest first.
File Type Posted
Questions_and_Answers_07-07-2016.docx DOCX document
Attachment_B_Tech_Specs_Adjustment_PRF2MRAA6036AW02.pdf PDF
Questions_and_Answers_06-30-2016.docx DOCX document
Attachment_B_Tech_Specs_for_Drapery_Contract_PRF2MRAA6036AW02.pdf PDF
RFQ__FBO.pdf PDF
Attachment_C_Floor_Plan_B3631_3635.pdf PDF
Statement_of_Work_PR_F2MRAA6036AW02.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers (REVISED)

June 30, 2016

1. Is this project new construction or remodel of existing?

Answer - remodel of existing

2. If remodel, will the rooms be occupied or un-occupied?

Answer - the rooms will be occupied

3. Will our installers have clear access to the windows?

Answer – Yes

4. How many bldgs. are involved and how many floors per bldg?

Answer - There are 2 buildings, 3 floors in each building.

5. Do the bldgs. have freight elevators?

Answer - No. The buildings have standard elevators.

6. Will secure locations be provided on-site to store the drapery & rods?

Answer - We do have storage rooms throughout the building. If the drapery install takes several days, the draperies can be installed in the warehouse. Vendor will be required to take them to the warehouse and pick them up themselves.

7. Can we have the goods shipped to our installer and store them off-site?

Answer - If the vendor wants to ship the goods to their installer and store them off site during the installation time it is up to them but there will be no additional charges.

8. There isn’t a fabric specified. Can we quote any fabric we choose?

Answer – Attachment B has been revised and updated.

9. Are the mounting surfaces, walls & ceilings, drywall/Sheetrock or concrete/brick?

Answer – They will be mountin to the walls/drywall

10. Can the treatments & rods that are removed be disposed of in the base’s dumpsters or must they be hauled off-site?

Answer – Dumpsters are on site where the draperies and hardward can be dumped.