Attachment 13 - Renovate Blake Gym - Addendum 2.pdf
PDF 67 KB Posted
- Attached to
- Renovate Blake Gym
- Solicitation number
- FA301024R0003
About this file
This document is an Addendum #2 for the Renovate Blake Gym contract opportunity. It provides changes to the previous Addendum #1 and the original bid/contract documents. Key details include:
The work to the Family Room, Storage, and Janitor rooms is now included in the Men and Women's Locker Room scope of work, omitting the requirement to acid wash the floor and base. Item #2 from Addendum #1, regarding the steel platforms, is being omitted - the steel platforms are to be removed per the original bid documents. Additionally, the requirement to demolish all wood gym flooring has been removed, with the contractor now required to protect the existing gym flooring during the renovation.
The related federal contract opportunity is a solicitation (FA301024R0003) for the Renovate Blake Gym project, with an estimated magnitude between $1,000,000 and $5,000,000. It is a Total Small Business set-aside, with a site visit scheduled for May 1, 2024. The award will be made on an all, some, or none basis depending on available funding at the time of award, with the period of performance based on the awarded CLIN(s).
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM #2 Date: 22 May 2024
PROJECT NAME: Renovate Blake Gym
LOCATION: Building 1201
PROJECT NUMBER: MAHG191089, WT: #13967122
The following conditions take precedence over conflict conditions in the Specifications, on the
Drawings, and in any other Contract Document. When a change is called for on a Drawing, this change shall carry through all applicable drawings, including all related architectural, civil, structural, mechanical, plumbing and electrical drawings. The Bid/Contract Documents are hereby amended in the following particulars:
Pertaining to Appendix #1:
1. REMOVE Appendix #1 in its entirety. The work to the Family Room, and also the adjacent Storage and Janitor rooms, is included in the Men and Women’s Locker Room scope of work. This omits the requirement to acid wash the floor and base.
Pertaining to Addendum #1:
2. OMIT item #2: Key note “K” is to remain on sheet D111 - The steel platforms are to be removed per the bid documents.
Pertaining to the Drawings – Reference Sheet D101:
3. OMIT Keynote “N”: – “Demolish in its Entirety All Wood Finish Flooring”. The wood gym flooring is to remain. However, the contractor shall protect the gym flooring from damage and the removal of the steel platform above the floor.
END OF ADDENDUM 2