This document is Appendix 2 to the Solicitation for the project to Repair Blake Gym, Solicitation Number FA301024R0003. The Appendix outlines the Option Scope of Work if Bid Option #1 is exercised, which includes renovations to the Weight/Cardio Room, Racquet Courts, and Lobby/Office Area/Gymnasium. The renovations involve new flooring, wall finishes, doors, and other improvements in these areas of the facility. The larger Solicitation is a Total Small Business set-aside for between $1,000,000 and $5,000,000 in proposed construction, with an award to be made on an all, some, or none basis depending on available funding. The Period of Performance will be determined based on which CLIN(s) are awarded.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Appendix 2 Rev 30 Jan 2024
FA301024R0003
APPENDIX 2
Project Number: MAHG191089
Project: Repair Blake Gym
OPTION SCOPE OF WORK:
I. The following scope of work items shall be performed if Bid Option #1 is exercised.
A. Weight/Cardio Room.
(Area includes weight room and 3 cardio rooms)
1. Weight Room:
a) New rubber flooring and new base (heavy duty rubber roll and rubber base)
2. Adjacent Weight Room (existing cardio room):
a) New gypsum wall board on metal stud wall framing on all walls
b) New rubber flooring and new base (heavy duty rubber roll and rubber base)
c) New demolition of hollow metal frame and glazing
3. New Circuit Room (existing cardio room):
a) New gypsum wall board on metal stud wall framing on all walls
b) New rubber flooring and new base (heavy duty rubber roll and rubber base)
4. New Workout Room with Kids’ Space (existing cardio room):
a) New gypsum wall board on metal stud wall framing on all walls
b) New rubber flooring and new base (heavy duty rubber roll and rubber base)
B. Raquet Courts
(Area includes 5 racquetball courts)
1. New Cardio Room (existing court #1 and court #2):
a) Demolition of cmu wall between the courts and between door and windows by corridor
b) New gypsum wall board on metal stud wall framing on all walls
c) New rubber flooring and new base (heavy duty rubber roll and rubber base)
d) New openings and new doors and frames
2. New Stretch Room (existing court #3):
a) Demolition of existing door and interior window
b) New gypsum wall board on metal stud wall framing on all walls
c) New rubber flooring and new base (heavy duty rubber roll and rubber base)
d) New opening and new doors and frames
C. Lobby/Office Area/Gymnasium
(Area includes lobby, office, general office, reception, laundry, storage, janitor, and family restroom)
1. Corridors:
a) New finish flooring and new base (ceramic tile to lobby area)
Appendix 2 Rev 30 Jan 2024
2. General Office:
a) New finish flooring and new base (carpet tile and rubber base)
3. Office:
a) New finish flooring and new base (carpet tile and rubber base)
4. Family RR:
a) New finish flooring (ceramic tile) and new base (ceramic tile base).
End of Appendix