Attachment 5 - Renovate Blake Gym - MSS.xls
XLS spreadsheet 64 KB Posted
- Attached to
- Renovate Blake Gym
- Solicitation number
- FA301024R0003
About this file
This document is an Attachment 5 - Material Submittals Schedule related to a federal contract opportunity to Renovate Blake Gym under Solicitation Number FA301024R0003.
The solicitation is a Total Small Business set-aside with an estimated construction value between $1,000,000 and $5,000,000. It requires the contractor to provide various material submittals for items such as concrete, masonry, doors, flooring, plumbing, HVAC, electrical, and security systems. The submittals have specified due dates, number of copies, and review/approval requirements. Key dates include a site visit on May 1, 2024 and a project completion date. The document also outlines requirements for O&M manuals and closeout documentation to be provided at the end of the project. The contract will be awarded on an all, some, or none basis depending on available funding.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Material Submittals Schedule
| Project Number: | |||
| MAHG191089 | Project Title: | ||
| Repair Blake Gym | Solicitation / Contract Number: |
[ FA301024R0003 ]
| Line Number | (To be completed by Project Engineer) | (To be completed by Contract Administrator) | 3-Apr-24 | |||||||||||||||||||
| Number of Copies Required (if not electronically submitted) | Remarks | |||||||||||||||||||||
| Item or Description of Item, Contract Reference, Type of Submittal | Certificate of Compliance | Shop Drawings | Samples | Color Selection | Manufacturer's Recommendation | Warranty-Manufacturer and/or Workmanship | Catalog Data | Operating Instructions | Schedules, Listings, Reports, Plans | Technical Data | Test Reports | Field Reports | Required Submission Date | Date Received in Contracting | Date to Civil Engineering | Return Suspense Date | Submittal Numbers | Date Contractor | ||||
| Notified | Contractor Resubmittal | Final Approval | ||||||||||||||||||||
| Approved | Disapproved | |||||||||||||||||||||
| 1 | HazMat Questionnaire | 3 | 5 Days Prior to Start Date | Provide the documents as required per the Environmental packet provided by Keesler AFB. | ||||||||||||||||||
| 2 | HazMat MSDS | 3 | 3 | 5 Days Prior to Start Date | Provide the documents as required per the Environmental packet provided by Keesler AFB. | |||||||||||||||||
| 3 | Hazmat Reporting Entry Form | 3 | 3 | 3 | 5 Days Prior to Start Date | Provide the documents as required per the Environmental packet provided by Keesler AFB. | ||||||||||||||||
| 4 | Recycling and Landfill Report | 3 | 3 | End of Contract | Provide the documents as required per the Environmental packet provided by Keesler AFB. | |||||||||||||||||
| 5 | Warranty (Manufacturer's) | 3 | End of Contract | |||||||||||||||||||
| 6 | 1-Year Warranty (Contractor) | 3 | End of Contract | |||||||||||||||||||
| 7 | 030516 - Underslab Vapor Barrier | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||||
| 8 | 031000 - Concrete Forming and Accessories | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||||||
| 9 | 032000 - Concrete Reinforcing | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||||||
| 10 | 033000 - Cast-in-Place Concrete | 3 | 10 Days Prior to need approval | |||||||||||||||||||
| 11 | 042000 - Unit Masonry | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||||||
| 12 | 061000 - Rough Carpentry | 3 | 10 Days Prior to need approval | |||||||||||||||||||
| 13 | 071300 - Sheet Waterproofing | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||||||
| 14 | ||||||||||||||||||||||
| 15 | 079200 - Joint Sealants | 3 | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||||
| 16 | 081113 - Hollow Metal Doors and Frames | 3 | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||||
| 17 | 081416 - Flush Wood Doors | 3 | 3 | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||
| 18 | 087100 - Door Hardware | 3 | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||||
| 19 | 092116 - Gypsum Board Assemblies | 3 | 10 Days Prior to need approval | |||||||||||||||||||
| 20 | 092400 - Cement Plastering | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||||
| 21 | 093000 - Tiling | 3 | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||||
| 22 | 095100 - Acoustical Ceilings | 3 | 3 | 3 | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||
| 23 | 096500 - Resilient Flooring | 3 | 3 | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||
| 24 | 096700 - Fluid-Applied Flooring | 3 | 3 | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||
| 25 | 096813 - Tile Carpeting | 3 | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||||
| 26 | 099113 - Exterior Painting | 3 | 3 | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||
| 27 | 099123 - Interior Painting | 3 | 3 | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||
| 28 | 099723 - Concrete and Masonry Coatings | 3 | 10 Days Prior to need approval | |||||||||||||||||||
| 29 | 101400 - Signage | 3 | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||||
| 30 | 102113.19 - Plastic Toilet Compartments | 3 | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||||
| 31 | 102800 - Toilet, Bath, and Laundry Accessories | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||||||
| 32 | 123600 - Countertops | 3 | 3 | 3 | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||
| 33 | 210500 - Common Work Results for Fire Suppression | 3 | 3 | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||
| 34 | 210523 - General-Duty Valves for Water-Based Fire-Suppression Piping | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||||||
| 35 | 211100 - Facility Fire-Suppression Water-Service Piping | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||||||
| 36 | 211300 - Fire-Suppression Sprinkler Systems | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||||
| 37 | 220523 - General-Duty Valves for Plumbing Piping | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||||||
| 38 | 220529 - Hangers and Supports for Plumbing Piping and Equipment | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||||||
| 39 | 220548 - Vibration and Seismic Controls for Plumbing Piping and Equipment | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||||||
| 40 | 220553 - Identification for Plumbing Piping and Equipment | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||||||
| 41 | 220716 - Plumbing Equipment Insulation | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||||||
| 42 | 220719 - Plumbing Piping Insulation | 3 | 10 Days Prior to need approval | |||||||||||||||||||
| 43 | 221005 - Plumbing Piping | 3 | 10 Days Prior to need approval | |||||||||||||||||||
| 44 | 221006 - Plumbing Piping Specialties | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||||
| 45 | 224000 - Plumbing Fixtures | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||||||
| 46 | 230519 - Meters and Gauges for HVAC Piping | 3 | 10 Days Prior to need approval | |||||||||||||||||||
| 47 | 230523 - General-Duty Valves for HVAC Piping | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||||||
| 48 | 230529 - Hangers and Supports for HVAC Piping and Equipment | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||||||
| 49 | 230548 - Vibration and Seismic Controls for HVAC | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||||||
| 50 | 230553 - Identification for HVAC Piping and Equipment | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||||||
| 51 | 230593 - Testing, Adjusting, and Balancing for HVAC | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||||
| 52 | 230713 - Duct Insulation | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||||||
| 53 | 230719 - HVAC Piping Insulation | 3 | 10 Days Prior to need approval | |||||||||||||||||||
| 54 | 232113 - Hydronic Piping | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||||||
| 55 | 232114 - Hydronic Specialties | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||||||
| 56 | 232123 - Hydronic Pumps | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||||||
| 57 | 233100 - HVAC Ducts and Casings | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||||||
| 58 | 233300 - Air Duct Accessories | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||||||
| 59 | 233423 - HVAC Power Ventilators | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||||||
| 60 | 233700 - Air Outlets and Inlets | 3 | 10 Days Prior to need approval | |||||||||||||||||||
| 61 | 234000 - HVAC Air Cleaning Devices | 3 | 10 Days Prior to need approval | |||||||||||||||||||
| 62 | 235216 - Condensing Boilers | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||||
| 63 | 236426 - Rotary-Screw Water Chillers | 3 | 3 | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||
| 64 | 237413 - Packaged Outdoor Central-Station Air-Handling Units | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||||||
| 65 | 260010 - Basic Electrical requirements | 3 | 10 Days Prior to need approval | |||||||||||||||||||
| 66 | 260051 - Electrical Related Work | 3 | 10 Days Prior to need approval | |||||||||||||||||||
| 67 | 260170 - Circuit and Motor Disconnects | 3 | 10 Days Prior to need approval | |||||||||||||||||||
| 68 | 260505 - Selective Demolition for Electrical | 10 Days Prior to need approval | ||||||||||||||||||||
| 69 | 260519 - Low-Voltage Electrical Power Conductors and Cables | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||||||
| 70 | 260526 - Grounding and Bonding for Electrical Systems | 3 | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||||
| 71 | 260529 - Hangers and Supports for Electrical Systems | 3 | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||||
| 72 | 260533.13 - Conduit for Electrical Systems | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||||||
| 73 | 260533.16 - Boxes for Electrical Systems | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||||||
| 74 | 260553 - Identification for Electrical Systems | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||||||
| 75 | 260573 - Power System Studies | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||||
| 76 | 260583 - Wiring Connections | 10 Days Prior to need approval | ||||||||||||||||||||
| 77 | 262416 - Panelboards | 10 Days Prior to need approval | ||||||||||||||||||||
| 78 | 262726 - Wiring Devices | 3 | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||||
| 79 | 265100 - Interior Lighting | 3 | 3 | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||
| 80 | 271000 - Structured Cabling | 3 | 3 | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | ||||||||||||||
| 81 | 275121 - Biophilic Audio-Visual Environmental Systems | 3 | 3 | 3 | 3 | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | ||||||||||||
| 82 | 284600 - Fire Detection and Alarm | 3 | 3 | 3 | 3 | 3 | 3 | 3 | 10 Days Prior to need approval | |||||||||||||
| 83 | O and M Manuals | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | Project Closeout | Provide a minimun of 2 hard copy binders and electronic data on two (2) DVDs. Include all warranty information, equipment manuals, test reports, approved submittal information, and other required information cataloged according to section number. |
&L&"Verdana,Bold"&12Schedule of Material Submittals&C&12Print on Legal size paper ( 8 x 14 ).
&R&P of &N Enter the due date from the Contractor (MM/DD/YY) Enter the date received from the Contractor. (MM/DD/YY) Enter the date submittal was given to CE for review. (MM/DD/YY) Enter the date the submittal is due back from CE
(MM/DD/YY)
Enter the Submittal Number Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
Enter Resubmittal Number Enter the submittal final approval date
(MM/DD/YY)