This document contains answers to questions regarding Request for Proposal FA300222R0001 for F-16 International Aircraft Maintenance and Pilot Differences Training. The Air Force will award an Indefinite Delivery Indefinite Quantity contract with a Minimum Obligation Amount Task Order 0001 for training services. Mobilization costs must be captured within existing Unit Price Book line items at the discretion of offerors over a 180 calendar day period. However, mobilization costs cannot be directly invoiced and are not a separate line item. Unit Price Book line items must be fully burdened to include all program management, materials, equipment, labor, facilities, and courseware costs.

View the file

Other files for this federal contract opportunity

Other files attached to F-16 International Aircraft Maintenance and Pilot Differences Training, newest first.
File Type Posted
RFP Questions and Answers 6 with Gov Response.pdf PDF
Attachment 5 TOPR Basis of Estimate Template.xlsx XLSX spreadsheet
Solicitation Amendment FA300222R00010004 SF 30.pdf PDF
Exhibit B Unit Price Book.xlsx XLSX spreadsheet
RFP Questions and Answers 5 with Gov Response.pdf PDF
RFP Questions and Answers 3 with Gov Response.pdf PDF
Attachment 5 TOPR Basis of Estimate Template.xlsx XLSX spreadsheet
Exhibit B Unit Price Book.xlsx XLSX spreadsheet
Attachment 5 TOPR Basis of Estimate Template.xlsx XLSX spreadsheet
Attachment 1 PWS.pdf PDF
Attachment 9 Section M - Evaluation Factors for Award.pdf PDF
Solicitation Amendment FA300222R00010003 SF 30.pdf PDF
Attachment 8 Section L - Instructions to Offerors.pdf PDF
Additional RFP Questions and Answers with Gov Response.pdf PDF
Solicitation Amendment FA300222R00010002 SF 30.pdf PDF
Attachment 1 PWS.pdf PDF
RFP Questions and Answers with Gov Response.pdf PDF
Solicitation Amendment FA300222R00010001 SF 30.pdf PDF
Attachment 4 DD 254.pdf PDF
Attachment 5 TOPR Basis of Estimate Template.xlsx XLSX spreadsheet
Attachment 4 DD 254.pdf PDF
Attachment 3 Data Assertions Table.xlsx XLSX spreadsheet
Solicitation - FA300222R0001.pdf PDF
Exhibit A CDRL.pdf PDF
Attachment 8 Section L - Instructions to Offerors.pdf PDF
Attachment 9 Section M - Evaluation Factors for Award.pdf PDF
Attachment 2 F-16 Task List by Specialty.pdf PDF
Exhibit B Unit Price Book.xlsx XLSX spreadsheet
Attachment 7 Past Performance Questionnaire.pdf PDF
Attachment 6 F-16 Est Req Sched.xlsx XLSX spreadsheet
Attachment 1 PWS.pdf PDF
Show all 31

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

AIR FORCE INSTALLATION CONTRACTING CENTER

20 Dec 21

F-16 International Aircraft Maintenance and Pilot Differences Training – RFP FA300222R0001

Questions and Answers # 4

1. The Answers to Questions re: Mobilization provided, “Due the Foreign Military Sales environment mobilization costs must be captured within the existing UPB line items. . . The means and methods of capturing mobilization costs within the UPB construct as described in Section G is at the discretion of the offeror. Amendment 3 will revise the mobilization period from 120 calendar days to 180 calendar days.”

Question: Will the Task Order be fully-funded upon award such that Mobilization costs are immediately billable?

Answer: No, Mobilization costs are not immediately billable at award of the Minimum Obligation

Amount (MOA) Task Order 0001 nor is Mobilization an individual UPB line item that invoices can be submitted against for awarded training task orders. The UPB will not be modified to add a separate mobilization line item. The means and methods of capturing mobilization costs within the UPB construct as described in Section G is at the discretion of the offeror. Additionally Section G states, “The UPB line items shall be fully burdened and all-encompassing to include but not limited to Program Management, Maintaining Flyable Condition, materials, equipment, labor, facilities, and required courseware.”