Attch_B,_HANGAR 68 MULTIPLE PROJECT-SPECIFICATIONS FINAL.edited20191206.pdf
PDF 4 MB Posted
- Attached to
- Renovate Hangar 68 Fire Suppression
- Solicitation number
- FA282320R0001
About this file
This document outlines a federal contract opportunity for renovating Hangar 68 at Eglin Air Force Base in Florida. Work includes upgrading the fire suppression system across multiple phases and rooms, along with optional additional renovations. Services required are sitework, utilities, fire suppression, abatement, HVAC, plumbing, electrical, and interior finishes. The solicitation is open to full and fair competition, with a NAICS code of 236220 and a 365-day performance period. Offerors must register in SAM and thoroughly review specifications and drawings prior to the question deadline. The solicitation and attachments provide project details, wage determinations, cost estimates, and small business participation requirements.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT NOS.: DWG/SPEC NO.:
FTFA 16-1189 19AA
FTFA 17-1045 19AB
FTFA 17-1126 19AC
FTFA 17-1120 19AD
SPECIFICATIONS
HANGAR 68 MULTIPLE PROJECT RENOVATION
EGLIN AFB, FLORIDA
FTFA-16-1189: REPAIR FIRE SUPPRESSION SYSTEM
HANGAR 68 (PHASES A/B/C/D)
FTFA 17-1045: RENOVATE PORTION OF HANGAR 68
(PHASE B)
FTFA-17-1126: REPAIR RESTROOMS NORTH SIDE AND
ALTER VESTIBULE, HANGAR 68 (PHASE B)
FTFA-17-1120: REPLACE HVAC AND RENOVATE
RESTROOMS SOUTH SIDE, HANGAR 68
(PHASE C)
FINAL SUBMITTAL
16 APRIL 2019
CIVIL ENGINEERING (96 CEG/CEN)
PETERSON ENGINEERING, INC.
75 SOUTH "F" STREET
PENSACOLA, FL 32502
(850) 434-0513
(850) 434-9674 FAX
peterson@petersoneng.com
JOB NO. 17002
Solicitation Amendment 3 Changes dated 06 DEC 19
HANGAR 68 MULTIPLE PROJECT RENOVATION FTFA 16-1189(19AA)/FTFA 17-1045(19AB)
EGLIN AFB, FLORIDA FTFA 17-1126(19AC)/FTFA 17-1120(19AD)
PROJECT TABLE OF CONTENTS Page 1
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 19.01 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS
01 78 00 CLOSEOUT SUBMITTALS
01 91 00.15 TOTAL BUILDING COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
02 82 16.00 20 ENGINEERING CONTROL OF ASBESTOS CONTAINING MATERIALS
02 83 13.00 20 LEAD IN CONSTRUCTION
DIVISION 04 - MASONRY
04 20 00 UNIT MASONRY
DIVISION 05 - METALS
05 40 00 COLD-FORMED METAL FRAMING
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 16 MINERAL FIBER BLANKET INSULATION
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 14 00 WOOD DOORS
08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
DIVISION 09 - FINISHES
09 06 00 SCHEDULES FOR FINISHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 30 10 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 ACOUSTICAL CEILINGS
09 62 38 STATIC-CONTROL FLOORING
09 65 00 RESILIENT FLOORING
09 68 00 CARPETING
09 90 00 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 14 00.20 INTERIOR SIGNAGE
10 21 13 TOILET COMPARTMENTS
10 28 13 TOILET ACCESSORIES
PROJECT TABLE OF CONTENTS Page 2
DIVISION 21 - FIRE SUPPRESSION
21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
21 22 00.00 40 CLEAN AGENT FIRE EXTINGUISHING SYSTEMS
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 23.13 20 BACnet DIRECT DIGITAL CONTROL SYSTEMS FOR HVAC
23 11 25 FACILITY GAS PIPING
23 52 00 HEATING BOILERS
23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE
23 64 26 CHILLED, CHILLED-HOT, AND CONDENSER WATER PIPING SYSTEMS
23 81 23.00 20 COMPUTER ROOM AIR CONDITIONING UNITS
23 82 00.00 20 TERMINAL HEATING AND COOLING UNITS
23 82 02.00 10 UNITARY HEATING AND COOLING EQUIPMENT
DIVISION 26 - ELECTRICAL
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 51 00 INTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76
APPENDICES
APPENDIX A
APPENDIX B
APPENDIX C
APPENDIX D
APPENDIX E
INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
ASBESTOS AND LEAD BASED PAINT SURVEY
MEMORANDUM FOR RECORD SECURITY DOOR
ENGINEERING INSPECTION REPORT – ANECHOIC CHAMBER DOOR
SYSTEM STRUCTURAL INTERIOR DESIGN
Referenced AIR FORCE BPA TYPICALS added
DEPARTMENT OF DEFENSE OZONE DEPLETING SUBSTANCES TURN-IN
PROCEDURES
-- End of Project Table of Contents --
SECTION 01 11 00
SUMMARY OF WORK
01/08
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. DEPARTMENT OF DEFENSE (DOD)
UFC 3-580-01 (2016; with Change 1, 01 Jun 2016) Telecommunications Interior Infrastructure Planning and Design
UFC 3-600-01 (2016; with Change 2, 25 Mar 2018) Fire Protection Engineering for Facilities
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Upon receipt of Government Furnished Equipment, the Contractor shall submit records in accordance with paragraph entitled, "Government Furnished Property," of this section.
Submit the following items to the Contracting Officer:
Utility Outage Requests; G Utility Connection Requests; G
1.3 WORK COVERED BY CONTRACT DOCUMENTS
1.3.1 Project Description
The work under this contract includes a comprehensive renovation of several key spaces and systems within Hangar 68. Work will be completed in phases as outlined below.
1.3.1.1 Phase A
Phase A construction shall concentrate on the main Hangar floor itself.
Work requires the removal of the existing Hangar 68 Anechoic Chamber Halon fire suppression system and replacement with a new clean agent Fire Suppression System. An overhead wet system shall be installed in the Hangar. All new work shall be in accordance with the requirements of UFC 3-600-01. New lighting and receptacles will be installed within the vestibules. Lighting will in general be recessed LED fixtures. Occupancy
SECTION 01 11 00 Page 1 sensors shall be installed throughout as required per UFC and ASHRAE requirements. Lighting levels shall be in accordance with IES and UFC standards. Emergency lighting will be provided via integral emergency drivers within the LED fixtures. Exit lights will be LED type with battery backup.
1.3.1.2 Phase B
Phase B construction shall focus on the North side Lean-to Administrative and Lab spaces. The North side shall include complete Heating, Ventilation, and Air Conditioning (HVAC), Fire Protection, and Restroom upgrades of both the first and second floors, and construction of a new secure, interior vestibule at the existing Northwest entry alcove. The second floor will undergo a complete interior renovation to include new floor, wall, and ceiling finishes as well as fixtures such as toilet partitions and signage.
Rooms include new offices and lab spaces, break room and corridor. New offices will be created, utilizing steel stud and gypsum board partitions for the JPrimes areas. New door openings will be cut through the existing CMU corridor wall as required to access newly configured spaces. A small walkway will be constructed between the existing 2nd floor system and the existing mezzanine. This will be constructed with angle steel bolted to the existing CMU wall and angles, which will transverse to the existing mezzanine. A metal grating system shall be provided to resist vertical loading criteria. Plumbing work shall include providing single compartment stainless steel kitchen sink and wall ice maker valve box and valve provided to control the cold water supply to the refrigerator and providing new drain, waste & vent piping system as indicated on the drawings.
Electrical work shall include new 120/208V panels installed on the second floor to serve new lighting and receptacle loads. Existing 400Hz and 28VDC distribution panels on the second floor shall remain. Interior lighting will in general be recessed LED fixtures. Occupancy sensors shall be installed throughout the as required per UFC and ASHRAE requirements.
Emergency lighting will be provided via integral emergency drivers within the LED fixtures. Exit lights will be LED type with battery backup.
Existing CCTV system monitored by Building 85, shall be protected with connection maintained throughout project's duration. Existing 2nd floor singlemode (SM) fiber optic cable (FOC) shall be extended to new the 2nd floor's new telecom room. All systems will be installed per the UFC requirements, and Eglin 96CS communications standards. Per UFC 3-580-01, all floor mounted equipment racks / cabinets shall be installed at or near the center of the telecommunication room with a minimum of 36 inches space both in front and in back of the rack, measured from the equipment, and a minimum side clearance of 24 inches on at least one end of the rack or row of adjacent racks.
The contractor shall be responsible for the procurement of new FF&E as well as the handling of the existing FF&E. Contractor shall coordinate with the contacting officer's representative for the selection and specification of the FF&E. Refer to Appendix D Structural Interior Design narrative for more information.
1.3.1.3 Phase C
Phase C construction shall focus on the South side Lean-to Administrative and Lab spaces. The South side shall include a complete Heating, Ventilation, and Air Conditioning (HVAC), Fire Protection, and Restroom upgrades of both the first and second floors. Interior renovation work shall be limited to updated restrooms, to include new toilet partitions and new wall, ceiling and floor finishes, and second floor mechanical room
SECTION 01 11 00 Page 2 enlargement. This is necessary due to the size of the new air handler on the second floor. Plumbing work will be limited to work required to support the new HVAC and Fire Suppression systems. Electrical work shall include new electrical distribution to support the new HVAC and Fire Suppression systems on the south side. All new lighting shall be LED with occupancy sensor controls per UFC and ASHRAE requirements. All lighting levels shall be in accordance with IES and UFC standards. Provide incidental related work, as indicated in the contract documents.
1.3.1.4 Phase D
Phase D construction is limited to the final testing of the entire Fire Protection System for Hangar 68.
1.3.2 Location
The work shall be located at Hangar 68, Eglin AFB, as indicated on the drawings. The exact location will be shown by the Contracting Officer.
1.4 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Restore portions of existing work, which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.5 ON-SITE PERMITS
1.5.1 Utility Outage Requests and Utility Connection Requests
Notify the Contracting Officer at least 48 hours prior to starting excavation work. Contractor is responsible for marking and verifying all utilities not marked. Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.
The Contractor shall verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated or specified to be removed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
Work shall be scheduled to hold outages to a minimum.
Utility outages and connections required during the prosecution of work that affect existing systems shall be arranged for at the convenience of the Government and shall be scheduled outside the regular working hours or on weekends.
1.6 LOCATION OF UNDERGROUND FACILITIES
The Contractor shall obtain a fully approved Form 103 "Work Clearance Form" prior to beginning work. Verify elevations before installing new work
SECTION 01 11 00 Page 3 closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.6.1 Notification Prior to Excavation
Notify the Contracting Officer at least 48 hours prior to starting excavation work.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 4
SECTION 01 14 00
WORK RESTRICTIONS
07/07
PART 1 GENERAL
1.1 SPECIAL SCHEDULING REQUIREMENTS
a. Permission to interrupt any Activity roads, railroads, and/or utility service shall be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
1.2 CONTRACTOR ACCESS AND USE OF PREMISES
1.2.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification.
1.2.1.1 Subcontractors and Personnel Contacts
Furnish a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.2.1.2 Identification Badges
All contractors are required to obtain a contractor access badge to be permitted to work on Eglin AFB, and must have it on their person at all times during the performance of the work. Instructions for the contractor badge application process is provided by the Contract Specialist.
Employee Verification: The contract FAR clause 52.222-54 Employment Eligibility Verification is applicable. The E-Verify clause states that contractors are required to enroll as a Federal Contractor in the E-Verify program within 30 calendar days of contract award. Information on registration for and use of the E-Verify program can be obtained via the Internet at the Department of Homeland Security Web site:
http://www.dhs.gov/E-Verify.
1.2.1.3 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installations except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer, with the Site Safety Officer, will identify designated smoking areas.
SECTION 01 14 00 Page 1
1.2.2 Working Hours
Regular working hours shall consist of a period from 7:00am to 5:00pm, Monday through Friday, excluding Government holidays.
1.2.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer's prior approval. Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours.
During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.
1.2.4 Occupied and Existing Building
The existing buildings and their contents shall be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.
1.2.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours."
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours."
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 14 00 Page 2
SECTION 01 32 01.00 10
PROJECT SCHEDULE
08/08
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Schedule; G
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule using AF Form 3064: Contract Progress Schedule. Show in the schedule the sequence in which the Contractor proposes to perform the work and dates on which the Contractor contemplates starting and completing all schedule activities. The scheduling of the entire project, including the design and construction sequences, is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel shall actively participate in its development. Subcontractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool.
The contract progress schedule, AF Form 3064 must be submitted and approved by Civil Engineering and the Contracting Officer prior to any work beginning
3.1.1 Approved Project Schedule
Use the approved Project Schedule, AF Form 3064: Contract Progress Schedule, to measure the progress of the work and to aid in evaluating time extensions. Make the schedule cost loaded and activity coded. The schedule will provide the basis for all progress payments. If the Contractor fails to submit any schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.
3.1.2 Contract Progress Report
Provide a Contract Progress Report on at least a weekly basis. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, take steps necessary to improve its progress including those that may be required by the Contracting Officer, without additional
SECTION 01 32 01.00 10 Page 1 cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.
3.1.3 Default Terms
Failure of the Contractor to comply with the requirements of the Contracting Officer shall be grounds for a determination, by the Contracting Officer, that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of the contract.
3.2 BASIS FOR PAYMENT AND COST LOADING
Use the schedule as the basis for determining contract earnings during each update period and therefore the amount of each progress payment. Lack of an approved schedule update, or qualified scheduling personnel, will result in the inability of the Contracting Officer to evaluate contract earned value for the purposes of payment. Failure of the Contractor to provide all required information will result in the disapproval of the preliminary, initial and subsequent schedule updates. In the event schedule revisions are directed by the Contracting Officer and those revisions have not been included in subsequent revisions or updates, the Contracting Officer may hold retainage up to the maximum allowed by contract, each payment period, until such revisions to the Project Schedule have been made. Activity cost loading shall be reasonable, as determined by the Contracting Officer. The aggregate value of all activities coded to a contract CLIN shall equal the value of the CLIN on the Schedule.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
The computer software system utilized to produce and update the Project Schedule shall be capable of meeting all requirements of this specification. Failure of the Contractor to meet the requirements of this specification will result in the disapproval of the contract progress schedule, AF Form 3064.
3.3.1 Level of Detail Required
Develop the Project Schedule to an appropriate level of detail. Failure to develop the Project Schedule to an appropriate level of detail, as determined by the Contracting Officer, will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.1.1 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Procurement activities are defined herein.
3.3.1.2 Procurement Activities
The schedule must include activities associated with the submittal, SECTION 01 32 01.00 10 Page 2 approval, procurement, fabrication and delivery of long lead materials, equipment, fabricated assemblies and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days. A typical procurement sequence includes the string of activities: submit, approve, procure, fabricate, and deliver.
3.3.1.3 Mandatory Tasks
The following tasks must be included and properly scheduled:
a. Submission and approval of O & M manuals.
b. Submission and approval of as-built drawings in electronic (.dwg and .pdf format).
e. Contractor's pre-final inspection.
f. Correction of punchlist from Contractor's pre-final inspection.
g. Government's pre-final inspection.
h. Correction of punch list from Government's pre-final inspection.
i. Final inspection.
3.3.1.4 Government Activities
Show Government and other agency activities that could impact progress.
These activities include, but are not limited to: approvals, environmental permit approvals by State regulators, inspections, utility tie-in, and Notice to Proceed (NTP).
SECTION 01 32 01.00 10 Page 3
SECTION 01 33 00
SUBMITTAL PROCEDURES
06/10
PART 1 GENERAL
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements. Use transmittal form AF Form 3000: Material Approval Submittal, for submitting in accordance with the instructions on the reverse side of the form. Once received from the Contracting Officer at 96 CEG, the government will have 14-days to review submittals and return AF Form 3000 to the Contracting Officer for approval/disapproval.
Contractor's Quality Control (CQC) System Manager to check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:
Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.
Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. DEPARTMENT OF DEFENSE (DOD)
UFC 1-300-08 (2009, with Change 2) Criteria for Transfer and Acceptance of DoD Real Property
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SECTION 01 33 00 Page 1
SD-01 Preconstruction Submittals
Submittals, which are required prior to issuance of contract notice to proceed, or commencing work on site, or the start of the next major phase of the construction on a multi-phase contract. Includes schedules, tabular list of data, or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.
Certificates of insurance
Surety bonds
List of proposed Subcontractors, submission of SF1413's
Construction Progress Schedule
Submittal register
Health and safety plan
Work plan
Environmental protection plan
All submittals shall be submitted under an US Air Force Form 3000, Material Approval Submittal.
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-04 Samples
Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for
SECTION 01 33 00 Page 2 the project.
Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies, which are to be incorporated into the project and those which will be removed at conclusion of the work.
SD-05 Design Data
Design calculations, mix designs, analyses or other data pertaining to a part of work.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within three years of date of contract award for the project.)
Report that includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report that includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports.
Daily logs and checklists.
Final acceptance test and operational test procedure.
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
Confined space entry permits.
Text of posted operating instructions.
SD-08 Manufacturer's Instructions
Preprinted material describing installation of a product, system or material, including special notices and (MSDS)concerning impedances, hazards and safety precautions.
SD-09 Manufacturer's Field Reports
SECTION 01 33 00 Page 3
Documentation of the testing and verification actions taken by manufacturer's representative at the job site, in the vicinity of the job site, or on a sample taken from the job site, on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must be signed by an authorized official of a testing laboratory or agency and must state the test results; and indicate whether the material, product, or system has passed or failed the test.
Factory test reports.
SD-10 Operation and Maintenance Data
Data that is furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer's help and product line documentation necessary to maintain and install equipment. This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.
This data is intended to be incorporated in an operations and maintenance manual or control system.
SD-11 Closeout Submittals
This project will not be a "Multi-Phase Contract".
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
Interim "DD Form 1354" with cost breakout for all assets 30 days prior to facility turnover.
Comply with DoD, UFC 1-300-08, Criteria for Transfer and Acceptance of Real Property
1.2.2 Approving Authority
Office or designated person authorized to approve submittal.
1.2.3 Work
As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, except those SD-01 Pre-Construction Submittals noted above, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office
SECTION 01 33 00 Page 4 that will review the submittal for the Government. Submit the following in accordance with this section.
SD-01 Preconstruction Submittals
Submittal Register; G
1.4 SUBMITTAL CLASSIFICATION
Submittals are classified as follows:
1.4.1 Government Approved G
Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer.
Government approval is required for any deviations from the Solicitation or Accepted Proposal and other items as designated by the Contracting Officer. Within the terms of the Contract Clause entitled, "Specifications and Drawings for Construction," they are considered to be "shop drawings."
1.4.2 Information Only
Submittals not requiring Government approval will be for information only.
They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.
1.5 FORWARDING SUBMITTALS REQUIRING GOVERNMENT APPROVAL
1.5.1 Submittals Required from the Contractor
As soon as practicable after award of contract, and before procurement of fabrication, forward to the Contracting Officer, submittals required in the technical sections of this specification, including shop drawings, product data and samples. Two copies of the transmittal form shall be provided with each submittal and identify all of the submittal(s) contents to the Contracting Officer.
1.5.1.1 O&M Data
The Contracting Officer for this project will review and approve O&M Data to verify the submittals comply with the contract requirements; submit data specified for a given item within 30 calendar days after the item is delivered to the contract site.
1.6 PREPARATION
1.6.1 Transmittal Form
Use transmittal form AF Form 3000: Material Approval Submittal for each submittal being submitted Government approved and information only submittals in accordance with the instructions on the reverse side of the form. The AF 3000 form can be obtained on line at the web site -http://www.e-publishing.af.mil/. Ensure both pages of the form are provided to the Government with each submission. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.
SECTION 01 33 00 Page 5
1.6.2 Identifying Submittals
When submittals are provided by a Subcontractor, the Prime Contractor is to prepare, review and stamp with Contractor's approval all specified submittals prior to submitting for Government approval.
Identify submittals on an AF Form 3000, except sample installations and sample panels, with the following information permanently adhered to or noted on each separate component of each submittal and noted on transmittal form. Mark each copy of each submittal identically, with the following:
a. Project number, title and location.
b. Construction contract number.
c. Date of the drawings and revisions.
d. Name, address, and telephone number of subcontractor, supplier, manufacturer and any other subcontractor associated with the submittal.
e. Section number of the specification section by which submittal is required.
f. Submittal description (SD) number of each component of submittal.
g. When a resubmission, add alphabetic suffix on submittal description, for example, submittal 18 would become 18A, to indicate resubmission.
h. Product identification and location in project.
1.6.3 Format of SD-01 Preconstruction Submittals and SD-11 Closeout Submittals
When submittal includes a document, which is to be used in project or become part of project record, other than as a submittal, do not apply Contractor's approval stamp to document, but to a separate sheet accompanying document.
1.6.4 Format for SD-02 Shop Drawings
Shop drawings are not to be less than 8-1/2 by 11 inches nor more than 30 by 42 inches, except for full size patterns or templates. Prepare drawings to accurate size, with scale indicated, unless other form is required.
Drawings are to be suitable for reproduction and be of a quality to produce clear, distinct lines and letters with dark lines on a white background.
Present A4 8-1/2 by 11 inches sized shop drawings as part of the bound volume for submittals required by section. Present larger drawings in sets.
Include on each drawing the drawing title, number, date, and revision numbers and dates, in addition to information required in paragraph entitled, "Identifying Submittals," of this section.
Number drawings in a logical sequence. Contractors may use their own number system. Each drawing is to bear the number of the submittal in a uniform location adjacent to the title block. Place the Government contract number in the margin, immediately below the title block, for each drawing.
SECTION 01 33 00 Page 6
Reserve a blank space, on the right hand side of each sheet for the Government disposition stamp.
Dimension drawings, except diagrams and schematic drawings; prepare drawings demonstrating interface with other trades to scale. Use the same unit of measure for shop drawings as indicated on the contract drawings.
Identify materials and products for work shown.
Include the nameplate data, size and capacity on drawings. Also, include applicable federal, military, industry and technical society publication references.
1.6.5 Format of SD-03 Product Data and SD-08 Manufacturer's Instructions
Present product data submittals for each section as a complete, bound volume. Include table of contents, listing page and catalog item numbers for product data.
Indicate, by prominent notation, each product, which is being submitted;
indicate specification section number and paragraph number to which it pertains.
Supplement product data with material prepared for project to satisfy submittal requirements for which product data does not exist. Identify this material as developed specifically for project, with information and format as required for submission of SD-07 Certificates.
Include the manufacturer's name, trade name, place of manufacture, and catalog model or number on product data. Also, include applicable federal, military, industry and technical society publication references. Should manufacturer's data require supplemental information for clarification, submit as specified for SD-07 Certificates.
Where equipment or materials are specified to conform to industry and technical society reference standards of the organizations such as American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), and Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance. In lieu of the label or listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the Contracting Officer.
State on the certificate that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.
Collect required data submittals for each specific material, product, unit of work, or system into a single submittal and marked for choices, options, and portions applicable to the submittal. Mark each copy of the product data identically. Partial submittals will not be accepted for expedition of construction effort.
Submit manufacturer's instructions prior to installation.
1.6.6 Format of SD-04 Samples
Furnish samples in sizes below, unless otherwise specified or unless the manufacturer has prepackaged samples of approximately same size as
SECTION 01 33 00 Page 7 specified:
a. Sample of Equipment or Device: Full size.
b. Sample of Materials Less Than 2 by 3 inches: Built up to A4 8-1/2 by 11 inches.
c. Sample of Materials Exceeding A4 8-1/2 by 11 inches: Cut down to A4 8-1/2 by 11 inches and adequate to indicate color, texture, and material variations.
d. Sample of Linear Devices or Materials: 10 inch length or length to be supplied, if less than 10 inches. Examples of linear devices or materials are conduit and handrails.
e. Sample of Non-Solid Materials: Pint. Examples of non-solid materials are sand and paint.
f. Color Selection Samples: 2 by 4 inches. Where samples are specified for selection of color, finish, pattern, or texture, submit the full set of available choices for the material or product specified. Sizes and quantities of samples are to represent their respective standard unit.
g. Sample Panel: 4 by 4 feet.
h. Sample Installation: 100 square feet.
Samples Showing Range of Variation: Where variations in color, finish, pattern, or texture are unavoidable due to nature of the materials, submit sets of samples of not less than three units showing extremes and middle of range. Mark each unit to describe its relation to the range of the variation.
Reusable Samples: Incorporate returned samples into work only if so specified or indicated. Incorporated samples are to be in undamaged condition at time of use.
Recording of Sample Installation: Note and preserve the notation of area constituting sample installation but remove notation at final clean up of project.
When color, texture or pattern is specified by naming a particular manufacturer and style, include one sample of that manufacturer and style, for comparison.
1.6.7 Format of SD-05 Design Data and SD-07 Certificates
Provide design data and certificates on 8-1/2 by 11 inches paper. Provide a bound volume for submittals containing numerous pages.
1.6.8 Format of SD-06 Test Reports and SD-09 Manufacturer's Field Reports
Provide reports on 8-1/2 by 11 inches paper in a complete bound volume.
Indicate by prominent notation, each report in the submittal. Indicate specification number and paragraph number to which it pertains.
SECTION 01 33 00 Page 8
1.7 QUANTITY OF SUBMITTALS
1.7.1 Number of Copies of SD-01 Preconstruction Submittals and SD-11 Closeout Submittals
Unless otherwise specified, submit two sets of administrative submittals.
1.7.2 Number of Copies of SD-02 Shop Drawings
Submit six copies of submittals of shop drawings requiring review and approval only by QC organization and seven copies of shop drawings requiring review and approval by Contracting Officer.
1.7.3 Number of Copies of SD-03 Product Data and SD-08 Manufacturer's Instructions
Submit in compliance with quantity requirements specified for shop drawings.
1.7.4 Number of Samples SD-04 Samples
a. Submit two samples, or two sets of samples showing range of variation, of each required item. One approved sample or set of samples will be retained by approving authority and one will be returned to Contractor.
b. Submit one sample panel or provide one sample installation where directed. Include components listed in technical section or as directed.
c. Submit one sample installation, where directed.
d. Submit one sample of non-solid materials.
1.7.5 Number of Copies SD-05 Design Data and SD-07 Certificates
Submit in compliance with quantity requirements specified for shop drawings.
1.7.6 Number of Copies SD-06 Test Reports and SD-09 Manufacturer's Field Reports
Submit in compliance with quantity and quality requirements specified for shop drawings other than field test results that will be submitted with QC reports.
1.7.7 Number of Copies of SD-10 Operation and Maintenance Data
Submit six copies of O&M Data to the Contracting Officer for review and approval.
1.8 INFORMATION ONLY SUBMITTALS
Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals.
The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work;
and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the
SECTION 01 33 00 Page 9
Government in those instances where the technical specifications so prescribe.
1.9 VARIATIONS
Variations from contract requirements require both Designer of Record (DOR) and Government approval pursuant to contract Clause FAR 52.236-21 and will be considered where advantageous to Government.
1.9.1 Considering Variations
Discussion with Contracting Officer prior to submission, after consulting with the DOR, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation, which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).
Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.
1.9.2 Proposing Variations
When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item.
Clearly mark the proposed variation in all documentation.
Set forth in writing the reason for any deviations and annotate such deviations on the submittal. The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.
1.9.3 Warranting That Variations Are Compatible
When delivering a variation for approval, Contractor, including its Designer(s) of Record, warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.9.4 Review Schedule Is Modified
In addition to normal submittal review period of 14 calendar days, a period of 10 working days will be allowed for consideration by the Government of submittals with variations.
1.10 SUBMITTAL REGISTER
Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and (i) as approved. A submittal register showing items of equipment and materials for which submittals are required by the specifications is provided as an attachment. This list may not be all inclusive and additional submittals may be required. Prepare and maintain submittal register, as the work progresses.
SECTION 01 33 00 Page 10
Column (c): Lists specification section in which submittal is required.
Column (d): Lists each submittal description (SD No. and type, e.g. SD-02 Shop Drawings) required in each specification section.
Column (e): Lists one principal paragraph in specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements.
Column (f): Indicate approving authority for each submittal.
1.10.1 Use of Submittal Register
Submit submittal register. Submit with QC plan and project schedule.
Verify that all submittals required for project are listed and add missing submittals. Coordinate and complete the following fields on the register submitted with the QC plan and the project schedule:
Column (a) Activity Number: Activity number from the project schedule.
Column (g) Contractor Submit Date: Scheduled date for approving authority to receive submittals.
Column (h) Contractor Approval Date: Date Contractor needs approval of submittal.
Column (i) Contractor Material: Date that Contractor needs material delivered to Contractor control.
1.10.2 Contractor Use of Submittal Register
Update the following fields with each submittal throughout contract.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.
Column (l) List date of submittal transmission.
Column (q) List date approval received.
1.10.3 Approving Authority Use of Submittal Register
Update the following fields.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (l) List date of submittal receipt.
Column (m) through (p) List Date related to review actions.
Column (q) List date returned to Contractor.
SECTION 01 33 00 Page 11
1.10.4 Government Review Action Codes Contractor Action Code and Action Code
Entries for columns (j) and (o), are to be used are as follows (others may be prescribed by Transmittal Form):
"A" - "Approved as submitted"; "Completed"
"B" - "Approved, except as noted on drawings"; "Completed"
"C" - "Approved, resubmission required"; "Resubmit"
"D" - "Returned by correspondence"; "Completed"
"E" - "Disapproved (See attached)"; "Resubmit"
"F" - "Receipt acknowledged"; "Completed"
"G" - "Other (Specify)"; "Resubmit"
"X" - "Receipt acknowledged, does not comply"; "Resubmit"
1.11 SCHEDULING
Schedule and submit concurrently submittals covering component items forming a system or items that are interrelated. Include certifications to be submitted with the pertinent drawings at the same time. No delay damages or time extensions will be allowed for time lost in late submittals.
a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.
b. Submittals called for by the contract documents will be listed on the register. If a submittal is called for but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but which have been omitted from the register or marked "N/A."
c. Re-submit register and annotate monthly by the Contractor with actual submission and approval dates. When all items on the register have been fully approved, no further re-submittal is required.
d. Carefully control procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."
e. Except as specified otherwise, allow review period, beginning with receipt by approving authority that includes at least 15 working days for submittals for QC Manager approval and 20 working days for submittals for Contracting Officer approval. Period of review for submittals with Contracting Officer approval begins when Government receives submittal from QC organization.
f…