This document contains a schedule of material submittals and a solicitation for replacing parking lot light poles at Glen Air Force Base. The schedule outlines 17 submittal line items required from the contractor, including project plans, structural and electrical components, O&M manuals, as-built drawings, and warranties. Key due dates range from award through project completion.

The solicitation seeks replacement of parking lot light poles at Glen Air Force Base under contract number FA255019RA016. A pre-bid site visit will be held on September 13, 2019, with questions due by September 18, 2019. Contractors must be bondable and not debarred. The selected contractor must provide signed SF1442 and acknowledge any amendments. Proposals are due as specified in the SF1442.

AF66, Material Submittal Schedule, for GLEN 17-1702 Parking Lot Light Poles solicitation.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Submittal 1

SCHEDULE OF MATERIAL SUBMITTALSPROJECT NUMBERPROJECT NAMESOLICITATION /CONTRACT NUMBER
GLEN 17-1702Replace parking Lot Light Poles
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
LINE NUMBERLINE ITEMCERTIFICATE OF COMPLIANCEAS-BUILT DRAWINGSCOLOR SELECTIONMANUFATURUR'S RECOMMENDATIONCATALOG DATAO&M RECOMMENDATIONSCALCULATIONSWARRANTYDRAWINGSREPORTTEST RESULTSREQUIRED SUBMISSION DATEDATE TO CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSAPPROVEDDISAPPROVEDCONTRACTOR SUBMITTALFINAL APPROVALREMARKS
GENERAL
1Project Specific MSDS Sheets1AWARD+30
2Form-3064 Contract Progress Schedule1AWARD+30
3Form-3065 Contract Progress Report1AWARD+30
4Health, Safety, and Environment Plan(s)1AWARD+30
Contractor's QC Plan1AWARD+30
Fatory Calculation for Poles1AWARD+30
5Work Phase Plan1AWARD+30
STRUCTURAL
6Grout Mix/Product Data for Base1AWARD+30
7Reinforcing Steel Mill Certifications1AWARD+30
8Slump Test results & Concrete Truck Tickets17 days after work
97-Day Concrete Compressive Strength Test117 days after work
MECHANICAL
10Pole eraction plan1NTP + 30
11Lighting fixture installation plan1NTP + 30
ELECTRICAL
12Wires1NTP + 30
13Swtches1NTP + 30
14Panels1NTP + 30
15Breakers1NTP + 30
16Lighting poles1NTP + 30
17Lighting Fixtures1NTP + 30
CLOSEOUT
18O&M Maintainance data, manuals and Manufacturer's Warranties1at completion
19As Built Submittal1at completion