Patrick AFB demo projects site visit--modcopy
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PAFB Sign In Sheet.pdf | ||
| CCAFS Prebid Site Visit Minutes and Question.docx | DOCX document | |
| Prebid_Signin Sheet.PDF | ||
| question with Answers as of 1 Sep 09.docx | DOCX document | |
| 09R0064 Conformed as of Amend 0003.doc | DOC document | |
| Amendment 0003.doc | DOC document | |
| Amend2Conformedcopy.doc | DOC document | |
| CCAFS Specs-Drawings other docs.zip | ZIP file | |
| question with Answers as of 20 Aug 09.docx | DOCX document | |
| FA2521-09-R-0064amend1conformed.doc | DOC document | |
| FA2521-09-R-0064Amend1mod.doc | DOC document | |
| SXHT 01-1229 Dwg Sht 2.zip | ZIP file | |
| SXHT 01-1229 Specs Part 3.zip | ZIP file | |
| SXHT 09-1051 Specs Part 2.zip | ZIP file | |
| SXHT 09-1051 Dwg Sheet 3.zip | ZIP file | |
| RFP 09-R-0064.doc | DOC document | |
| Hazardous Waste Generation Form.doc | DOC document | |
| SXHT 05-1252 Dwg Sht 2.zip | ZIP file | |
| SXHT 08-1095 Specs Part 3.zip | ZIP file | |
| DBA WD F17 Rev 15 as of 10 Jul 09.docx | DOCX document | |
| SXHT 05-1252 Specs Part 3.zip | ZIP file | |
| SXHT 08-1095 Dwg Sheet 1.zip | ZIP file |
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS
The following have been modified:
INSTRUCTION TO OFFERORS
SECTION L-5
L-500
TYPE OF ACQUISITION
THIS ACQUISITION IS 100% Competitive Hubzone set-aside.
L-501
INFORMATION REGARDING SITE VISIT,
PREPARATION AND SUBMISSION OF OFFERS
NOTICE OF PRE-BID/PRE-PROPOSAL CONFERENCE (SITE VISITS)
1.
a. A pre-bid/pre-proposal (site visit) conference will be held at 2:00pm ET, 25 August 2009, at the 45th Contracting Squadron, Bldg 1704, 2nd flr, room #2101, Cape Canaveral AFS, FL for the purpose of answering questions regarding this solicitation. The site visits will follow. For escorted access attendees must arrive at the main gate visitor center NO LATER THAN 1:15pm to ensure processing for escorted entry badges to CCAFS.
b. Entry procedures for CCAFS is rigid and the following procedure is required for escorted entry. Submit legible copies of proof of citizenship (birth certificate, voter's registration card or passport), a copy of social security card and a copy of driver's license along with a copy of CCAFS Temporary Pass Request (completing BADGE INFORMATION section – Attachment 6 of this solicitation) for each person requesting a badge , not to exceed 2 personnel to Carl Davison ((321) 853-0877). Information may be faxed to (321) 853-0904, or e-mailed to carl.davison@patrick.af.mil at prior to 3:00pm ET, 21 August 2009. This information must be provided in advance in order to ensure access to the military base/conference site and adequate seating for the conference. CCAFS security will perform a criminal history check for each badge request.
c. Bidders/Offerors are requested to submit questions to the point of contact noted above not later than 09:00am ET, 23 August 2009. Information provided at this conference shall not qualify the terms and conditions of the solicitation and specifications. Terms of the solicitation and solicitation remain unchanged unless the solicitation is amended in writing. If an amendment is issued, normal procedures relating to the acknowledgment and receipt of solicitation amendments shall apply.
d. A record of the conference shall be made and posted on www.fbo.gov. The record should include minutes of the meeting, including questions (on a non-attribution basis) and answers.
e. See FAR provision 52.236-27 in Section L above for information regarding the site visit. Offeror should note the contract clause 52.236-3 "Site Investigation and Conditions Affecting the Work."
2.
a. A pre-bid/pre-proposal conference will be conducted at 9:00am ET, 26 August 2009, at 45th Contracting Squardron, Patrick AFB, FL for the purpose of answering questions regarding Patrick AFB demo projects in this solicitation.
b. Submit the names of all attendees exactly as they appear on drivers license, date of birth, social security number and if U.S. citizen, not to exceed 2 personnel to Mr. Richard Becker at (321) 494-1913 prior to 2:00pm ET, 25 August 2009. This information must be provided in advance in order to ensure access of the military base/conference site and adequate seating for the conference.
c. Bidders/Offerors are requested to submit questions to the point of contact noted above not later than 9:00am ET, 25 Aug 2009. Information provided at this conference shall not qualify the terms and conditions of the solicitation and specifications. Terms of the solicitation and solicitation remain unchanged unless the solicitation is amended in writing. If an amendment is issued, normal procedures relating to the acknowledgment and receipt of solicitation amendments shall apply.
d. A record of the conference shall be made and posted on www.fbo.gov.. The record should include minutes of the meeting, including questions (on a non-attribution basis) and answers.
e. See FAR provision 52.236-27 in Section L above for information regarding the site visit. Offeror should note the contract clause 52.236-3 "Site Investigation and Conditions Affecting the Work."
f. Original and (1) copy of the proposal package must be completed and returned to the 45 CONS/LGCAA, Attn FA2521-09-R-0064, 1201 Edward H. White II Street, Bldg 423, Room C202, Patrick AFB, FL 32925-3238 prior to the time set for proposal closing. HANDCARRIED PROPOSALS MUST BE DEPOSITED IN THE BID DEPOSITORY LOCATED THEREIN. See SF1442, Block 13A
L-102 N O T I C E
Offerors are cautioned that Patrick AFB has stringent visitor control procedures requiring individuals not affiliated with the installation to obtain a visitor pass and be cleared by the Government point of contact to be visited prior to entrance. IT IS POSSIBLE THAT THE POINT OF CONTACT MAY NOT BE AVAILABLE TO CLEAR OFFERORS FOR ENTRANCE WHICH MAY PROHIBIT SUBMISSION OF HANDCARRIED OFFERS; CONSEQUENTLY, OFFERORS ELECTING TO HANDCARRY THEIR PROPOSALS FOR SUBMITTAL JUST PRIOR TO PROPOSAL CLOSING TIME DO SO AT THEIR OWN RISK. Late proposals will be processed in accordance with the provision 52.215-1 entitled "Instructions to Offerors--Competitive Acquisitions."
L-103
AMENDMENT OF SOLICITATION PRIOR TO PROPOSAL CLOSING TIME
The Government reserves the right to revise or amend the specifications, drawings or the solicitation prior to the proposal closing time. Such revisions or amendments, will be communicated by amendments to this Request For Proposal. If such amendments require material changes in quantities or prices, the proposal closing date may be postponed by enough days to enable offerors to revise their proposals. In such cases, the amendment will include an announcement of the new proposal closing date and time. Amendments will be posted on the Internet with the solicitation documents without notice. Offerors are responsible for accessing all amendments prior to proposal submission at www.fbo.gov.
L-104
POSTPONEMENT OF PROPOSAL CLOSING DATE
a. An amendment postponing proposal closing may be issued even after the time scheduled for proposal closing, under the following conditions:
(1) When the Contracting Officer has reason to believe that the offers of an important segment of offerors have been delayed in the mail for causes beyond their control and without their fault or negligence (such as, but not limited to, flood, fire, accident, weather conditions or strikes); or
(2) When emergency or unanticipated events interrupt normal governmental processes so that conducting proposal closing as scheduled is impracticable.
b. At the time a determination is made to postpone a proposal closing under subparagraph a(1), above, an announcement of the determination shall be publicly posted and, if practicable before issuance of formal amendment of the RFP, otherwise communicated to prospective offerors.
c. In the case of subparagraph a(2) above, the Contracting Officer may proceed with the proposal evaluation as soon as practicable after the time scheduled, without prior amendment to the RFP or Notice to Offerors whenever the delay incident to such amendment or notice is not in the best interest of the Government. In such case, the time of actual proposal closing shall be deemed to be the time set for proposal closing for the purpose of determining late proposals.
L-105
PROPOSAL PREPARATION INSTRUCTIONS
(a) General Format and Content
1. All proposals shall be complete, self-sufficient, and respond directly to the requirements of this solicitation. A proposal is defined as one, which will include separate volumes as specified below.
2. Submitted volumes and areas shall be fully responsive to and consistent with the following:
(a) Requirements of the RFP and Specifications contained therein;
(b) Federal laws, regulations and standards pertaining to the specifications;
(c) Instructions to offerors in Section L;
(d) Evaluation factors for award in Section M.
(b) Specific Requirements
1. Volume I – Past and Present Performance.
(a) Contractors' past and present performance will be obtained from the Construction Contractor Appraisal Support System (CCASS), which includes performance information for DoD construction contracts in excess of $500,000, in addition to other sources. Performance data from all military service is maintained in this system. Only government employees can access the system. In addition to whatever past/present performance data for a contractor is found in CCASS, the Government will consider contractors’ past and present performance of other relevant contracts they have recently performed. The Government may seek additional past and present performance data from other automated and non-automated sources as well. Therefore, contractors must provide the information identified in paragraphs (b) through (i) below for any contracts that they desire the Government to recognize in the evaluation of past and present performance. In addition to the prime contractors performancer information, past and present performance information will also be sought on subcontractors, teaming partners, joint ventures and other companies that are part of the proposal.
(b) Provide data as specified in paragraph “f” below. This requirement also applies to all proposed first tier subcontractors, teaming partners, and joint ventures.
(c) Past and present performance, for the purpose of satisfying the above requirement, means quality of work, essentially comparable to this acquisition. Current contracts or subcontracts completed within the past three (3) years will be considered RECENT. RELEVANT contracts are contracts of similar size and complexity and have a logical connection with the work being acquired, whether or not it was government work or commercial work. If your firm has provided relevant and recent past/present performance documentation to Patrick AFB FL in response to other solicitations within the last six (6) months, a letter referencing the RFP number(s) and title(s) can be provided in lieu of providing Volume I. Identify the corporate division that performed the contract/subcontract, if applicable.
(d) In describing contractual effort and the contractors’ performance, include specific details of technical performance (actual performance versus required performance), actual quality or reliability versus specified levels; security deviations, violations, compromises; performance incentives and award fee earned versus total award fee pool, etc.); management performance in meeting program schedules and milestones; and cost performance (under or overruns, cost incentives earned or lost, etc.). The discussion should include "lessons learned" or a description of any corrective action taken to prevent recurrence of past performance listed and considered substandard, and a narration or recitation of how the past performance may benefit this program.
(e) The Past and Present Performance Volume may be provided to the government or commercial points of contact for verification. Past and present performance information on recent contracts not listed by the contractors, or that of previous or planned subcontractors, may also be solicited directly from the ACO or other authoritative government or commercial sources. Verification of past and present performance information may also be handled telephonically. The Past and Present Performance Volume shall include a list of all customers to whom Past and Present Performance Customer Surveys were provided, including current point of contact and phone number.
(f) Provide a comprehensive list of all recent and relevant contracts as defined above in paragraph c, over the past three- (3) years. If you believe a classified project is significant for this proposal, then simply state "Classified" where appropriate and provide points of contract. Include the following:
1. Contract Number
2. Total dollar value (original and Final)
3. Contracting Agency
4. Title of Contract
5. Government program manager (name, address, phone number)
6. Description of program/project
7. PCO and ACO (name, address, and phone number)
8. Period of performance
9. Type of Contract (Firm Fixed Price, Fixed Price Incentive, Cost Plus Fixed Fee, Cost Plus Award Fee, etc.)
(g) Provide the Past and Present Performance (Volume 1) at least 10 calendar days prior to, but not later than, the proposal closing date.
(h) Customer Satisfaction Surveys. Contractors shall provide the reproducible Present and Past Performance Customer Survey form, located as a attachment to L, to its customers for direct response back to the Government. The Present and Past Performance Information obtained directly from contractors’ customers will be used, in addition to information from other sources, to evaluate contractors’ past and present performance in accordance with the criteria set forth in Section M of this solicitation. Completed Customer Satisfaction Surveys sent directly to the Government from any offeror will not be considered in the evaluations.
(i) It is the responsibility of contractors to ensure that their customers complete Customer Satisfaction Surveys for all projects that are to be considered in the evaluation of a contractor’s present/past performance and to ensure that its customers send such completed surveys directly to the Contracting Office not later than the date and time established for receipt of proposals. Any Customer Satisfaction Surveys received after the closing date for receipt of offers shall be deemed to be a late modification or revision to a proposal, within the meaning of FAR 52.215-1, Instructions to Offerors, and will not be considered, except as allowed in that provision.
2. Volumes 2 - SF 1442, Proposal Schedule, Section K Representations and Certifications, Section G, & Section I
Fill in the proposal schedule. Complete the Representations and Certifications as required in Section K. Fill in blanks, when appropriate in Section G and Section I.
3. Volume 3 - Financial Data
Submit financial data in a separate volume to include the following:
(a) Names, addresses and points of contact for all financial institution organizations utilized to determine if contractor has adequate financial resources to perform the contract or the ability to obtain them.
(b) Written authority to contact the provided financial institution
L-106
PUBLIC OPENING OF PROPOSALS
Offers will not be publicly opened at the time set for proposal closing in the Request for Proposal. Their content will not be made public to the offerors until after award.
L-107 PROPOSAL SUBMISSION
a. Submit your proposal in accordance with paragraph L-105 and SF1442, block 13A.
b. Submit your past/present performance in accordance with paragraph L-105 and SF 1442, block 13A
c. Payment in advance of installation for stored materials on site if applicable will not be considered under this contract.
d. All proposals delivered in response to this solicitation shall reflect the following information on the address label:
Solicitation Number FA2521-09-R-0064.
The legend “To be delivered unopened to the Contracting Officer” and
The volume and copy numbers contained in each box.
e. Submit your proposal to the address reference in Block 7 of the SF 1442.
L-108. SEQUENCE OF EVENTS DURING PROPOSAL EVALUATION
The following describes the sequence of events offerors can expect during proposal evaluation and negotiation:
a. The Air Force will employ PERFORMANCE PRICE TRADE-OFF (PPT) techniques to evaluate proposals and determine the successful offeror in this acquisition.
b. Upon receipt of the offerors' Past and Present Performance history Proposals, they will be reviewed for completeness and compliance with RFP requirements. They will receive detailed evaluation employing the criteria identified in Section M (or the “M” clauses) of this RFP.
c. Any exchanges with offerors after receipt of proposals will be conducted in accordance with FAR 15.306.
d.. The Government reserves the right to make an award based upon initial offers received, without discussion with offerors. The Contracting Officer may conduct negotiations and/or request final proposal revisions.
L-109 CENTRAL CONTRACTOR REGISTRATION SYSTEM (CCRS)
All contractors doing business with the Department of Defense (DOD) must register with the CCR. The CCR applies to all contractors; those doing business electronically and those who are not. Contractors not registered in the CCRS will not be eligible for contract award in accordance with DFARS 252.204-7004. Register with CCR by contacting the Defense Logistics Agency (DLA) at one of the following:
Address:
Department of Defense
ATTN: Central Contractor Registration
74 West Washington Avenue, Suite 7
Battle Creek, MI 49017
Telephone: 1-888-227-2423
FAX 269-961-7243
e-mail ccr.dlis.dla.mil
Web Site www.ccr.gov
PAST AND PRESENT PERFORMANCE QUESTIONNAIRE
FA2521-09-R-0064
A. GENERAL INFORMATION: Please correct any information below known to be inaccurate:
Contractor’s Name: ____________________ Telephone Number: ____________________
Address: __________________________ Fax Number: _________________________
__________________________ Point of Contact: ______________________
(The government enters the following information based on list of references provided by the offeror. The offeror will enter this information if the solicitation requires him to submit questionnaires to the references.)
Project Title and Brief Description of Work: _____________________________________*
Contract Number Provided by Offeror: ___________________ Dollar Amount: ________*
Contract Period or Dates of Performance Provided by Offeror: ______________________* Contractor performed as the ( Prime Contractor ( Sub-Contractor ( Key Personnel.
* Note: If offeror holds or has held other contracts with your agency/organization in the last 3 years, please complete separate evaluation forms for those contracts as well.
B. RESPONDENT INFORMATION:
Name of Respondent:
_____________________ Title: ____________________________
Address: _____________________
Telephone Number: ___________________
Fax Number:
Email Address: _____________________
C. FAX COMPLETED SURVEY FORM TO: _________________, Contracting Officer at (321) 494-6193
D. PERFORMANCE INFORMATION: Choose the appropriate letter on the scale (E, G, S, M, U, and N) that most accurately describes the contractor’s performance or situation. PLEASE PROVIDE A NARRATIVE EXPLANATION FOR ANY RATINGS OF M or U.
| E |
| G |
| S |
| M |
| U |
| N |
| Exceptional |
| Good |
| Satisfactory |
| Marginal |
| Unsatisfactory |
| Neutral |
Performance meets contractual requirements with many exceeded to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with no more than a few minor problems for which corrective actions taken by the contractor were highly effective.
Performance meets contractual requirements with some exceeded to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with no more than some minor problems for which corrective actions taken by the contractor were effective.
Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor were satisfactory.
Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions or the contractor’s proposed actions appear only marginally effective or were not fully implemented.
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
Performance was not observed or not applicable to the current effort being reported against.
CONTRACTOR’S NAME: _______________ CONTRACT NUMBER: _______________
Note: Include this information on each page of the questionnaire form to ensure there is no mix up in information among contracts surveyed for respective primes/subs, etc.
Place an “X” in the appropriate column using the definitions matrix above.
| The contractor: |
| E |
| G |
| S |
| M |
| U |
| N |
| 1. |
| Provided experienced managers and supervisors with the technical and administrative abilities needed to meet contract requirements. |
| 2. |
| Demonstrated ability to hire, maintain, and replace, if necessary, qualified personnel during the contract period. |
| 3. |
| Delegated authority to project managers and supervisors commensurate with contract requirements. |
| 4. |
| Home office participated in solving significant local problems. |
| 5. |
| Compliance with Davis-Bacon Act and EEO requirements to include Payrolls properly completed and submitted |
| 6. |
| Provided effective quality control and/or inspection procedures to meet contract requirements. |
| 7. |
| Corrected deficiencies in timely manner and pursuant to their quality control procedures. |
| 8. |
| Provided timely resolution of contract discrepancies. |
| 9. |
| Identified problems as they occurred. |
| 10. |
| Suggested alternative approaches to problems. |
| 11. |
| Displayed initiative to solve problems. |
| 12. |
| Developed realistic progress schedules and stay on schedule . |
| 13. |
| Completion of punch-list items. |
| 14. |
| Provided timely resolution of warranty defects. |
| 15. |
| Was responsive to contract changes. |
| 16. |
| Adequacy of site clean up- all work and storage areas are cleaned and secured at end of each day |
| 17. |
| Effectiveness of jobsite supervision – site is safe and secure, clear line of supervision. |
| 18. |
| Obtained consent of surety for increases in bonding as work-in-progress increased. |
| 19. |
| Paid subcontractors/suppliers in a timely manner. |
| 20. |
| Use of Specified Materials – contractor used specified or equal material or products |
| 21. |
| Cooperated with Government personnel after award. |
| 22. |
| How would you rate the contractor's overall performance? |
| 23. |
| Was the contractor ever issued a cure or show cause notice under the referenced contract? If yes, explain outcome in “remarks.” |
| YES/NO |
| 24. |
| Would you award another contract to this contractor? If not, explain in “remarks.” |
| YES/NO |
| 25. |
| Is the contractor rated in CCAS? |
| YES/NO |
CONTRACTOR’S NAME: ___________________ CONTRACT NUMBER __________
Remarks:_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
(End of Summary of Changes)