Attachment 12a - RKMF200083 - Electrical As-Builts Sunshades 31-34.pdf

PDF 2 MB Posted

Attached to
57 WG Sunshades Nellis AFB
Solicitation number
F3G3AA3111AW01
Issued by

View the file

Other files

File Type Posted
Attachment 8 - Conduit Fill Calculation.pdf PDF
Attachment 7 - Sunshades Q and A 8 June 2023.pdf PDF
Attachment 10a - Electrical Power for Sunshades 20-22.pdf PDF
Attachment 5a - Sunshade Locations 23 and 24.pdf PDF
Attachment 5b - Sunshade Locations 23 24 39.pdf PDF
Combo - F3G3AA3111AW01 Sunshades - Amendment 4.pdf PDF
Attachment 10 - Electrical Power for Sunshades 17-19.pdf PDF
Attachment 9 - MSB One Line for Sunshades 13-34.pdf PDF
Attachment 11 - RKMF200146 - Flood Lights and Receptacles for Sunshades.pdf PDF
Attachment 12b - RKMF200084 - Electrical As-Builts Sunshades 41-46.pdf PDF
Attachment 12 - RKMF210070 - Electrical As-Builts Sunshades 23-24.pdf PDF
Attachment 1a - Statement of Work 31 May 23.pdf PDF
Combo - F3G3AA3111AW01 Sunshades - Amendment 3.pdf PDF
Attachment 6 - Sunshades Q and A 2 Sep 2022 Amendment 1.pdf PDF
Attachment 3a - Drawings for Reference.PDF PDF
Attachment 2 - Lighting Spec Sheet.pdf PDF
Combo - F3G3AA3111AW01 Sunshades.pdf PDF
Attachment 6 - Sunshades Q and A 2 Sep 2022.pdf PDF
Attachment 5 - Sunshade Rows Map Location.PNG PNG image
Attachment 1 - Statement Of Work 29 March 23.pdf PDF
Attachment 3 - As Built for Reference.pdf PDF
Attachment 4 - UFC 3.575.01 July 1 2012.pdf PDF
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RKMF 20-0083

NELLIS AIR FORCE BASE

NEVADA

SCHEDULE OF DRAWINGS

SHEET REFERENCE NUMBER SHEET TITLE

G-1 COVER PAGE, HAUL ROUTE

G-2 GENERAL NOTES

G-3 SITE PLAN

CD-1 CIVIL DEMO ROWS 31 - 34

C-1 CIVIL DETAILS

E-1 POWER PLAN ROWS 31 -34

INSTALL ELECTRICAL POWER

FOR FLIGHT LINE SUNSHADES

BASE CIVIL ENGINEERING

(BLDG 812)

NORTH GATE

SECURITY POLICE

(BLDG 2)

MAIN GATE

CONTRACTING OFFICE

(BLDG 588)

TYNDALL GATE

N

E

S

W

FIRE DEPT

(BLDG 277)

A B C D E F G H

SHEET

REFERENCE

NUMBER

ANSI

D

AF PROJECT NUMBER:

AEC FILE NAME:

DRAWING SCALE:

PLOT SCALE:

SYMBOL DATE DESCRIPTION

REVISIONS

F I L E

N

O

NELLIS AFB, NEVADA

DESIGNED BY:

DRAWN BY:

CHECKED BY:

PROJ. ENG.

1:1

AF CONTRACT NUMBER:

INV. NUMBER:

BUILDING OR FACILITY:

DATE APPR

DATE:

DATE:

DATE:

DATE:

DEPARTMENT OF THE AIR FORCE

NELLIS AFB, NEVADA

INSTALL ELEC. PWR FOR SUNSHADES

ROWS 31-34

COVER PAGE, HAUL ROUTE

AS SHOWN

20-0083

RKMF200083G01

WELDIN

WELDIN

WELDIN

WELDIN

G-1

8/11/21

9/19/19

9/19/19

9/19/19

9/19/19

AS-BUILT

RECORD

DRAWINGS

HAUL ROUTE

PROJECT LOCATION

ROWS 31 THRU 34

A B C D E F G H

SHEET

REFERENCE

NUMBER

ANSI

D

AF PROJECT NUMBER:

AEC FILE NAME:

DRAWING SCALE:

PLOT SCALE:

SYMBOL DATE DESCRIPTION

REVISIONS

F I

NELLIS AFB, NEVADA

DESIGNED BY:

DRAWN BY:

CHECKED BY:

PROJ. ENG.

1:1

AF CONTRACT NUMBER:

INV. NUMBER:

BUILDING OR FACILITY:

DATE APPR

DATE:

DATE:

DATE:

DATE:

DEPARTMENT OF THE AIR FORCE

NELLIS AFB, NEVADA

INSTALL ELEC. PWR FOR SUNSHADES

ROWS 31-34

GENERAL NOTES

AS SHOWN

20-0083

RKMF200083G02

WELDIN

WELDIN

WELDIN

WELDIN

G-2

8/11/21

9/19/19

9/19/19

9/19/19

9/19/19

AS-BUILT

RECORD

DRAWINGS

SECTION 3: DESCRIPTIONS OF WORK

Install Electrical Power for Flight Line Sunshades. Install all work in accordance with specifications in Nellis SABER Contract. All materials, supplies, and debris shall be completely removed from the job site prior to final inspection. The work to be accomplished includes the following description

3.1 GENERAL REQUIREMENTS – DIVISION 1

3.1.1 Contractor to perform weekly coordination meetings at a convenient time for the user and contractor.

3.1.2 The construction sites shall be swept daily or as required to keep flight line clear of soil and debris (FOD).

3.1.3 If Contractor personnel do not have Restricted Area Badges, then escorts will be required for this project.

3.2 EXISTING CONDITIONS – DIVISION 2

3.2.1 Remove existing concrete apron, asphalt and landscaping for trenching and conduit placement. The main trench in the apron to be 5’ in width. Minimize trench saw cutting in the apron and roadways. The concrete is at least 12” ±-(2”) thick in most places on apron and 6” in roadway.

3.2.2 Provide and install a temporary 6’ fence with entrance and exit gates around work area, one area at a time.

3.2.3 Provide temporary low profile barricades to direct traffic around work site area.

3.3 CONCRETE – DIVISION 3

3.3.1 Remove and replace concrete apron for trenching and conduit placement. Concrete shall be in accordance with specifications for air field pavements.

3.3.2 3” Core through wall and fence where needed in and around Bldg. 285 for 2” PVC conduit to run out of building and provide power to sunshades.

3.3.3 The concrete for the apron shall be Mix #844 650PSI Flex designed mix.

3.4 ELECTRICAL – DIVISION 26

3.4.1 Remove and replace concrete apron for trenching and conduit placement. Minimize trench saw cutting in the apron. The concrete is at least 12” ±-(2”) thick in most places. Conduit shall be a min. 12” below bottom of concrete.

3.4.2 All conduit in trench shall have a sand bedding and cover.

ROWS 31, 32, 33 & 34

3.4.3 For rows 31 thru 34 provide and install a 100A/3P disconnect switch the on the side of the terminal compartment of the service transformer to building/hangar 295.

3.4.4 Terminate line side conductors (3#2) on low voltage terminals of the transformer.

3.4.5 Route 2” schedule 80 PVC conduit w/3#2 along wall of building conductors to a 100A/480VAC panelboard 225A enclosure and buss, w/3P-100A main breaker) mounted on wall of the portion of building/hangar 285 next to Flight Line Road.

3.4.6 Contractor to trench for new conduit along the exterior wall of building 290 from transformer to wall at the Flight line. From there the contractor shall feed the four apron sunshades on rows 31, 32, 33 and 34.

3.4.7 Provide and install 3-40A/3P breakers to feed the existing sunshades and one spare 40A/3P breaker.

3.4.8 Provide and install four sets of 2” schedule 80 PVC with 4 #4 in each conduit and route to each of the sunshades on rows 31, 32, 33 and 34.

3.4.9 At each sunshade provide and install a 60A/3p disconnect as well as

3.4.10At each sunshade provide and install a 30KVA 3P/480-208Y/120VAC Dry Type transformer. The Disconnect shall be in a NEMA 12 enclosure. The dry type transformers shall have

NEMA 3R outdoor/weatherproof enclosures

3.4.11The four electrical panelboards at each of the sunshades shall be mounted at approximately 72” to top of panelboard. The panelboard itself shall have a NEMA 12 dustproof enclosure. It shall be a column type along the lines of the Eaton 2a-LX style with 100A/3P copper buss and main breaker.

3.5 COMMUNICATIONS – DIVISION 27

3.5.1 Provide and install one 4” schedule 80 PVC and 100,000 lbs. rated pullboxes in the same trench as electrical conduit for Communications. This conduit will be run to each sunshade that the electrical conduit is being ran to, however to a separate pole. The conduit will go no further than the last sunshades being provided with power in this project.

3.5.2 Provide and install an 18” x 24” pullbox on an existing pole at each sunshade to terminate the 4” conduit in to.

3.5.3 Terminate the communication conduit on the wall in front of building 285 in an 18” x 24” pullbox next to existing communication box.

3.6 EXTERIOR IMPROVEMENTS – DIVISION 32

3.6.1 Provide and install 4 each 6” surface mount, bolt down bollards at each row the electrical and communication conduit will be ran to. Install 3 each bollards for the electrical and 1 each bollard for the communication.

3.6.2 Provide and install 4” asphalt paving where removed for trenching.

SCALE: 1"=300'-0"

OVERALL SITE PLAN

N

ES

W

A B C D E F G H

SHEET

REFERENCE

NUMBER

ANSI

D

AF PROJECT NUMBER:

AEC FILE NAME:

DRAWING SCALE:

PLOT SCALE:

SYMBOL DATE DESCRIPTION

REVISIONS

F I

NELLIS AFB, NEVADA

DESIGNED BY:

DRAWN BY:

CHECKED BY:

PROJ. ENG.

1:1

AF CONTRACT NUMBER:

INV. NUMBER:

BUILDING OR FACILITY:

DATE APPR

DATE:

DATE:

DATE:

DATE:

DEPARTMENT OF THE AIR FORCE

NELLIS AFB, NEVADA

INSTALL ELEC. PWR FOR SUNSHADES

ROWS 31-34

SITE PLAN

AS SHOWN

20-0083

RKMF200083G03

WELDIN

WELDIN

WELDIN

WELDIN

G-3

8/11/21

9/19/19

9/19/19

9/19/19

9/19/19

AS-BUILT

RECORD

DRAWINGS

SHEET E-2 ROWS 31 - 34

R O

W

R O

W

R O

W

R O

W

AutoCAD SHX Text

BUILDING 878

AutoCAD SHX Text

BUILDING 880

AutoCAD SHX Text

BUILDING 882

AutoCAD SHX Text

BUILDING 297

AutoCAD SHX Text

BUILDING 295

AutoCAD SHX Text

BUILDING 292

AutoCAD SHX Text

BUILDING 290

AutoCAD SHX Text

BUILDING 285

AutoCAD SHX Text

BUILDING 286

AutoCAD SHX Text

BUILDING 294

AutoCAD SHX Text

BUILDING 284

AutoCAD SHX Text

BUILDING 282

AutoCAD SHX Text

BUILDING 283

AutoCAD SHX Text

BUILDING 277

AutoCAD SHX Text

BUILDING 276

AutoCAD SHX Text

BUILDING 270

AutoCAD SHX Text

BUILDING 259

AutoCAD SHX Text

BUILDING 262

AutoCAD SHX Text

BUILDING 260

AutoCAD SHX Text

BUILDING 257

AutoCAD SHX Text

BUILDING 253

AutoCAD SHX Text

BUILDING 255

AutoCAD SHX Text

BUILDING 256

AutoCAD SHX Text

BUILDING 252

AutoCAD SHX Text

BUILDING 250

AutoCAD SHX Text

BUILDING 245

AutoCAD SHX Text

BUILDING 248

AutoCAD SHX Text

BUILDING 246

AutoCAD SHX Text

BUILDING 244

AutoCAD SHX Text

BUILDING 241

AutoCAD SHX Text

BUILDING 239

AutoCAD SHX Text

BUILDING 237

AutoCAD SHX Text

BUILDING 233

AutoCAD SHX Text

BUILDING 234

AutoCAD SHX Text

BUILDING 236

AutoCAD SHX Text

BUILDING 238

AutoCAD SHX Text

BUILDING 879

AutoCAD SHX Text

BUILDING 877

AutoCAD SHX Text

BUILDING 285

AutoCAD SHX Text

BUILDING 882

AutoCAD SHX Text

BUILDING 290

AutoCAD SHX Text

BUILDING 295

AutoCAD SHX Text

BUILDING 283

AutoCAD SHX Text

BUILDING 277

AutoCAD SHX Text

BUILDING 256

AutoCAD SHX Text

BUILDING 253

AutoCAD SHX Text

BUILDING 244

AutoCAD SHX Text

SUNSHADE 13

AutoCAD SHX Text

SUNSHADE 14

AutoCAD SHX Text

SUNSHADE 15

AutoCAD SHX Text

SUNSHADE 16

AutoCAD SHX Text

SUNSHADE 17

AutoCAD SHX Text

SUNSHADE 18

AutoCAD SHX Text

SUNSHADE 19

AutoCAD SHX Text

SUNSHADE 20

AutoCAD SHX Text

SUNSHADE 21

AutoCAD SHX Text

SUNSHADE 22

AutoCAD SHX Text

SUNSHADE 23

AutoCAD SHX Text

SUNSHADE 32

AutoCAD SHX Text

SUNSHADE 33

AutoCAD SHX Text

SUNSHADE 34

AutoCAD SHX Text

SUNSHADE 40

AutoCAD SHX Text

SUNSHADE 41

AutoCAD SHX Text

SUNSHADE 42

AutoCAD SHX Text

SUNSHADE 43

AutoCAD SHX Text

SUNSHADE 44

AutoCAD SHX Text

FUTURE SUNSHADE 24

AutoCAD SHX Text

FUTURE SUNSHADE 25

AutoCAD SHX Text

FUTURE SUNSHADE 26

AutoCAD SHX Text

FUTURE SUNSHADE 28

AutoCAD SHX Text

FUTURE SUNSHADE 29

AutoCAD SHX Text

FUTURE SUNSHADE 27

AutoCAD SHX Text

FUTURE SUNSHADE 30

AutoCAD SHX Text

FUTURE SUNSHADE 31

AutoCAD SHX Text

FUTURE SUNSHADE 35

AutoCAD SHX Text

FUTURE SUNSHADE 36

AutoCAD SHX Text

FUTURE SUNSHADE 37

AutoCAD SHX Text

FUTURE SUNSHADE 39

AutoCAD SHX Text

FUTURE SUNSHADE 38

POINT OF

CONNECTION IN

EXISTING

ELECTRICAL ROOM

ROW 31

ROW 32

ROW 34

ROW 33

START OF

TRENCH

NEW 480V

PANEL ON

WALL

SCALE: 1"=60'-0"

TRENCH LAYOUT ROWS 31 - 34

1 N

ES

W

A B C D E F G H

SHEET

REFERENCE

NUMBER

ANSI

D

AF PROJECT NUMBER:

AEC FILE NAME:

DRAWING SCALE:

PLOT SCALE:

SYMBOL DATE DESCRIPTION

REVISIONS

F I

NELLIS AFB, NEVADA

DESIGNED BY:

DRAWN BY:

CHECKED BY:

PROJ. ENG.

1:1

AF CONTRACT NUMBER:

INV. NUMBER:

BUILDING OR FACILITY:

DATE APPR

DATE:

DATE:

DATE:

DATE:

DEPARTMENT OF THE AIR FORCE

NELLIS AFB, NEVADA

INSTALL ELEC. PWR FOR SUNSHADES

ROWS 31-34

CIVIL DEMO PLAN

AS SHOWN

20-0083

RKMF200083CD1

WELDIN

WELDIN

WELDIN

WELDIN

CD-1

8/11/21

9/19/19

9/19/19

9/19/19

9/19/19

AS-BUILT

RECORD

DRAWINGS

SHEET NOTES:

LEGEND

NOT IN CONTRACT

0 60' 120' 180'

SCALE: 1" = 60'

30'

DEMOLITION NOTES

1. CONTRACTOR TO VERIFY LOCATION AND SIZE OF EXISTING

EQUIPMENT FOR DEMOLITION, RELOCATION AND POINT OF

CONNECTION

2. THE CONSTRUCTION SIGHT WILL BE SWEPT DAILY OR AS

NEEDED TO KEEP THE FLIGHT LINE CLEAR OF SOIL AND

DEBRIS (FOD)

3. ESCORTS WILL BE REQUIRED FOR THIS PROJECT

4. ASPHALT CUTS ARE APPROX. 4" THICK

5. CONCRETE VEHICLE ROAD CUTS ARE APPROX. 8" THICK

6. CONCRETE APRON CUTS ARE APPROX. 12"± 2" THICK

DEMOLISH EXISTING CONCRETE, ASPHALT, AND

LANDSCAPING AS NEED TO TRENCH FOR ELECTRICAL

CONDUIT

DEMOLISH EXISTING CONCRETE, ASPHALT AS NEEDED

TO INSTALL NEW COMM & POWER PULL BOX

CORE DRILL EXISTING BLDG AS NEEDED TO INSTALL

SURFACE MOUNT CONDUIT FROM ELECTRICAL ROOM TO

SIDE OF BLDG TO START UNDER GROUND WORK

DEMOLISH EXISTING CONCRETE, ASPHALT, AS NEED TO

TRENCH FOR COMMUNICATION CONDUIT

AutoCAD SHX Text

BUILDING 286

AutoCAD SHX Text

BUILDING 294

AutoCAD SHX Text

BUILDING 284

AutoCAD SHX Text

BUILDING 282

AutoCAD SHX Text

BUILDING 283

AutoCAD SHX Text

BUILDING 285

AutoCAD SHX Text

BUILDING 290

AutoCAD SHX Text

SUNSHADE 32

AutoCAD SHX Text

SUNSHADE 33

AutoCAD SHX Text

SUNSHADE 34

AutoCAD SHX Text

FUTURE SUNSHADE 30

AutoCAD SHX Text

FUTURE SUNSHADE 31

AutoCAD SHX Text

FUTURE SUNSHADE 35

FUTURE SUNSHADE 36

6" CONCRETE

FILLED BOLLARD

EXISTING

CONCRETE

" BOLT WITH 4"

MIN EMBEDMENT

10"

SQ

7"

" BOLT (TYP)

EXISTING

CONCRETE OR

A.C. PAVEMENT

UNDISTURBED

SOIL

COMPACTED SOIL FROM

EXCAVATION SPOILS

SAND BEDDING

AND COVER

4" CONDUIT

2'

NEW

CONCRETE

DEPTH VARIES

12" -16"

MIN.

8"

4" TYPE 2 UNDER

CONCRETE

NOTE: RUN COMM TRENCH 4" DEEPER THAN POWER TRENCH WERE

THEY CROSS EACH OTHER

EXISTING

CONCRETE OR

A.C. PAVEMENT

UNDISTURBED

SOIL

COMPACTED SOIL FROM

EXCAVATION SPOILS

2'

NEW

CONCRETE

DEPTH VARIES

12" MIN.

8"

4" TYPE 2 UNDER

CONCRETE

(5) 2" CONDUIT

SAND BEDDING

AND COVER

EXISTING

CONCRETE OR

A.C. PAVEMENT

UNDISTURBED

SOIL

COMPACTED SOIL FROM

EXCAVATION SPOILS

(5) 2" CONDUIT

5'

NEW

CONCRETE

DEPTH VARIES

12" MIN.

8"

4" TYPE 2 UNDER

CONCRETE

(1) 4" CONDUIT

SAND BEDDING

AND COVER

TO POWER

VAULT AT ROW

NEW 100A 3P

PANEL

NEW POWER

SERVICE RACK

NEW BOLLARD

(TYP)

NEW 60A 3P DISCONNECT

NEW 30 KVA 3P

480-208Y/120VAC

TRANSFORMER

EXISTING

SUNSHADE POLE

EXISTING

CONCRETE

NEW COMM

BOX

TO COMM

VAULT AT ROW

NEW CONCRETE PAD

EXISTING

SUNSHADE POLE

NEW BOLLARD

(TYP)

NEW COMM

SERVICE RACK

1" DIA DOWELS 20"

LONG @12" O.C.

EXISTING

CONCRETE

NEW 45OO PSI

CONCRETE

CONTROL JOINT

SEE DETAIL A

CONTROL JOINT

SEE DETAIL A

1/2" ± 1/8"

2 1/2"

SAW 1/4" GROOVE

SEAL WITH JOINT

SEALANT

DETAIL A

SCALE: NTS

BOLLARD DETAIL

SCALE: NTS

MAIN TRENCH DETAIL

SCALE: NTS

COMM TRENCH DETAIL

SCALE: NTS

POWER TRENCH DETAIL

SCALE: NTS

SERVICE / COMM ELEVATION AT SUNSHADES

SCALE: NTS

CONCRETE DETAIL

A B C D E F G H

SHEET

REFERENCE

NUMBER

ANSI

D

AF PROJECT NUMBER:

AEC FILE NAME:

DRAWING SCALE:

PLOT SCALE:

SYMBOL DATE DESCRIPTION

REVISIONS

F I

NELLIS AFB, NEVADA

DESIGNED BY:

DRAWN BY:

CHECKED BY:

PROJ. ENG.

1:1

AF CONTRACT NUMBER:

INV. NUMBER:

BUILDING OR FACILITY:

DATE APPR

DATE:

DATE:

DATE:

DATE:

DEPARTMENT OF THE AIR FORCE

NELLIS AFB, NEVADA

INSTALL ELEC. PWR FOR SUNSHADES

ROWS 31-34

CIVIL DETAILS

AS SHOWN

20-0083

RKMF200083C01

WELDIN

WELDIN

WELDIN

WELDIN

C-1

8/11/21

9/19/19

9/19/19

9/19/19

9/19/19

AS-BUILT

RECORD

DRAWINGS

POINT OF

CONNECTION IN

EXISTING

ELECTRICAL ROOM

ROW 31

ROW 32

ROW 34

ROW 33

START OF

TRENCH

NEW 480V

PANEL ON

WALL

EXISTING

COMM

MANHOLE

#294

NEW COMM

PULL BOX

ROW 31

NEW ELEC

PULL BOX

ROW 31

NEW COMM

BOX ROW 31

4" COMM

CONDUIT

NEW

TRANSFORMER

ROW 31

NEW COMM

PULL BOX

ROW 32

NEW ELEC

PULL BOX

ROW 32

NEW COMM

BOX ROW 32

4" COMM

CONDUIT

NEW

TRANSFORMER

ROW 32

NEW COMM

PULL BOX

ROW 33

NEW ELEC

PULL BOX

ROW 33

4" COMM

CONDUIT

NEW COMM

PULL BOX

ROW 34

NEW ELEC

PULL BOX

ROW 34

4" COMM

CONDUIT

EXISTING

SERVICE MDS

BLDG 285

NEW

ELEC

LB

NEW

ELEC

LB

NEW

ELEC

LB

NEW 100A/480VAC

PANELBOARD

NEW

BUCKET SWITCH

IN MDS

NEW COMM

BOX ROW 33

NEW

TRANSFORMER

ROW 33

NEW COMM

BOX ROW 34

NEW

TRANSFORMER

ROW 34

4" COMM

CONDUIT

2"

POWER

CONDUIT

4" COMM

CONDUIT

PNL ROW 31

100A MCB

10KAIC

2" CONDUIT

WITH #1 GAUGE

NEW

DISCONNECT

SWITCH

PNL ROW 31

100A MCB

10KAIC

NEW

DISCONNECT

SWITCH

PNL ROW 31

100A MCB

10KAIC

NEW

DISCONNECT

SWITCH

PNL ROW 31

100A MCB

10KAIC

NEW

DISCONNECT

SWITCH

2" CONDUIT

WITH #4 GAUGE

2" CONDUIT

WITH #4 GAUGE

2" CONDUIT

WITH #4 GAUGE

2" CONDUIT

WITH #2 GAUGE

EXISTING

COMM MH294

SCALE: 1"=60'-0"

POWER PLAN ROWS 31 - 34

N

ES

W

A B C D E F G H

SHEET

REFERENCE

NUMBER

ANSI

D

AF PROJECT NUMBER:

AEC FILE NAME:

DRAWING SCALE:

PLOT SCALE:

SYMBOL DATE DESCRIPTION

REVISIONS

F I

NELLIS AFB, NEVADA

DESIGNED BY:

DRAWN BY:

CHECKED BY:

PROJ. ENG.

1:1

AF CONTRACT NUMBER:

INV. NUMBER:

BUILDING OR FACILITY:

DATE APPR

DATE:

DATE:

DATE:

DATE:

DEPARTMENT OF THE AIR FORCE

NELLIS AFB, NEVADA

INSTALL ELEC. PWR FOR SUNSHADES

ROWS 31-34

POWER PLAN

AS SHOWN

20-0083

RKMF200083E01

WELDIN

WELDIN

WELDIN

WELDIN

E-1

8/11/21

9/19/19

9/19/19

9/19/19

9/19/19

AS-BUILT

RECORD

DRAWINGS

SHEET NOTES:

CONSTRUCTION NOTES

LEGEND

NOT IN CONTRACT

0 60' 120' 180'

SCALE: 1" = 60'

30'

1. CONTRACTOR TO VERIFY LOCATION AND SIZE OF EXISTING

EQUIPMENT FOR DEMOLITION, RELOCATION AND POINT OF

CONNECTION

2. THE CONSTRUCTION SIGHT WILL BE SWEPT DAILY OR AS

NEEDED TO KEEP THE FLIGHT LINE CLEAR OF SOIL AND

DEBRIS (FOD)

3. ESCORTS WILL BE REQUIRED FOR THIS PROJECT

4. ASPHALT CUTS ARE APPROX. 4" THICK

5. CONCRETE VEHICLE ROAD CUTS ARE APPROX. 8" THICK

6. CONCRETE APRON CUTS ARE APPROX. 12"± 2"THICK

1 INSTALL NEW DRY TYPE TRANSFORMER FOR EACH ROW

2 INSTALL NEW CONCRETE ELECTRICAL PULL BOX FOR

EACH ROW

SCALE: NTS

CONDUIT LAYOUT 31 - 34

4 INSTALL NEW 100A PANEL FOR EACH ROW

5 INSTALL NEW BOLT DOWN BOLLARDS FOR EACH ROW

6 INSTALL 4" SCH 80 CONDUIT FOR COMMUNICATIONS

3 INSTALL NEW CONCRETE COMMUNICATION PULL BOX

FOR EACH ROW

7 INSTALL 2" SCH 80 CONDUIT FOR POWER

8 INSTALL NEW COMM BOX FOR EACH ROW

9 ROUTE CONDUIT ON EXTERIOR OF BLDG 285 UNTIL

YOU GET TO THE SIDEWALK SIDE IN BETWEEN BLDG

285 & BLDG 290

10 NEW 100A/480VAC PANEL BOARD WITH 225A ENCLOSURE

AND BUS WITH 3P-100A BREAKER

1 4 5

1 4 5

1 4 5

1 4 5

11 INSTALL NEW DISCONNECT SWITCH

12 INSTALL NEW 4" COMMUNICATIONS CONDUIT TO BE

ROUTED BEHIND BLDG 285 TO EXISTING

COMMUNICATIONS MANHOLE #294

AutoCAD SHX Text

BUILDING 286

AutoCAD SHX Text

BUILDING 294

AutoCAD SHX Text

BUILDING 284

AutoCAD SHX Text

BUILDING 282

AutoCAD SHX Text

BUILDING 283

AutoCAD SHX Text

BUILDING 285

AutoCAD SHX Text

BUILDING 290

AutoCAD SHX Text T

AutoCAD SHX Text T

AutoCAD SHX Text T

T

RKMF200083G01
RKMF200083G01-G-1
RKMF200083G02
RKMF200083G02-G-2
RKMF200083G03
RKMF200083G03-G-3
RKMF200083CD1
RKMF200083CD1-CD-1
RKMF200083C01
RKMF200083C01-C-1
RKMF200083E01
RKMF200083E01-E-1