Attachment_7_-_Construction_ _Demolition_Waste_Management.pdf

PDF 89 KB Posted

Attached to
Design/Build Repair Roof B1025
Solicitation number
F2K2AC4029A001-1
Issued by

View the file

Other files

File Type Posted
Amendment_4.pdf PDF
Q_ _A.pdf PDF
Amendment_3.pdf PDF
Amendment_2.pdf PDF
Amendment_1.pdf PDF
Site_Visit_Sign-in_Sheet_2_Apr_14.pdf PDF
Attachment_18_-_Wage_Determination_NM140040_1-3-2014_NM40.pdf PDF
Attachment_17_-_Quiroga-Pfeiffer_Structural_Report_-_B1025_Roof_Loading_Analysis.pdf PDF
Attachment_12_-_AF_Form_3065__Progress_Report.pdf PDF
SF_Form_1442_-_Solicitation.pdf PDF
Attachment_2_-_95__Design_Guide_Submittal.pdf PDF
Attachment_14_-_AF_Form_66_-_Schedule_of_Material_Submittals.xls XLS spreadsheet
Attachment_16_-_DUSD(IE)_SECTION_438_EISA_2007_Policy_Memo_Signed_19_Jan_2010.pdf PDF
Attachment_20_-_Building_1025_Map.pdf PDF
Attachment_5_-_AF_LEED_SDD_Implementation_Guidance.pdf PDF
Attachment_11_-_AF_Form_3064_-_Progress_Schedule.xls XLS spreadsheet
Attachment_21_-_Kirtland_AFB_Map.pdf PDF
Attachment_3_-_Architectural_Compatibility_Plan_(ACP)_Dated_2_Oct_2010.pdf PDF
Attachment_10_-_Past_Performance_Information_Form.docx DOCX document
Attachment_19_-_Wage_Determination_NM140013_1-3-2014_NM13.pdf PDF
Attachment_13_-_AF_Form_3000-_Material_Approval_Submittal.pdf PDF
Attachment_1_-_Statement_of_Work_(SOW)_Dated_17_Dec_2013_-_Design-Build_Repair_Roof_B1025.pdf PDF
Attachment_8_-_AF_Form_3052_-_Contractor_Proposal_Form_Base_Bid.xlsx XLSX spreadsheet
Attachment_6_-_Waste_Summary_-_01_74_19_Appendix_A.xls XLS spreadsheet
Attachment_15_-_DD_Form_1354_-_Transfer_and_Acceptance_of_DoD_Real_Property.pdf PDF
Attachment_9_-_AF_Form_3052_-_Contractor_Proposal_Form_Additive.xlsx XLSX spreadsheet
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

[Insert Project Title]

MHMV[X]

Section 01 74 19

SECTION 01 74 19

CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

04/12

PART 1 - GENERAL

1.1 SUMMARY

KAFB’s waste management goals include increased recycling and conservation of materials. Construction and Demolition (C&D) debris has been identified as a particular target for reuse and recycling for several reasons:

a. Meeting the 60% (by weight) diversion rate goal for C&D debris as set by the DoD Strategic Sustainability Performance Plan under Executive Order 13514

(October 2009);

b. Many of the waste streams generated during C&D projects are highly recyclable at reasonable prices;

c. Diverting C&D debris for reuse and recycling lengthens the life of

Kirtland’s on-base C&D landfill;

d. Maximizing source reduction, reuse, and recycling of C&D debris protects the environment, both on-site and off-site, during project operations, and prevents environmental pollution and damage.

1.2 RELATED SPECIFICATION SECTIONS

01 33 00 – Submittal Procedures

01 35 40.00 20 - Environmental Management

01 45 00.10 20 – Quality Control for Minor Construction

01 78 00 – Closeout Submittals

1.3 DEFINITIONS

Definitions pertaining to sustainable development: As defined in ASTM E2114.

1.4 QUALITY ASSURANCE

A. Maximize use of source reduction and recycling procedures.

B. Diversion Goals: Diversion shall be maximized within the scope and budget of each individual project. Diversion shall be measured as a percent by weight of total solid waste generated by the project.

1. The following list of materials must be recycled, salvaged, or re-used, without approved annotation on the Waste Management

Plan. The Contractor is encouraged to identify and propose additional materials for consideration for recycling, salvage, or reuse as applicable to this project.

a. Asphalt

b. Concrete, including concrete block, concrete masonry units(CMU), and rocks

c. Asphalt concrete (“blacktop”)

d. Brick

e. Paper, including bond, newsprint, cardboard, mixed paper, packing materials, and packaging

f. Plastics

g. Carpet and carpet pad

h. Beverage containers

i. Gypsum wallboard, unpainted

j. Fluorescent lamps, per New Mexico Environment Department regulations (20.4.1.1000 NMAC and 20.4.1.1001 NMAC)

k. Green materials (e.g. tree trimmings and land clearing debris).

l. Metals, ferrous and non-ferrous, including but not limited to: stud trim, ductwork, piping, reinforcing steel (rebar), roofing, other trim, steel, iron, galvanized sheet steel, stainless steel, aluminum, copper, zinc, lead, brass, and bronze.

m. Wood, including clean dimensional lumber, clean hardwoods, and pallet wood.

1.5 SUBMITTALS

The following shall be submitted in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

A. Solid Waste Management Plan

1. Immediately after receipt of Notice of Award of Bid, and prior to preconstruction conference, the Contractor shall submit a

Draft Solid Waste Management Plan. The Draft Solid Waste

Management Plan shall contain, at minimum:

a. A list of the project wastes expected to be generated, by type and approximate quantity.

b. Disposal options: The name and location of all landfill(s) proposed for trash disposal, a copy of the permit or license for each facility. Identify materials that cannot be recycled or reused, and provide justification for each material.

c. Alternatives to Landfill Disposal: A list of each material proposed to be salvaged, reused, or recycled during the course of the Project, the proposed end use or market for each material (including name, location, and copy of license).

d. Reporting: A sample Summary of Waste report including, at minimum, the information required in Section 1.5 (B).

See Attachment Two for an example of this report.

e. The Draft Solid Waste Management Plan shall include, at a minimum, the relevant materials included in Section 1.3 that are required to be considered for diversion.

2. Following the submittal of the Draft Solid Waste Management Plan, Government will review the Plan and either approve or return with comments. Among these comments there may be suggested alternatives to the proposed disposal options in order to increase recycling, reduce costs, or both.

file://kafbfs00ce/CMSJV%20Active%20Projects/100070C%20-%20Repair%20Wyoming%20PHIII%20-%20H%20to%20Gibson/Specs/01%2033%2000.doc

3. Once all comments have been addressed and resolved, the Contractor shall submit a Final Waste Management Plan. The

Final Waste Management Plan shall contain the following:

a. List of the proposed jobsite wastes to be generated, including types and approximate quantities.

b. Disposal options: The name and location of all landfill(s) to be used for trash disposal.

c. Alternatives to Landfilling: A list of the waste materials from the Project that will be separated for reuse, salvage, or recycling.

d. Markets: A list of the market(s) or other on-site or off-site end use(s) that will be used for each material that will be separated for reuse, salvage, or recycling.

B. Progress Documentation: Document solid waste disposal and diversion.

1. The Contractor shall submit with each Application for Progress Payment a Summary of Waste generated by the Project. Failure to submit this information shall render the Application for Payment incomplete and shall delay Progress Payment. The Summary shall be submitted on a form approved by the Owner and shall contain the following information:

a. The amount (in tons) of material landfilled from the

Project and the identity of the landfill. Attach manifests, weight tickets, receipts, and invoices, or other documentation that will validate the amounts listed.

b. For each material recycled, reused, or salvaged from the Project, the amount (in tons), the date removed from the jobsite, and the receiving party. Attach manifests, weight tickets, receipts, and invoices, or other documentation that will validate the amounts listed.

C. Record Submittals. With Record Submittals as specified in Section 01 78 00, submit the following:

1. Summary of solid waste disposal and diversion. Submit on form approved by Owner.

PART 2 – PRODUCTS

PART 3 – EXECUTION

3.1 SOLID WASTE MANAGEMENT

A. Develop and implement a Waste Management Plan as specified herein.

B. Implementation.

1. Manager: The Contractor shall designate a specific party (or parties) responsible for instructing workers in recycling and overseeing and documenting results of the Final Waste Management

Plan for the Project.

2. Instruction: The Contractor or his designated waste manager shall provide on-site instruction regarding appropriate separation, handling, and recycling, salvage, reuse, and/or return methods to be used by all involved parties at the appropriate stages of the

Project.

3. Separation facilities: As appropriate during each stage of the Project, the Contractor shall lay out and label a specific area(s) to facilitate separation of materials for potential recycling, salvage, reuse, and return. Recycling and waste bin areas are to be kept neat and clean and clearly marked in order to avoid contamination of materials.

4. Hazardous wastes: Hazardous wastes shall be separated and disposed of IAW federal, state, and local regulations. Coordinate with

Section 01 41 00.

C. Maximize recycling and reuse of materials. The following is a partial list of resources that may be useful in developing the Waste

Management Plan. This list is provided for Contractor’s information only. For more information, contact the New Mexico Environment

Department and/or the New Mexico Recycling Coalition.

1. Recycling Haulers and Markets. An extensive list of New Mexico haulers and markets for recyclable materials is available on-line at the following URL:

http://www.recyclenewmexico.com/Construction_Recycling.htm. This list is provided for information only and may not comprehensive;

other haulers and markets may also be available.

2. Sample Solid Waste and Recycling Plan. A sample plan is available on-line at the following URL:

http://www.recyclenewmexico.com/pdf/APPENDIX_D_SAMPLE_Recycling_Man agement_Plan.pdf. This plan is provided for information only and may not be comprehensive for a given project. Contractor is to adapt this plan to this project.

--End of Section--http://www.recyclenewmexico.com/Construction_Recycling.htm http://www.recyclenewmexico.com/pdf/APPENIX_D_SAMPLE_Recycling_Management_Plan.pdf http://www.recyclenewmexico.com/pdf/APPENIX_D_SAMPLE_Recycling_Management_Plan.pdf