About this file

This document is a Work Write-Up for a furnace and air conditioning replacement project issued by the City of Jackson, Michigan, for a residential property located at 138 W Addison Street. The project involves replacing the existing furnace with a new 95% efficient, gas-fired forced air furnace that meets Michigan Mechanical Code standards, along with installing a new AC unit with an Energy Star rating. The work includes comprehensive HVAC system modifications such as installing new registers, providing adequate return air, potentially updating ductwork, and ensuring proper heating and cooling distribution throughout the home.

The project appears to be part of a municipal home improvement or rehabilitation program, with the work being prepared and overseen by a city representative (sharrison@cityofjackson.org). No specific pricing details are provided in the document, but the work write-up suggests the project will be competitively bid with contractors required to review and accept the scope of work. The document indicates that electrical work will be handled separately, and any necessary plumbing or wiring repairs to comply with local codes will be included in the project scope. The work write-up is dated 12/13/2024 and requires signatures from the homeowner, contractor, and a construction specialist to formalize the project agreement.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Work Write-Up

F19 - FURNACE - AC- REPLACENENT.

* EXHIBIT 1 *

Dated: 12/13/2024

CUSTOMER INFORMATION

WEATHERS LISA R

138 W ADDISON, JACKSON, MI 49203

PREPARED BY

sharrison@cityofjackson.org

* NOTE *

THE CUSTOMER AND CONTRACTOR MUST SIGN THE BOTTOM OF EACH PAGE ONLY IF

1) THIS WORK WRITE-UP BECOMES PART OF A CONSTRUCTION CONTRACT

2) THE UNDERSIGNED CUSTOMER AND CONTRACTOR HAVE REVIEWED, APPROVED AND AGREED TO THE WORK AND PRICES DESCRIBED IN THIS WORK WRITE-UP

Location: Unassigned

General Requirements
Quantity
Units
Total

1 - F19 - FURNACE/ AC Unit - REPLACE (Specification ID:1.19000 Estimated Qty:0)

* PERMIT REQUIRED *

Replace existing furnace with new 95% efficient forced air, gas fired furnace bearing AGA label. Furnace output capacity shall be sufficient to heat the structure according to NWAHA standards. Installations shall comply with the current Michigan Mechanical Code. All habitable rooms, as designated by the Building Inspector, shall be supplied with warm air sufficient to maintain temperatures according to NWAHA standards. All new register installations shall be located in floor or low wall with the exception of bathrooms, which shall be wall mounted. Provide an adequate means of return air for these new supply runs. The use of ceiling diffuser outlets will be allowed only with prior approval. When new supply or returns are required and duct is run through any habitable room, it shall be enclosed in new or existing walls. Any new enclosure shall match existing surfaces. Installation shall include a register in the warm air plenum or trunkline to provide heat to the cellar and a new thermostat. A filter rack with cover shall be installed in the return air duct outside of the furnace cabinet. Whenever possible, insulate new supply and return ducts in unheated attic spaces, ventilated crawl spaces, and other exposed locations to prevent excessive heat loss. Flexible duct shall be used only in attics or crawl spaces. If not bid As a separate part of this contract, the installation shall include repair or replacement of wiring and/or plumbing necessary to comply with local code. If the existing ductwork is not to be replaced, it must be approved by the Mechanical Inspector and:

AC unit, sized accordingly, installed to manufacturer instructions and have a energy start rating.

Electrical by others.

Total

Prepared By: sharrison@cityofjackson.org on 12/13/2024

OWNER ACCEPTS SCOPE OF WORK

I have read the contents of this work write up and received a copy. I fully understand the repairs to be made to my property.

x___________________________________
Owner:Date

CONTRACTOR ACCEPTS SCOPE OF WORK

I have read the contents of this work write up and agree to perform all work called for in accordance with the bid submitted on __________.

x___________________________________
ContractorDate
x______________________________________
Construction SpecialistDate
Prepared By: sharrison@cityofjackson.org on 12/13/2024