About this file
This is a plumbing underground shop drawing submittal review form for the Santa Cruz Downtown Library Tenant Improvements project in California, prepared by ECHELCON, INC. and reviewed by Jayson Architecture. The submittal, designated as 22 05 00-03.1 UG Plumbing SD, was submitted on October 22, 2025, by Jackson Bigham and reviewed on October 30, 2025, by Brian Croshal and Diego Perez. The review process evaluated general conformance with contract documents for the underground plumbing systems serving the downtown library tenant area, which includes domestic water and sanitary system fixtures and routing within the tenant spaces as part of the broader tenant improvement project.
The review resulted in a "Revise & Resubmit" determination with specific corrections required. Markup notes direct the contractor to relocate the Floor Clean-Out (FCO) per specifications on sheet WLH-P2.20W and to locate stub-ups using provided dimensions on sheet WLH-P2.20E, with measurements of 3'-4" and 14'-2" from grid references, plus 2'-6" and 2'-3" from toilet and sink locations respectively. An additional note requires ensuring pipes are positioned tightly against the concrete wall. The review clarifies that ECHELCON, INC. is responsible for general conformance review only, while the contractor retains full responsibility for dimensional accuracy, field coordination, quantities, and all deviations from contract documents, with the stamped submission not constituting a change order.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ECHELCON, INC.
Review is for general conformance with the contract documents for this project only. Subcontractor or supplier is responsible for omissions, quantities, dimensions, field conditions, coordination with all trades, and information pertaining to fabrication processes or construction techniques. Review shall not relieve subcontractor or supplier from responsibility for errors, omissions or deviation from contract documents. Stamped submission does not constitute a change order.
By:
Date:
Submittal # Description:
Jackson Bigham
22 05 00-03.1 UG PLumbing SD
10/22/2025
CONSULTANT/ OTHER
ENGINEER
ARCHITECT
Brian Croshal, 2025-10-30
DIEGO PEREZ 10/30/2025
NO EXCEPTIONS TAKEN
MAKE CORRECTIONS NOTED
REVISE & RESUBMIT
SUBMIT SPECIFIED ITEM
REVIEWER DATE
SUBMITTAL WAS REVIEWED FOR DESIGN CONFORMITY AND GENERAL
COMPLIANCE WITH THE CONTRACT DOCUMENTS ONLY. THE CONTRACTOR
IS RESPONSIBLE FOR CONFIRMING AND COORDINATING DIMENSIONS AT
THE PROJECT SITE FOR TOLERANCE, CLEARANCE, QUANTITIES, FABRICATION,
COORDINATION WITH OTHER TRADES, AND CONSTRUCTION MEANS AND
METHODS. THIS REVIEW DOES NOT RELIEVE THE CONTRACTOR FROM FULL
CONFORMANCE WITH THE CONTRACT DOCUMENTS.
JAYSON ARCHITECTURE STREET SAN FRANCISCO CA
MAKE CORRECTIONS NOTED:
- SEE SHEET WLH-P2.20W, RELOCATE FCO PER MARKUP
- SEE SHEET WLH-P2.20E, LOCATE STUB UPS PER MARKUP DIMENSIONS
DannyNguyenPham Text Box
FOR REFERENCE ONLY
DannyNguyenPham
JA: PLEASE LOCATE FCO IN
THIS LOCATION
DannyNguyenPham
6' - 6" 1' - 7"
JA: PLEASE LOCATE STUB-
UPS USING THESE
DIMENSIONS TAKEN FROM
GRID 3' - 4"
14' - 2"
2' - 6"
TOILET
2' - 3"
SINK
JA: PLEASE ENSURE PIPES
ARE TIGHT TO CONCRETE
WALL