Exhibit_H_-_Core_&_Shell_Schedule_R2.pdf
PDF 408 KB Posted
- Attached to
- Santa Cruz Downtown Library Tenant Improvements
- Solicitation number
- IFB No. ED-0328
- Issued by
- Santa Cruz County, San Francisco City, California
About this file
This document is a detailed project schedule for the Santa Cruz Downtown Library tenant improvements, a construction project managed by the City of Santa Cruz, California. The project encompasses comprehensive tenant improvement work including mechanical, electrical, plumbing, fire protection, and low-voltage systems; interior partitions, glazing, ceilings, railings, and finishes; and specialized library components. The work spans from July 21, 2025, through December 21, 2027, totaling 609 days of scheduled activities. Major project phases include structural concrete work (253 days), framing and MEP rough-in (142 days), structural steel and library components (205 days), exterior work (120 days), interior finishes (125 days), landscape and amenities (multiple phases totaling over 200 days), elevator installation (240 days), and garage parking completion (320 days). The schedule details sequential tasks across eight floors of residential units, community spaces, and support facilities, with specific milestones for structural elements, mechanical systems, interior finishes, landscaping, and final inspections and system testing.
The schedule indicates that only prequalified contractors via RFQ #ED-2026-01 are eligible to bid on this invitation for bid (IFB), with firms including Bobo Construction, Inc., Bogard Construction, Inc., and Dilbeck & Sons among those prequalified. The project includes critical path activities with dependencies on concrete curing, steel installation, MEP coordination, and sequential floor completion. Landscape work includes maintenance areas, green roofs, and improvements at multiple street frontages (Cathcart Street, Cedar Street, and Lincoln Avenue), scheduled to commence in late August 2027 and continue through December 2027. The comprehensive schedule incorporates inspections, state certifications for elevator installations, and final cleanup and commissioning phases, with substantial completion targeted for late December 2027.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task Name Duration Start Finish 0 THE LIBRARY PROJECT 609 days Mon 7/21/25 Tue 12/21/27
1 STARTING POINT: 15 days Fri 7/25/25 Thu 8/14/25
12 Submittals 59 days Mon 7/21/25 Fri 10/10/25
25 MASS EXCAVATION AND SMP 69 days Mon 8/4/25 Fri 11/7/25
40 JOINT TRENCH/WET UTILITIES 80 days Mon 7/28/25 Mon 11/17/25
51 STRUCTURAL CONCRETE 253 days Thu 10/23/25 Tue 10/27/26
52 Mat Slab - Footings, Walls, Colum115 days Thu 10/23/25 Mon 4/13/26
118 Level 2 Deck Apartments/Parking71 days Fri 1/30/26 Mon 5/11/26
137 Level 2 - Walls & Cols 52 days Tue 3/10/26 Wed 5/20/26
148 Level 3 Deck Parking 69 days Wed 3/4/26 Tue 6/9/26
177 Level 3 - Walls & Cols 49 days Mon 4/27/26 Mon 7/6/26
198 Level 4 Podium Deck 103 days Wed 6/3/26 Tue 10/27/26
199 Pour area #1 22 days Wed 6/3/26 Thu 7/2/26
208 Pour #2 33 days Wed 6/10/26 Mon 7/27/26
220 Pour #3 31 days Thu 6/18/26 Fri 7/31/26
229 Pour #4 88 days Wed 6/24/26 Tue 10/27/26
230 Mitek column delay 15 days Wed 6/24/26 Wed 7/15/26
231 Install column stubs 9 days Thu 7/16/26 Tue 7/28/26
232 Pour columns 2 days Wed 7/29/26 Thu 7/30/26
233 cure 14 edays Thu 7/30/26 Thu 8/13/26
234 stand main columns 8 days Thu 8/13/26 Mon 8/24/26
235 Shore 6 days Mon 7/27/26 Mon 8/3/26
236 MEP 5 days Tue 8/4/26 Mon 8/10/26
237 Ciarra Mitek weld splice de 15 days Fri 8/28/26 Fri 9/18/26
Install column stubs 7/16 Pour columns 7/29
MEP 8/4
Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Project: THE LIBRARY PROJECT Date: Fri 9/11/26
238 Rebar 7 days Mon 9/21/26 Tue 9/29/26
239 AB's/HD's/CJ's 2 days Wed 9/30/26 Thu 10/1/26
240 Inspect 2 days Fri 10/2/26 Mon 10/5/26
241 Pour 1 day Mon 10/5/26 Mon 10/5/26
242 Cure 21 edays Mon 10/5/26 Mon 10/26/26
243 Strip 1 day Tue 10/27/26 Tue 10/27/26
244 MOCK UPS 84 days Mon 7/28/25 Fri 11/21/25
250 FRAMING/MEP ROUGH IN 142 days Fri 7/31/26 Wed 2/24/27
251 4th Floor 20 units plus community room, computer room and managers office
70 days Fri 7/31/26 Fri 11/6/26
252 Set scaffold floors 1 - 4 8 days Wed 10/28/26 Fri 11/6/26
253 Survey 1 day Fri 7/31/26 Fri 7/31/26
254 Snap and detail 7 days Mon 8/3/26 Tue 8/11/26
255 Set steel at managers/community area
15 days Wed 8/12/26 Tue 9/1/26
256 Plate and inspect 7 days Thu 8/6/26 Fri 8/14/26
257 THREE HOUR WALL DELAY 12 days Wed 8/19/26 Thu 9/3/26
258 Frame 4th floor walls 10 days Mon 8/10/26 Fri 8/21/26
259 walls at center area 2 days Wed 8/26/26 Thu 8/27/26
260 Floor Joist 5th floor 7 days Fri 8/21/26 Mon 8/31/26
261 Shear and Inspect 4th floor wa6 days Tue 9/1/26 Wed 9/9/26
262 Sheet 5th Floor 5 days Tue 9/1/26 Tue 9/8/26
263 Floor nail inspection 2 days Tue 9/1/26 Wed 9/2/26
264 DWV 4th Floor 5 days Tue 9/1/26 Tue 9/8/26
265 4th Floor MEP rough in 5 days Thu 9/3/26 Thu 9/10/26
Rebar 9/21 AB's/HD's/CJ's 9/30
Inspect 10/2 Pour 10/5 Cure 10/5
Strip 10/27
Set scaffold floors 1 - 4 10/28
Snap and detail 8/3 t managers/community area 8/12
Floor Joist 5th floor 8/21 ear and Inspect 4th floor walls 9/1
Sheet 5th Floor 9/1
DWV 4th Floor 9/1 4th Floor MEP rough in 9/3
Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
266 Fire Sprinklers Rough In 5 days Fri 9/11/26 Thu 9/17/26
267 Water rough in 5 days Fri 9/18/26 Thu 9/24/26
268 Elec. Distribution rough in 5 days Fri 9/25/26 Thu 10/1/26
269 Pre HVAC Rough in 5 days Fri 10/2/26 Thu 10/8/26
270 5th Floor 26 units 48 days Thu 9/3/26 Tue 11/10/26
271 Snap and detail 4 days Thu 9/3/26 Wed 9/9/26
272 Plate and inspect 0 days Wed 9/16/26 Wed 9/16/26
273 Frame 5th floor walls 5 days Thu 9/3/26 Thu 9/10/26
274 Floor joist 6th floor 6 days Fri 9/11/26 Fri 9/18/26
275 Shear and inspect 5th floor 7 days Mon 9/21/26 Tue 9/29/26
276 sheet 6th floor 5 days Mon 9/21/26 Fri 9/25/26
277 Floor nail inspection 2 days Mon 9/28/26 Tue 9/29/26
278 DWV 5th Floor 5 days Wed 9/30/26 Tue 10/6/26
279 5th Floor MEP rough in 5 days Wed 10/7/26 Tue 10/13/26
280 Fire Sprinklers Rough In 5 days Wed 10/14/26 Tue 10/20/26
281 Water rough in 5 days Wed 10/21/26 Tue 10/27/26
282 Elec. Distribution rough in 5 days Wed 10/28/26 Tue 11/3/26
283 Pre HVAC Rough in 5 days Wed 11/4/26 Tue 11/10/26
284 6th Floor 26 units 53 days Tue 9/29/26 Mon 12/14/26
285 Snap and detail 4 days Tue 9/29/26 Fri 10/2/26
286 Plate and inspect 2 days Thu 10/8/26 Fri 10/9/26
287 Frame 6th floor walls 5 days Mon 10/12/26 Fri 10/16/26
288 Floor joist 7th floor 6 days Mon 10/19/26 Mon 10/26/26
289 Shear and inspect 6th floor 7 days Mon 10/19/26 Tue 10/27/26
Fire Sprinklers Rough In 9/11 Water rough in 9/18
Elec. Distribution rough in 9/25 Pre HVAC Rough in 10/2
9/16
Floor joist 6th floor 9/11 Shear and inspect 5th floor 9/21 sheet 6th floor 9/21 Floor nail inspection 9/28
DWV 5th Floor 9/30 5th Floor MEP rough in 10/7 Fire Sprinklers Rough In 10/14
Water rough in 10/21 Elec. Distribution rough in 10/28
Pre HVAC Rough in 11/4
Snap and detail 9/29 Plate and inspect 10/8
Frame 6th floor walls 10/12 Floor joist 7th floor 10/19
Shear and inspect 6th floor 10/19
Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
290 sheet 7th floor 5 days Tue 10/27/26 Mon 11/2/26
291 Floor nail inspection 2 days Wed 10/28/26 Thu 10/29/26
292 DWV 6th Floor 5 days Fri 10/30/26 Thu 11/5/26
293 6th Floor MEP rough in 5 days Fri 11/6/26 Thu 11/12/26
294 Fire Sprinklers Rough In 5 days Fri 11/13/26 Thu 11/19/26
295 Water rough in 5 days Fri 11/20/26 Mon 11/30/26
296 Elec. Distribution rough in 5 days Tue 12/1/26 Mon 12/7/26
297 Pre HVAC Rough in 5 days Tue 12/8/26 Mon 12/14/26
298 7th Floor 26 units 53 days Mon 11/2/26 Wed 1/20/27
299 Snap and detail 4 days Mon 11/2/26 Thu 11/5/26
300 Plate and inspect 2 days Wed 11/11/26 Thu 11/12/26
301 Frame 7th floor walls 5 days Fri 11/13/26 Thu 11/19/26
302 Floor joist 8th floor 6 days Fri 11/20/26 Tue 12/1/26
303 Shear and inspect 7th floor 7 days Fri 11/20/26 Wed 12/2/26
304 sheet 8th floor 5 days Wed 12/2/26 Tue 12/8/26
305 Floor nail inspection 2 days Thu 12/3/26 Fri 12/4/26
306 DWV 7th Floor 5 days Mon 12/7/26 Fri 12/11/26
307 7th Floor MEP rough in 5 days Mon 12/14/26 Fri 12/18/26
308 Fire Sprinklers Rough In 5 days Mon 12/21/26 Mon 12/28/26
309 Water rough in 5 days Tue 12/29/26 Tue 1/5/27
310 Elec. Distribution rough in 5 days Wed 1/6/27 Tue 1/12/27
311 Pre HVAC Rough in 5 days Wed 1/13/27 Wed 1/20/27
312 8th Floor 26 units 53 days Tue 12/8/26 Wed 2/24/27
313 Snap and detail 4 days Tue 12/8/26 Fri 12/11/26 sheet 7th floor 10/27 Floor nail inspection 10/28
DWV 6th Floor 10/30 6th Floor MEP rough in 11/6 Fire Sprinklers Rough In 11/13
Water rough in 11/20 Elec. Distribution rough in 12/1
Pre HVAC Rough in 12/8
Snap and detail 11/2 Plate and inspect 11/11
Frame 7th floor walls 11/13 Floor joist 8th floor 11/20
Shear and inspect 7th floor 11/20 sheet 8th floor 12/2
Floor nail inspection 12/3 DWV 7th Floor 12/7
7th Floor MEP rough in 12/14 Fire Sprinklers Rough In 12/21
Water rough in 12/29 Elec. Distribution rough in 1/6
Pre HVAC Rough in 1/13
Snap and detail 12/8
Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
314 Plate and inspect 2 days Thu 12/17/26 Fri 12/18/26
315 Frame 8th floor walls 5 days Mon 12/21/26 Mon 12/28/26
316 roof joists 7 days Mon 12/28/26 Wed 1/6/27
317 Shear and inspect 8th floor 7 days Tue 12/29/26 Thu 1/7/27
318 sheet roof 5 days Thu 1/7/27 Wed 1/13/27
319 nail inspection 2 days Fri 1/8/27 Mon 1/11/27
320 DWV 8th Floor 5 days Tue 1/12/27 Tue 1/19/27
321 8th Floor MEP rough in 5 days Wed 1/20/27 Tue 1/26/27
322 Fire Sprinklers Rough In 5 days Wed 1/27/27 Tue 2/2/27
323 Water rough in 5 days Wed 2/3/27 Tue 2/9/27
324 Elec. Distribution rough in 5 days Wed 2/10/27 Wed 2/17/27
325 Pre HVAC Rough in 5 days Thu 2/18/27 Wed 2/24/27
326 ROOF 35 days Tue 1/12/27 Wed 3/3/27
327 Framing curbs and scuppers 15 days Tue 1/12/27 Tue 2/2/27
328 MEP penetrations and flashings 10 days Wed 1/20/27 Tue 2/2/27
329 Roofing 30 days Wed 1/20/27 Wed 3/3/27
330 STRUCTURAL STEEL LIBRARY 205 days Tue 8/25/26 Thu 6/17/27
331 Stand Mitek columns 20 days Tue 8/25/26 Tue 9/22/26
332 Set beams/Steel Trusses 20 days Wed 9/23/26 Tue 10/20/26
333 Set pan decking 12 days Wed 10/21/26 Thu 11/5/26
334 Install roofing 10 days Fri 11/6/26 Thu 11/19/26
335 Install attachment clips for infill framing and curtain wall
10 days Fri 11/6/26 Thu 11/19/26
336 Intumescent Paint 30 days Fri 11/20/26 Wed 1/6/27
337 Infill metal framing 18 days Thu 1/7/27 Tue 2/2/27
Plate and inspect 12/17 Frame 8th floor walls 12/21 roof joists 12/28 Shear and inspect 8th floor 12/29 sheet roof 1/7 nail inspection 1/8 DWV 8th Floor 1/12
8th Floor MEP rough in 1/20 Fire Sprinklers Rough In 1/27
Water rough in 2/3 Elec. Distribution rough in 2/10
Pre HVAC Rough in 2/18
Framing curbs and scuppers 1/12 MEP penetrations and flashings 1/20
Roofing 1/20
Stand Mitek columns 8/25 Set beams/Steel Trusses 9/23
Set pan decking 10/21 Install roofing 11/6 s for infill framing and curtain wall 11/6
Intumescent Paint 11/20 Infill metal framing 1/7
Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
338 install rated ceiling assembly 15 days Wed 2/3/27 Wed 2/24/27
339 Install Storefront/Curtain Wall Upper Area
35 days Wed 2/3/27 Wed 3/24/27
340 Install Curtain wall lower level 40 days Thu 3/25/27 Wed 5/19/27
341 WRB/siding and trim/Wood Paneling
12 days Thu 5/20/27 Mon 6/7/27
342 Production rock interior 8 days Tue 6/8/27 Thu 6/17/27
343 Paint Exterior 7 days Tue 6/8/27 Wed 6/16/27
344 EXTERIORS 120 days Thu 3/4/27 Fri 8/20/27
345 4TH floor (breakdown by elevations later)
70 days Thu 3/4/27 Thu 6/10/27
346 Densglass 10 days Thu 3/4/27 Wed 3/17/27
347 Windows, waterproofing and flashings
15 days Thu 3/18/27 Wed 4/7/27
348 Lath 5 days Thu 4/8/27 Wed 4/14/27
349 Stucco/Siding 30 days Thu 4/15/27 Wed 5/26/27
350 Paint 10 days Thu 5/27/27 Thu 6/10/27
351 5th floor 75 days Thu 3/18/27 Thu 7/1/27
352 Densglass 10 days Thu 3/18/27 Wed 3/31/27
353 Windows, waterproofing and flashings
15 days Thu 4/1/27 Wed 4/21/27
354 Install railing/awning brackets5 days Thu 4/22/27 Wed 4/28/27
355 Lath 5 days Thu 4/29/27 Wed 5/5/27
356 Stucco/Siding 20 days Thu 5/6/27 Thu 6/3/27
357 Install railings/awnings 5 days Fri 6/4/27 Thu 6/10/27
358 Paint 10 days Fri 6/11/27 Thu 6/24/27
359 Clean windows 5 days Fri 6/25/27 Thu 7/1/27 install rated ceiling assembly 2/3 nstall Storefront/Curtain Wall Upper Area 2/3
Install Curtain wall lower level 3/25 WRB/siding and trim/Wood Paneling 5/20
Production rock interior 6/8 Paint Exterior 6/8
Densglass 3/4 Windows, waterproofing and flashings 3/18
Lath 4/8 Stucco/Siding 4/15
Paint 5/27
Densglass 3/18 Windows, waterproofing and flashings 4/1
Install railing/awning brackets 4/22 Lath 4/29
Stucco/Siding 5/6 Install railings/awnings 6/4
Paint 6/11 Clean windows 6/25
Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
360 6th floor 75 days Thu 4/1/27 Fri 7/16/27
361 Densglass 10 days Thu 4/1/27 Wed 4/14/27
362 Windows, waterproofing and flashings
15 days Thu 4/15/27 Wed 5/5/27
363 Install railing/awning brackets5 days Thu 5/6/27 Wed 5/12/27
364 Lath 5 days Thu 5/13/27 Wed 5/19/27
365 Stucco/Siding 20 days Thu 5/20/27 Thu 6/17/27
366 Install railings/awnings 5 days Fri 6/18/27 Thu 6/24/27
367 Paint 10 days Fri 6/25/27 Fri 7/9/27
368 Clean windows 5 days Mon 7/12/27 Fri 7/16/27
369 7th floor 75 days Thu 4/15/27 Fri 7/30/27
370 Densglass 10 days Thu 4/15/27 Wed 4/28/27
371 Windows, waterproofing and flashings
15 days Thu 4/29/27 Wed 5/19/27
372 Install railing/awning brackets5 days Thu 5/20/27 Wed 5/26/27
373 Lath 5 days Thu 5/27/27 Thu 6/3/27
374 Stucco/Siding 20 days Fri 6/4/27 Thu 7/1/27
375 Install railings/awnings 5 days Fri 7/2/27 Fri 7/9/27
376 Paint 10 days Mon 7/12/27 Fri 7/23/27
377 Clean windows 5 days Mon 7/26/27 Fri 7/30/27
378 8th floor 80 days Thu 4/29/27 Fri 8/20/27
379 Densglass 10 days Thu 4/29/27 Wed 5/12/27
380 Windows, waterproofing and flashings
15 days Thu 5/13/27 Thu 6/3/27
381 Install railing/awning brackets5 days Fri 6/4/27 Thu 6/10/27
382 Lath 5 days Fri 6/11/27 Thu 6/17/27
Densglass 4/1 Windows, waterproofing and flashings 4/15
Install railing/awning brackets 5/6 Lath 5/13
Stucco/Siding 5/20 Install railings/awnings 6/18
Paint 6/25 Clean windows 7/12
Densglass 4/15 Windows, waterproofing and flashings 4/29
Install railing/awning brackets 5/20 Lath 5/27
Stucco/Siding 6/4 Install railings/awnings 7/2
Paint 7/12 Clean windows 7/26
Densglass 4/29 Windows, waterproofing and flashings 5/13
Install railing/awning brackets 6/4 Lath 6/11
Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
383 Stucco/Siding 20 days Fri 6/18/27 Fri 7/16/27
384 Install railings/awnings 5 days Mon 7/19/27 Fri 7/23/27
385 Paint 10 days Mon 7/26/27 Fri 8/6/27
386 Clean windows 5 days Mon 8/9/27 Fri 8/13/27
387 drop scaffold 5 days Mon 8/16/27 Fri 8/20/27
388 Install water heaters level 4 10 days Wed 5/19/27 Wed 6/2/27
389 INTERIORS 125 days Wed 2/10/27 Fri 8/6/27
390 4th floor 20 units 78 days Wed 3/17/27 Tue 7/6/27
391 Framing pick up and straighten5 days Wed 3/17/27 Tue 3/23/27
392 Pre rock in units 3 days Wed 3/24/27 Fri 3/26/27
393 Insulate and inspect corridor li 3 days Wed 3/24/27 Fri 3/26/27
394 Second side shear/inspection a4 days Mon 3/29/27 Thu 4/1/27
395 Pre rock at corridors 4 days Fri 4/2/27 Wed 4/7/27
396 Run MEP at corridors 6 days Thu 4/8/27 Thu 4/15/27
397 Inspect MEP at corridors 1 day Fri 4/16/27 Fri 4/16/27
398 Set tubs 3 days Wed 3/24/27 Fri 3/26/27
399 Unit electrical 6 days Wed 3/24/27 Wed 3/31/27
400 Frame and MEP inspection 3 days Wed 3/31/27 Fri 4/2/27
401 Insulation and Inspection 3 days Wed 3/31/27 Fri 4/2/27
402 RC channel 5 days Wed 3/31/27 Tue 4/6/27
403 Second side shear at units 4 days Fri 4/2/27 Wed 4/7/27
404 Production drywall and inspect6 days Thu 4/8/27 Thu 4/15/27
405 Drop ceilings frame and inspec10 days Tue 4/13/27 Mon 4/26/27
406 Drop ceilings frame and inspec10 days Mon 4/19/27 Fri 4/30/27
Stucco/Siding 6/18 Install railings/awnings 7/19
Paint 7/26 Clean windows 8/9 drop scaffold 8/16
Framing pick up and straightening 3/17 Pre rock in units 3/24
Insulate and inspect corridor lids 3/24 Second side shear/inspection at corridors 3/29
Pre rock at corridors 4/2 Run MEP at corridors 4/8
Inspect MEP at corridors 4/16 Set tubs 3/24
Unit electrical 3/24 Frame and MEP inspection 3/31
Insulation and Inspection 3/31 RC channel 3/31
Second side shear at units 4/2 Production drywall and inspection 4/8
Drop ceilings frame and inspect units 4/13 Drop ceilings frame and inspect at corridors 4/19
Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
407 Hang corridor lids 7 days Mon 5/3/27 Tue 5/11/27
408 insulate walls/inspect corridor 4 days Wed 5/12/27 Mon 5/17/27
409 Tape and Texture units 12 days Thu 4/22/27 Fri 5/7/27
410 Paint walls and ceilings units 6 days Mon 5/10/27 Mon 5/17/27
411 Hang corridor walls 5 days Tue 5/18/27 Mon 5/24/27
412 Millwork 6 days Tue 5/18/27 Tue 5/25/27
413 Paint trim 6 days Fri 5/21/27 Fri 5/28/27
414 Cabinets 6 days Wed 5/26/27 Thu 6/3/27
415 Countertops 5 days Tue 6/1/27 Mon 6/7/27
416 Tape and texture corridors 12 days Tue 5/25/27 Thu 6/10/27
417 Base and millwork at corridors 5 days Fri 6/11/27 Thu 6/17/27
418 Paint corridors 5 days Fri 6/18/27 Thu 6/24/27
419 Trim MEP units 5 days Tue 6/1/27 Mon 6/7/27
420 Trim MEP corridors 5 days Tue 6/22/27 Mon 6/28/27
421 Rough clean 5 days Thu 6/3/27 Wed 6/9/27
422 Hot check 5 days Mon 6/7/27 Fri 6/11/27
423 Vinyl units 5 days Wed 6/9/27 Tue 6/15/27
424 Carpet at corridors 5 days Tue 6/29/27 Tue 7/6/27
425 Hardware and accessories 4 days Fri 6/11/27 Wed 6/16/27
426 Appliances 4 days Mon 6/14/27 Thu 6/17/27
427 Window blinds 4 days Tue 6/22/27 Fri 6/25/27
428 Punch, final clean, owner walk 10 days Tue 6/15/27 Mon 6/28/27
429 5th floor 26 units 105 days Tue 3/9/27 Wed 8/4/27
430 Framing pick up and straighten6 days Tue 3/9/27 Tue 3/16/27
Hang corridor lids 5/3 insulate walls/inspect corridors 5/12
Tape and Texture units 4/22 Paint walls and ceilings units 5/10
Hang corridor walls 5/18 Millwork 5/18
Paint trim 5/21 Cabinets 5/26
Countertops 6/1 Tape and texture corridors 5/25
Base and millwork at corridors 6/11 Paint corridors 6/18
Trim MEP units 6/1 Trim MEP corridors 6/22
Rough clean 6/3 Hot check 6/7 Vinyl units 6/9
Carpet at corridors 6/29 Hardware and accessories 6/11
Appliances 6/14 Window blinds 6/22
Punch, final clean, owner walks/Final units 6/15
Framing pick up and straightening 3/9
Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
431 Pre rock and pre gyp in units 5 days Wed 3/17/27 Tue 3/23/27
432 Insulate and inspect corridor li 4 days Wed 3/17/27 Mon 3/22/27
433 Second side shear/inspection a4 days Tue 3/23/27 Fri 3/26/27
434 Pre rock and pre gyp at corrido4 days Mon 3/29/27 Thu 4/1/27
435 Run MEP at corridors 6 days Fri 4/2/27 Fri 4/9/27
436 Inspect MEP at corridors 1 day Mon 4/12/27 Mon 4/12/27
437 Set tubs 4 days Mon 3/22/27 Thu 3/25/27
438 Unit electrical 6 days Wed 3/24/27 Wed 3/31/27
439 Frame and MEP inspection 3 days Wed 3/31/27 Fri 4/2/27
440 Insulation and Inspection 3 days Thu 4/1/27 Mon 4/5/27
441 RC channel 5 days Fri 4/2/27 Thu 4/8/27
442 Second side shear at units 4 days Wed 4/7/27 Mon 4/12/27
443 1st layer of drywall at units 6 days Fri 4/9/27 Fri 4/16/27
444 Production drywall and inspect6 days Thu 4/15/27 Thu 4/22/27
445 Drop ceilings frame and inspec10 days Wed 4/21/27 Tue 5/4/27
446 Drop ceilings frame and inspec10 days Tue 4/13/27 Mon 4/26/27
447 Hang corridor lids 7 days Tue 4/27/27 Wed 5/5/27
448 insulate walls/inspect corridor 4 days Thu 5/6/27 Tue 5/11/27
449 Tape and Texture units 12 days Mon 5/3/27 Tue 5/18/27
450 Paint walls and ceilings units 8 days Wed 5/19/27 Fri 5/28/27
451 Hang corridor walls 5 days Wed 5/12/27 Tue 5/18/27
452 Gypcrete at units 5 days Wed 5/19/27 Tue 5/25/27
453 Millwork 6 days Fri 5/28/27 Mon 6/7/27
454 Paint trim 6 days Fri 6/4/27 Fri 6/11/27
Pre rock and pre gyp in units 3/17 Insulate and inspect corridor lids 3/17
Second side shear/inspection at corridors 3/23 Pre rock and pre gyp at corridors 3/29
Run MEP at corridors 4/2 Inspect MEP at corridors 4/12
Set tubs 3/22 Unit electrical 3/24
Frame and MEP inspection 3/31 Insulation and Inspection 4/1
RC channel 4/2 Second side shear at units 4/7
1st layer of drywall at units 4/9 Production drywall and inspection 4/15
Drop ceilings frame and inspect units 4/21 Drop ceilings frame and inspect at corridors 4/13
Hang corridor lids 4/27 insulate walls/inspect corridors 5/6
Tape and Texture units 5/3 Paint walls and ceilings units 5/19
Hang corridor walls 5/12 Gypcrete at units 5/19
Millwork 5/28 Paint trim 6/4
Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
455 Cabinets 6 days Thu 6/10/27 Thu 6/17/27
456 Countertops 5 days Wed 6/16/27 Tue 6/22/27
457 Gypcrete at corridors 4 days Wed 5/26/27 Tue 6/1/27
458 Tape and texture corridors 12 days Wed 6/2/27 Thu 6/17/27
459 Base and millwork at corridors 5 days Fri 6/18/27 Thu 6/24/27
460 Paint corridors 5 days Fri 6/25/27 Thu 7/1/27
461 Trim MEP units 5 days Wed 6/23/27 Tue 6/29/27
462 Trim MEP corridors 5 days Mon 6/28/27 Fri 7/2/27
463 Rough clean 5 days Thu 7/1/27 Thu 7/8/27
464 Hot check 5 days Wed 7/7/27 Tue 7/13/27
465 Vinyl units 5 days Mon 7/12/27 Fri 7/16/27
466 Hardware and accessories 4 days Thu 7/15/27 Tue 7/20/27
467 Appliances 5 days Mon 7/19/27 Fri 7/23/27
468 Window blinds 4 days Mon 7/19/27 Thu 7/22/27
469 Punch, final clean, owner walk 10 days Thu 7/22/27 Wed 8/4/27
470 6th floor 26 units 113 days Mon 3/1/27 Fri 8/6/27
471 Framing pick up and straighten6 days Mon 3/1/27 Mon 3/8/27
472 Pre rock and pre gyp in units 5 days Tue 3/9/27 Mon 3/15/27
473 Insulate and inspect corridor li 4 days Tue 3/9/27 Fri 3/12/27
474 Second side shear/inspection a4 days Mon 3/15/27 Thu 3/18/27
475 Pre rock and pre gyp at corrido4 days Fri 3/19/27 Wed 3/24/27
476 Run MEP at corridors 6 days Thu 3/25/27 Thu 4/1/27
477 Inspect MEP at corridors 1 day Fri 4/2/27 Fri 4/2/27
478 Set tubs 4 days Fri 3/12/27 Wed 3/17/27
Cabinets 6/10 Countertops 6/16
Gypcrete at corridors 5/26 Tape and texture corridors 6/2
Base and millwork at corridors 6/18 Paint corridors 6/25
Trim MEP units 6/23 Trim MEP corridors 6/28
Rough clean 7/1 Hot check 7/7 Vinyl units 7/12
Hardware and accessories 7/15 Appliances 7/19
Window blinds 7/19 Punch, final clean, owner walks/Final Units 7/22
Framing pick up and straightening 3/1 Pre rock and pre gyp in units 3/9
Insulate and inspect corridor lids 3/9 Second side shear/inspection at corridors 3/15
Pre rock and pre gyp at corridors 3/19 Run MEP at corridors 3/25
Inspect MEP at corridors 4/2 Set tubs 3/12
Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
479 Unit electrical 6 days Tue 3/16/27 Tue 3/23/27
480 Frame and MEP inspection 3 days Tue 3/23/27 Thu 3/25/27
481 Insulation and Inspection 3 days Wed 3/24/27 Fri 3/26/27
482 RC channel 5 days Thu 3/25/27 Wed 3/31/27
483 Second side shear at units 4 days Tue 3/30/27 Fri 4/2/27
484 1st layer of drywall at units 6 days Thu 4/1/27 Thu 4/8/27
485 Production drywall and inspect6 days Wed 4/7/27 Wed 4/14/27
486 Drop ceilings frame and inspec10 days Tue 4/13/27 Mon 4/26/27
487 Drop ceilings frame and inspec10 days Mon 4/5/27 Fri 4/16/27
488 Hang corridor lids 7 days Mon 4/19/27 Tue 4/27/27
489 insulate walls/inspect corridor 4 days Wed 4/28/27 Mon 5/3/27
490 Tape and Texture units 12 days Fri 4/23/27 Mon 5/10/27
491 Paint walls and ceiling units 8 days Tue 5/11/27 Thu 5/20/27
492 Hang corridor walls 5 days Tue 5/4/27 Mon 5/10/27
493 Gypcrete at units 5 days Fri 5/21/27 Thu 5/27/27
494 Millwork 6 days Wed 6/2/27 Wed 6/9/27
495 Paint trim 6 days Tue 6/8/27 Tue 6/15/27
496 Cabinets 6 days Mon 6/14/27 Mon 6/21/27
497 Countertops 5 days Fri 6/18/27 Thu 6/24/27
498 Gypcrete at corridors 4 days Fri 5/28/27 Thu 6/3/27
499 Tape and texture corridors 12 days Fri 6/4/27 Mon 6/21/27
500 Base and millwork at corridors 5 days Tue 6/22/27 Mon 6/28/27
501 Paint corridors 5 days Tue 6/29/27 Tue 7/6/27
502 Trim MEP units 5 days Fri 6/25/27 Thu 7/1/27
Unit electrical 3/16 Frame and MEP inspection 3/23
Insulation and Inspection 3/24 RC channel 3/25
Second side shear at units 3/30 1st layer of drywall at units 4/1
Production drywall and inspection 4/7 Drop ceilings frame and inspect units 4/13
Drop ceilings frame and inspect at corridors 4/5 Hang corridor lids 4/19 insulate walls/inspect corridors 4/28 Tape and Texture units 4/23
Paint walls and ceiling units 5/11 Hang corridor walls 5/4
Gypcrete at units 5/21 Millwork 6/2
Paint trim 6/8 Cabinets 6/14
Countertops 6/18 Gypcrete at corridors 5/28
Tape and texture corridors 6/4 Base and millwork at corridors 6/22
Paint corridors 6/29 Trim MEP units 6/25
Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
503 Trim MEP corridors 5 days Wed 6/30/27 Wed 7/7/27
504 Rough clean 5 days Tue 7/6/27 Mon 7/12/27
505 Hot check 5 days Fri 7/9/27 Thu 7/15/27
506 Vinyl units 5 days Wed 7/14/27 Tue 7/20/27
507 Hardware and accessories 4 days Mon 7/19/27 Thu 7/22/27
508 Appliances 5 days Wed 7/21/27 Tue 7/27/27
509 Window blinds 4 days Wed 7/21/27 Mon 7/26/27
510 Punch, final clean, owner walk 10 days Mon 7/26/27 Fri 8/6/27
511 7th floor 26 units 110 days Fri 2/19/27 Mon 7/26/27
512 Framing pick up and straighten6 days Fri 2/19/27 Fri 2/26/27
513 Pre rock and pre gyp in units 5 days Mon 3/1/27 Fri 3/5/27
514 Insulate and inspect corridor li 4 days Mon 3/1/27 Thu 3/4/27
515 Second side shear/inspection a4 days Fri 3/5/27 Wed 3/10/27
516 Pre rock and pre gyp at corrido4 days Thu 3/11/27 Tue 3/16/27
517 Run MEP at corridors 6 days Wed 3/17/27 Wed 3/24/27
518 Inspect MEP at corridors 1 day Thu 3/25/27 Thu 3/25/27
519 Set tubs 4 days Thu 3/4/27 Tue 3/9/27
520 Unit electrical 6 days Mon 3/8/27 Mon 3/15/27
521 Frame and MEP inspection 3 days Mon 3/15/27 Wed 3/17/27
522 Insulation and Inspection 3 days Tue 3/16/27 Thu 3/18/27
523 RC channel 5 days Wed 3/17/27 Tue 3/23/27
524 Second side shear at units 4 days Mon 3/22/27 Thu 3/25/27
525 1st layer of drywall at units 6 days Wed 3/24/27 Wed 3/31/27
526 Production drywall and inspect6 days Tue 3/30/27 Tue 4/6/27
Trim MEP corridors 6/30 Rough clean 7/6
Hot check 7/9 Vinyl units 7/14
Hardware and accessories 7/19 Appliances 7/21
Window blinds 7/21 Punch, final clean, owner walks/Final units 7/26
Framing pick up and straightening 2/19 Pre rock and pre gyp in units 3/1
Insulate and inspect corridor lids 3/1 Second side shear/inspection at corridors 3/5
Pre rock and pre gyp at corridors 3/11 Run MEP at corridors 3/17
Inspect MEP at corridors 3/25 Set tubs 3/4
Unit electrical 3/8 Frame and MEP inspection 3/15
Insulation and Inspection 3/16 RC channel 3/17
Second side shear at units 3/22 1st layer of drywall at units 3/24
Production drywall and inspection 3/30
Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
527 Drop ceilings frame and inspec10 days Mon 4/5/27 Fri 4/16/27
528 Drop ceilings frame and inspec10 days Fri 3/26/27 Thu 4/8/27
529 Hang corridor lids 7 days Fri 4/9/27 Mon 4/19/27
530 insulate walls/inspect corridor 4 days Tue 4/20/27 Fri 4/23/27
531 Tape and Texture units 12 days Thu 4/15/27 Fri 4/30/27
532 Paint walls and ceilings units 8 days Mon 5/3/27 Wed 5/12/27
533 Hang corridor walls 5 days Mon 4/26/27 Fri 4/30/27
534 Gypcrete at units 5 days Thu 5/13/27 Wed 5/19/27
535 Millwork 6 days Mon 5/24/27 Tue 6/1/27
536 Paint 6 days Fri 5/28/27 Mon 6/7/27
537 Cabinets 6 days Fri 6/4/27 Fri 6/11/27
538 Countertops 5 days Thu 6/10/27 Wed 6/16/27
539 Gypcrete at corridors 4 days Thu 5/20/27 Tue 5/25/27
540 Tape and texture corridors 12 days Wed 5/26/27 Fri 6/11/27
541 Base and millwork at corridors 5 days Mon 6/14/27 Fri 6/18/27
542 Paint corridors 5 days Mon 6/21/27 Fri 6/25/27
543 Trim MEP units 5 days Thu 6/17/27 Wed 6/23/27
544 Trim MEP corridors 5 days Tue 6/22/27 Mon 6/28/27
545 Rough clean 5 days Fri 6/25/27 Thu 7/1/27
546 Hot check 5 days Wed 6/30/27 Wed 7/7/27
547 Vinyl units 5 days Tue 7/6/27 Mon 7/12/27
548 Carpet at corridors 5 days Tue 6/29/27 Tue 7/6/27
549 Hardware and accessories 4 days Fri 7/9/27 Wed 7/14/27
550 Appliances 4 days Fri 7/9/27 Wed 7/14/27
Drop ceilings frame and inspect units 4/5 Drop ceilings frame and inspect at corridors 3/26
Hang corridor lids 4/9 insulate walls/inspect corridors 4/20
Tape and Texture units 4/15 Paint walls and ceilings units 5/3
Hang corridor walls 4/26 Gypcrete at units 5/13
Millwork 5/24 Paint 5/28
Cabinets 6/4 Countertops 6/10
Gypcrete at corridors 5/20 Tape and texture corridors 5/26
Base and millwork at corridors 6/14 Paint corridors 6/21
Trim MEP units 6/17 Trim MEP corridors 6/22
Rough clean 6/25 Hot check 6/30 Vinyl units 7/6
Carpet at corridors 6/29 Hardware and accessories 7/9
Appliances 7/9
Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
551 Window blinds 4 days Tue 7/13/27 Fri 7/16/27
552 Punch, final clean, owner walk 10 days Tue 7/13/27 Mon 7/26/27
553 8th floor 26 units 106 days Wed 2/10/27 Mon 7/12/27
554 Framing pick up and straighten6 days Wed 2/10/27 Thu 2/18/27
555 Pre rock and pre gyp in units 5 days Fri 2/19/27 Thu 2/25/27
556 Insulate and inspect corridor li 4 days Fri 2/19/27 Wed 2/24/27
557 Second side shear/inspection a4 days Thu 2/25/27 Tue 3/2/27
558 Pre rock and pre gyp at corrido4 days Wed 3/3/27 Mon 3/8/27
559 Run MEP at corridors 6 days Tue 3/9/27 Tue 3/16/27
560 Inspect MEP at corridors 1 day Wed 3/17/27 Wed 3/17/27
561 Set tubs 4 days Wed 2/24/27 Mon 3/1/27
562 Unit electrical 6 days Fri 2/26/27 Fri 3/5/27
563 Frame and MEP inspection 3 days Fri 3/5/27 Tue 3/9/27
564 Insulation and Inspection 3 days Mon 3/8/27 Wed 3/10/27
565 Second side shear at units 2 days Thu 3/11/27 Fri 3/12/27
566 1st layer of drywall at units 5 days Thu 3/11/27 Wed 3/17/27
567 Production drywall and inspect6 days Tue 3/16/27 Tue 3/23/27
568 Drop ceilings frame and inspec10 days Mon 3/22/27 Fri 4/2/27
569 Drop ceilings frame and inspec10 days Thu 3/18/27 Wed 3/31/27
570 Hang corridor lids 7 days Thu 4/1/27 Fri 4/9/27
571 insulate walls/inspect corridor 4 days Mon 4/12/27 Thu 4/15/27
572 Tape and Texture units 12 days Thu 4/1/27 Fri 4/16/27
573 Paint walls and ceiling units 8 days Mon 4/19/27 Wed 4/28/27
574 Hang corridor walls 5 days Fri 4/16/27 Thu 4/22/27
Window blinds 7/13 Punch, final clean, owner walks/Final units 7/13
Framing pick up and straightening 2/10 Pre rock and pre gyp in units 2/19
Insulate and inspect corridor lids 2/19 Second side shear/inspection at corridors 2/25
Pre rock and pre gyp at corridors 3/3 Run MEP at corridors 3/9
Inspect MEP at corridors 3/17 Set tubs 2/24
Unit electrical 2/26 Frame and MEP inspection 3/5
Insulation and Inspection 3/8 Second side shear at units 3/11
1st layer of drywall at units 3/11 Production drywall and inspection 3/16
Drop ceilings frame and inspect units 3/22 Drop ceilings frame and inspect at corridors 3/18
Hang corridor lids 4/1 insulate walls/inspect corridors 4/12
Tape and Texture units 4/1 Paint walls and ceiling units 4/19
Hang corridor walls 4/16
Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
575 Gypcrete at units 5 days Thu 4/29/27 Wed 5/5/27
576 Millwork 6 days Mon 5/10/27 Mon 5/17/27
577 Paint 6 days Fri 5/14/27 Fri 5/21/27
578 Cabinets 6 days Thu 5/20/27 Thu 5/27/27
579 Countertops 5 days Wed 5/26/27 Wed 6/2/27
580 Gypcrete at corridors 4 days Thu 5/6/27 Tue 5/11/27
581 Tape and texture corridors 12 days Wed 5/12/27 Thu 5/27/27
582 Base and millwork at corridors 5 days Fri 5/28/27 Fri 6/4/27
583 Paint corridors 5 days Mon 6/7/27 Fri 6/11/27
584 Trim MEP units 5 days Thu 6/3/27 Wed 6/9/27
585 Trim MEP corridors 5 days Tue 6/8/27 Mon 6/14/27
586 Rough clean 5 days Fri 6/11/27 Thu 6/17/27
587 Hot check 5 days Wed 6/16/27 Tue 6/22/27
588 Vinyl units 5 days Mon 6/21/27 Fri 6/25/27
589 Carpet at corridors 5 days Tue 6/15/27 Mon 6/21/27
590 Hardware and accessories 5 days Thu 6/24/27 Wed 6/30/27
591 Appliances 4 days Thu 6/24/27 Tue 6/29/27
592 Window blinds 4 days Tue 6/29/27 Fri 7/2/27
593 Punch, final clean, owner walk 10 days Mon 6/28/27 Mon 7/12/27
594 Community Room/Computer Lab 4th floor/Laundry/Managers Office/Lounge
101 days Wed 3/24/27 Fri 8/13/27
595 Framing pick up and straightening4 days Wed 3/24/27 Mon 3/29/27
596 Pre HVAC 4 days Tue 3/30/27 Fri 4/2/27
597 Pre rock 4 days Mon 4/5/27 Thu 4/8/27
Gypcrete at units 4/29 Millwork 5/10
Paint 5/14 Cabinets 5/20
Countertops 5/26 Gypcrete at corridors 5/6
Tape and texture corridors 5/12 Base and millwork at corridors 5/28
Paint corridors 6/7 Trim MEP units 6/3
Trim MEP corridors 6/8 Rough clean 6/11
Hot check 6/16 Vinyl units 6/21
Carpet at corridors 6/15 Hardware and accessories 6/24
Appliances 6/24 Window blinds 6/29
Punch, final clean, owner walks/Final units 6/28
Framing pick up and straightening 3/24 Pre HVAC 3/30
Pre rock 4/5
Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
598 Build drops 9 days Fri 4/9/27 Wed 4/21/27
599 HVAC 3 days Thu 4/22/27 Mon 4/26/27
600 Electrical 4 days Tue 4/27/27 Fri 4/30/27
601 Frame and MEP inspection 2 days Mon 5/3/27 Tue 5/4/27
602 Insulation and Inspection 3 days Wed 5/5/27 Fri 5/7/27
603 Production drywall 3 days Mon 5/10/27 Wed 5/12/27
604 Tape and Texture 10 days Thu 5/13/27 Wed 5/26/27
605 Millwork 4 days Thu 5/27/27 Wed 6/2/27
606 Paint 4 days Thu 6/3/27 Tue 6/8/27
607 Flooring/Tile 10 days Wed 6/9/27 Tue 6/22/27
608 MEP trim 8 days Wed 6/23/27 Fri 7/2/27
609 Install Machines at Laundry 5 days Tue 7/6/27 Mon 7/12/27
610 Rough clean 3 days Tue 7/13/27 Thu 7/15/27
611 Hot check 4 days Fri 7/16/27 Wed 7/21/27
612 Hardware and accessories 5 days Thu 7/22/27 Wed 7/28/27
613 Punch final clean 10 days Thu 7/29/27 Wed 8/11/27
614 Final inspections 2 days Thu 8/12/27 Fri 8/13/27
615 LANDSCAPE MAINTENANCE AND
EMPLOYEE COURTYARD 4th floor
58 days Mon 8/23/27 Thu 11/11/27
616 Clean up and layout 3 days Mon 8/23/27 Wed 8/25/27
617 Waterproof podium and test 5 days Thu 8/26/27 Wed 9/1/27
618 Install drain mat 1 day Thu 9/2/27 Thu 9/2/27
619 Build planters 7 days Fri 9/3/27 Tue 9/14/27
620 run MEPS conduits etc 3 days Wed 9/15/27 Fri 9/17/27
621 Install gates/railings 3 days Wed 9/15/27 Fri 9/17/27
Build drops 4/9
HVAC 4/22
Electrical 4/27 Frame and MEP inspection 5/3
Insulation and Inspection 5/5 Production drywall 5/10
Tape and Texture 5/13 Millwork 5/27
Paint 6/3 Flooring/Tile 6/9
MEP trim 6/23 Install Machines at Laundry 7/6
Rough clean 7/13 Hot check 7/16
Hardware and accessories 7/22 Punch final clean 7/29
Final inspections 8/12
Clean up and layout 8/23 Waterproof podium and test 8/26
Install drain mat 9/2 Build planters 9/3 run MEPS conduits etc 9/15 Install gates/railings 9/15
Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
622 paint gates and railings 2 days Mon 9/20/27 Tue 9/21/27
623 waterproof planters/test 5 days Mon 9/20/27 Fri 9/24/27
624 fill planters with dirt 4 days Mon 9/27/27 Thu 9/30/27
625 flat work/ pavers 8 days Fri 10/1/27 Tue 10/12/27
626 soil amendments 2 days Wed 10/13/27 Thu 10/14/27
627 MEP trim 6 days Fri 10/15/27 Fri 10/22/27
628 planting and irrigation 6 days Mon 10/25/27 Mon 11/1/27
629 FF and E 3 days Tue 11/2/27 Thu 11/4/27
630 punch and detail 5 days Fri 11/5/27 Thu 11/11/27
631 LIBRARY GREEN ROOF 4th floor 42 days Thu 8/26/27 Mon 10/25/27
632 Clean up and layout 4 days Thu 8/26/27 Tue 8/31/27
633 Waterproof podium and test 5 days Wed 9/1/27 Wed 9/8/27
634 Install drain mat 1 day Thu 9/9/27 Thu 9/9/27
635 run MEPS conduits etc 3 days Fri 9/10/27 Tue 9/14/27
636 soil amendments 2 days Wed 9/15/27 Thu 9/16/27
637 MEP trim 7 days Fri 9/17/27 Mon 9/27/27
638 planting and irrigation 7 days Tue 9/28/27 Wed 10/6/27
639 FF and E 5 days Thu 10/7/27 Wed 10/13/27
640 punch and detail 8 days Thu 10/14/27 Mon 10/25/27
641 LANDSCAPE NORTH SIDE @ ALLEY 53 days Mon 8/23/27 Thu 11/4/27
642 Clean up and back fill at building 3 days Mon 8/23/27 Wed 8/25/27
643 Install Bio Swale planter 5 days Thu 8/26/27 Wed 9/1/27
644 install drainage 3 days Thu 9/2/27 Tue 9/7/27
645 formwork/rebar planter walls 8 days Wed 9/8/27 Fri 9/17/27 paint gates and railings 9/20 waterproof planters/test 9/20 fill planters with dirt 9/27 flat work/ pavers 10/1 soil amendments 10/13
MEP trim 10/1 planting and irrigation 10/2
FF and E 11/ punch and detail 11/
Clean up and layout 8/26 Waterproof podium and test 9/1
Install drain mat 9/9 run MEPS conduits etc 9/10 soil amendments 9/15 MEP trim 9/17 planting and irrigation 9/28 FF and E 10/7 punch and detail 10/1
Clean up and back fill at building 8/23 Install Bio Swale planter 8/26 install drainage 9/2 formwork/rebar planter walls 9/8
Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
646 install MEP's/irrigation sleeves at planter 3 days Mon 9/20/27 Wed 9/22/27
647 pour planter 2 days Thu 9/23/27 Fri 9/24/27
648 Install irrigation 5 days Mon 9/27/27 Fri 10/1/27
649 waterproof planter 4 days Mon 10/4/27 Thu 10/7/27
650 vehicular ashpalt 5 days Fri 10/8/27 Thu 10/14/27
651 plant trees/plants 5 days Fri 10/15/27 Thu 10/21/27
652 install benches/bike racks and tree grates
5 days Fri 10/22/27 Thu 10/28/27
653 punch and detail 5 days Fri 10/29/27 Thu 11/4/27
654 LANDSCAPE @ CATHCART STREET 46 days Fri 9/10/27 Fri 11/12/27
655 Clean up and rough grade 3 days Fri 9/10/27 Tue 9/14/27
656 layout and stake side walks/features/Bio Swales
2 days Wed 9/15/27 Thu 9/16/27
657 Install Bio Swales 3 days Fri 9/17/27 Tue 9/21/27
658 install drainage 2 days Wed 9/22/27 Thu 9/23/27
659 dig tree wells 3 days Fri 9/24/27 Tue 9/28/27
660 finish grading 2 days Wed 9/29/27 Thu 9/30/27
661 Install irrigation 5 days Fri 10/1/27 Thu 10/7/27
662 fine grade and form side walk/ram6 days Fri 10/8/27 Fri 10/15/27
663 pour sidewalk/entry ramp 4 days Mon 10/18/27 Thu 10/21/27
664 import soil to tree wells 3 days Fri 10/22/27 Tue 10/26/27
665 plant trees/plants 5 days Wed 10/27/27 Tue 11/2/27
666 install benches/bike racks and tree grates
3 days Wed 11/3/27 Fri 11/5/27
667 punch and detail 5 days Mon 11/8/27 Fri 11/12/27 install MEP's/irrigation sleeves at planter 9/20 pour planter 9/23 Install irrigation 9/27 waterproof planter 10/4 vehicular ashpalt 10/8 plant trees/plants 10/1 install benches/bike racks and tree grates 10/2 punch and detail 10/
Clean up and rough grade 9/10 layout and stake side walks/features/Bio Swales 9/15
Install Bio Swales 9/17 install drainage 9/22 dig tree wells 9/24 finish grading 9/29
Install irrigation 10/1 fine grade and form side walk/ramp 10/8 pour sidewalk/entry ramp 10/1 import soil to tree wells 10/2 plant trees/plants 10/2 install benches/bike racks and tree grates 11/ punch and detail 11/
Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
668 LANDSCAPE @ CEDAR STREET 48 days Wed 9/29/27 Tue 12/7/27
669 Clean up and rough grade 3 days Wed 9/29/27 Fri 10/1/27
670 layout and stake side walks/features/Bio Swales
2 days Mon 10/4/27 Tue 10/5/27
671 Install Bio Swales 3 days Wed 10/6/27 Fri 10/8/27
672 install drainage 2 days Mon 10/11/27 Tue 10/12/27
673 dig tree wells 3 days Wed 10/13/27 Fri 10/15/27
674 install MEP's/irrigation sleeves at planters
3 days Mon 10/18/27 Wed 10/20/27
675 pour planters 2 days Thu 10/21/27 Fri 10/22/27
676 finish grading 2 days Mon 10/25/27 Tue 10/26/27
677 Install irrigation 5 days Wed 10/27/27 Tue 11/2/27
678 waterproof planters 4 days Wed 11/3/27 Mon 11/8/27
679 pour bands/steps 1 day Tue 11/9/27 Tue 11/9/27
680 fine grade and form side walk/ram5 days Wed 11/10/27 Tue 11/16/27
681 pour sidewalk/ramp 2 days Wed 11/17/27 Thu 11/18/27
682 import soil to planters and tree wells
3 days Fri 11/19/27 Tue 11/23/27
683 plant trees/plants 5 days Wed 11/24/27 Thu 12/2/27
684 install benches/bike racks and tree grates
3 days Fri 12/3/27 Tue 12/7/27
685 LANDSCAPE @ LINCOLN 38 days Mon 10/18/27 Fri 12/10/27
686 Clean up and rough grade 3 days Mon 10/18/27 Wed 10/20/27
687 layout and stake side walks/features/Bio Swales
2 days Thu 10/21/27 Fri 10/22/27
688 Install Bio Swales 3 days Mon 10/25/27 Wed 10/27/27
689 install drainage 2 days Thu 10/28/27 Fri 10/29/27
Clean up and rough grade 9/29 layout and stake side walks/features/Bio Swales 10/4
Install Bio Swales 10/6 install drainage 10/11 dig tree wells 10/13 install MEP's/irrigation sleeves at planters 10/1 pour planters 10/2 finish grading 10/2
Install irrigation 10/2 waterproof planters 11/ pour bands/steps 11/ fine grade and form side walk/ramp 11/ pour sidewalk/ramp 11 import soil to planters and tree wells 11 plant trees/plants 1 install benches/bike racks and tree grates 1
Clean up and rough grade 10/1 layout and stake side walks/features/Bio Swales 10/2
Install Bio Swales 10/2 install drainage 10/2
Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
690 dig tree wells 3 days Mon 11/1/27 Wed 11/3/27
691 finish grading 2 days Thu 11/4/27 Fri 11/5/27
692 Install irrigation 5 days Mon 11/8/27 Fri 11/12/27
693 fine grade and form side walk/ram5 days Mon 11/15/27 Fri 11/19/27
694 pour sidewalk/ramp 2 days Mon 11/22/27 Tue 11/23/27
695 import soil to tree wells 3 days Wed 11/24/27 Tue 11/30/27
696 plant trees/plants 5 days Wed 12/1/27 Tue 12/7/27
697 install benches/bike racks and tree grates
3 days Wed 12/8/27 Fri 12/10/27
698 ELEVATORS 240 days Fri 11/20/26 Wed 11/3/27
699 Elevator # 3 3 STOP CREW 1 67 days Fri 11/20/26 Tue 3/2/27
700 install steel columns/plates 5 days Fri 11/20/26 Mon 11/30/26
701 insulate shaft/inspect 5 days Tue 12/1/26 Mon 12/7/26
702 drywall shaft and tape 10 days Tue 12/8/26 Mon 12/21/26
703 install elevator 20 days Tue 12/22/26 Thu 1/21/27
704 fire caulk and close in door openings
10 days Fri 1/22/27 Thu 2/4/27
705 adjustment 5 days Fri 2/5/27 Thu 2/11/27
706 call in for State 10 days Fri 2/12/27 Fri 2/26/27
707 State inspect elevator 2 days Mon 3/1/27 Tue 3/2/27
708 Elevator # 4 2 STOP LIBRARY CRE 67 days Tue 12/1/26 Tue 3/9/27
709 install steel columns/plates 5 days Tue 12/1/26 Mon 12/7/26
710 insulate shaft/inspect 5 days Tue 12/8/26 Mon 12/14/26
711 drywall shaft and tape 10 days Tue 12/15/26 Tue 12/29/26
712 install elevator 20 days Wed 12/30/26 Thu 1/28/27 dig tree wells 11/1 finish grading 11/
Install irrigation 11/ fine grade and form side walk/ramp 11 pour sidewalk/ramp 11 import soil to tree wells 11 plant trees/plants 1 install benches/bike racks and tree grates 1 install steel columns/plates 11/20 insulate shaft/inspect 12/1 drywall shaft and tape 12/8 install elevator 12/22 fire caulk and close in door openings 1/22 adjustment 2/5 call in for State 2/12
State inspect elevator 3/1 install steel columns/plates 12/1 insulate shaft/inspect 12/8 drywall shaft and tape 12/15 install elevator 12/30
Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
713 fire caulk and close in door openings 10 days Fri 1/29/27 Thu 2/11/27
714 adjustment 5 days Fri 2/12/27 Fri 2/19/27
715 call in for State 10 days Mon 2/22/27 Fri 3/5/27
716 State inspect elevator 2 days Mon 3/8/27 Tue 3/9/27
717 Elevator # 5 COMMERCIAL 3
STOP CREW 1
82 days Tue 12/8/26 Tue 4/6/27
718 install steel columns/plates 5 days Tue 12/8/26 Mon 12/14/26
719 insulate shaft/inspect 5 days Tue 12/15/26 Mon 12/21/26
720 drywall shaft and tape 10 days Tue 12/22/26 Wed 1/6/27
721 install elevator 25 days Fri 1/22/27 Fri 2/26/27
722 fire caulk and close in door openings
10 days Mon 3/1/27 Fri 3/12/27
723 adjustment 5 days Mon 3/15/27 Fri 3/19/27
724 call in for State 10 days Mon 3/22/27 Fri 4/2/27
725 State inspect elevator 2 days Mon 4/5/27 Tue 4/6/27
726 Elevator # 2 @ LINCOLN 8 STOP
CREW 2
87 days Fri 6/18/27 Wed 10/20/27
727 install steel columns/plates 10 days Fri 6/18/27 Thu 7/1/27
728 insulate shaft/inspect 5 days Fri 7/2/27 Fri 7/9/27
729 drywall shaft and tape 10 days Mon 7/12/27 Fri 7/23/27
730 install elevator 35 days Mon 7/26/27 Mon 9/13/27
731 fire caulk and close in door openings
10 days Tue 9/14/27 Mon 9/27/27
732 adjustment 5 days Tue 9/28/27 Mon 10/4/27
733 call in for State 10 days Tue 10/5/27 Mon 10/18/27
734 State inspect elevator 2 days Tue 10/19/27 Wed 10/20/27 fire caulk and close in door openings 1/29 adjustment 2/12 call in for State 2/22
State inspect elevator 3/8 install steel columns/plates 12/8 insulate shaft/inspect 12/15 drywall shaft and tape 12/22 install elevator 1/22 fire caulk and close in door openings 3/1 adjustment 3/15 call in for State 3/22
State inspect elevator 4/5 install steel columns/plates 6/18 insulate shaft/inspect 7/2 drywall shaft and tape 7/12 install elevator 7/26 fire caulk and close in door openings 9/14 adjustment 9/28 call in for State 10/5
State inspect elevator 10/1
Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
735 Elevator # 1 @ CATHCART 8
STOP CREW 1
87 days Fri 7/2/27 Wed 11/3/27
736 install steel columns/plates 10 days Fri 7/2/27 Fri 7/16/27
737 insulate shaft/inspect 5 days Mon 7/19/27 Fri 7/23/27
738 drywall shaft and tape 10 days Mon 7/26/27 Fri 8/6/27
739 install elevator 35 days Mon 8/9/27 Mon 9/27/27
740 fire caulk and close in door openings
10 days Tue 9/28/27 Mon 10/11/27
741 adjustment 5 days Tue 10/12/27 Mon 10/18/27
742 call in for State 10 days Tue 10/19/27 Mon 11/1/27
743 State inspect elevator 2 days Tue 11/2/27 Wed 11/3/27
744 GARAGE PARKING 3 LEVELS 320 days Mon 8/17/26 Fri 11/19/27
745 build 1, 2 and 3 hour walls storages/elev. Shaft/MEP rooms
50 days Mon 8/17/26 Mon 10/26/26
746 run sprinkler lines 25 days Tue 10/27/26 Wed 12/2/26
747 install MEP 30 days Thu 12/3/26 Fri 1/15/27
748 install trash chutes 10 days Thu 4/8/27 Wed 4/21/27
749 run sprinklers to trash chutes/inspect
7 days Thu 4/22/27 Fri 4/30/27
750 close in shafts at trash chute front12 days Mon 5/3/27 Tue 5/18/27
751 install door frames, doors, gates 20 days Tue 1/19/27 Tue 2/16/27
752 materials storage/laydown (optio 100 days Wed 2/17/27 Thu 7/8/27
753 end materials storage 30 days Fri 7/9/27 Thu 8/19/27
754 clean 18 days Fri 8/20/27 Wed 9/15/27
755 pressure wash 9 days Thu 9/16/27 Tue 9/28/27
756 stripe 7 days Wed 11/3/27 Thu 11/11/27 install steel columns/plates 7/2 insulate shaft/inspect 7/19 drywall shaft and tape 7/26 install elevator 8/9 fire caulk and close in door openings 9/28 adjustment 10/1 call in for State 10/
State inspect elevator 11/ run sprinkler lines 10/27 install MEP 12/3 install trash chutes 4/8 run sprinklers to trash chutes/inspect 4/22 close in shafts at trash chute fronts 5/3 install door frames, doors, gates 1/19 materials storage/laydown (option) 2/17 end materials storage 7/9 clean 8/20 pressure wash 9/16 stripe 11/
Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
757 install wheel stops/truncated domes 6 days Fri 11/12/27 Fri 11/19/27
758 install FE cab's 5 days Wed 9/29/27 Tue 10/5/27
759 systems start up/testing 20 days Wed 10/6/27 Tue 11/2/27
760 Inspections 10 days Wed 11/3/27 Tue 11/16/27
761 Complete phase for TCO 40 days Mon 10/25/27 Tue 12/21/27 install wheel stops/truncated domes 11/ install FE cab's 9/29 systems start up/testing 10/6
Inspections 11/
Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress