Southwest Storage and Repump Facility
Solicitation number
26-B-50IF
Issued by
Volusia County, Florida

About this file

This is a Bid Price Sheet (Exhibit G) for the Southwest Storage and Repump Facility project in Volusia County, Florida. The project encompasses the construction of a new two-million-gallon potable water storage tank, a high-service pump station, and a combined electrical/IT/chemical storage building, along with all associated civil site development, concrete foundations, mechanical systems, electrical and instrumentation installations. The bid sheet itemizes over 100 line items organized into 15 major categories, including site work, ground storage tank installation, yard piping, chemical feed systems, high-service pumps, sanitary sump pump stations, an operations building, and electrical and SCADA systems. Site work quantities include tree removal (116 each), clearing and grubbing (111,000 cubic feet), excavation of unsuitable material (4,200 cubic yards), and importing fill (18,200 cubic yards). The operations building measures 3,100 square feet, and the project requires three high-service pump units with associated piping assemblies and concrete pads.

The bid price sheet contains no pricing information, as all unit prices and total prices are listed as zero dollars, indicating this is a blank template for contractor submission. All items are priced on a lump-sum basis except for unit-priced line items such as tree removal, fill importing, fencing, and the two-inch force main. The bid includes provisions for a mobilization allowance not to exceed five percent of total project cost, demobilization, record drawings, and closeout. A payment and performance bond is required and must be included in the total bid price. The sheet does not specify bid submission deadlines, response dates, site visit requirements, or award timelines, as these details would typically appear in separate bidding documents or the RFP instructions.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Tab

Exhibit G - Bid Price Sheet 26-B-50IF
Southwest Storage & Re-Pump Facility (SWSRF)
Contractor Name:
ItemDescriptionUNITQTYUnit PriceTotal Price
1Mobilization, Bid Bond, Insurance, and General Conditions
1.1Mobilization, Bid Bond, Insurance, and General Conditions (can not be more than 5% of project cost)LS1$ - 0$ - 0
2Demobilization, Record Drawings and Closeout
2.1Demobilization, Record Drawings and CloseoutLS1$ - 0$ - 0
3Pre-Construction Video
3.1Pre-Construction VideoLS1$ - 0$ - 0
4Site Work
4.1Erosion & Sedimentation Control (including silt fence)LS1$ - 0$ - 0
4.2Tree RemovalEA116$ - 0$ - 0
4.3Clearing and GrubbingCF111000$ - 0$ - 0
4.4Excavation and Removal of Unsuitable MaterialCY4200$ - 0$ - 0
4.5Importing FillCY18200$ - 0$ - 0
4.6Proofrolling SiteCF111000$ - 0$ - 0
4.7DewateringLS1$ - 0$ - 0
4.8GradingLS1$ - 0$ - 0
4.9SodSY624$ - 0$ - 0
4.10SeedSY8665$ - 0$ - 0
4.11Stormwater Piping System and StructuresLS1$ - 0$ - 0
4.12Stormwater PondLS1$ - 0$ - 0
4.13Concrete Pads for Above Ground Assemblies and Generator and TransformerCY46$ - 0$ - 0
4.14Concrete Driveway (6" thick)CY280$ - 0$ - 0
4.15Asphalt DrivewaySY275$ - 0$ - 0
4.16FencingLF1490$ - 0$ - 0
4.17Roll GateLS1$ - 0$ - 0
52.0 MG Ground Storage Tank (GST)
5.1Furnish & Install New GST (2,000,000 gal)LS1$ - 0$ - 0
5.2Furnish & Install 16" GST Fill Piping up to the Valve (including the Valve and couplings)LS1$ - 0$ - 0
5.3Furnish & Install 24" GST Discharge Piping up to the Valve (including the Valve and couplings)LS1$ - 0$ - 0
5.4Furnish & Install 8" GST Drain Piping (including the Valve)LS1$ - 0$ - 0
5.5Install Safety Ladder and Safety Rails Around the Roof HatchLS1$ - 0$ - 0
5.6Apply Interior CoatingLS1$ - 0$ - 0
5.7Furnish & Install GST In-Tank Pax MixerLS1$ - 0$ - 0
6Yard Piping
6.1Furnish & Install 16" DIP Supply and GST Fill Line including Fittings and 16" Gate ValveLS1$ - 0$ - 0
6.2Furnish & Install 24" DIP GST Discharge Piping including FittingsLS1$ - 0$ - 0
6.3Furnish & Install 24" DIP HSP Header and Discharge Piping including FittingsLS1$ - 0$ - 0
6.4Furnish & Install 24"/16" DIP Finished Water Discharge Piping including FittingsLS1$ - 0$ - 0
6.5Furnish & Install 16" DIP GST By-Pass Piping including Fittings and 16" Gate ValveLS1$ - 0$ - 0
6.6Furnish & Install 16" DIP SWSRF By-Pass Piping including Fittings and 16" Gate ValveLS1$ - 0$ - 0
6.7Furnish & Install Fire Hydrant with associated Piping and ValveEA1$ - 0$ - 0
6.8Furnish & Install 2" Potable Water Service Meter Assembly and Service to the FacilitiesLS1$ - 0$ - 0
6.9Connect SWSRF to the Potable Water Distribution SystemEA2$ - 0$ - 0
7Aboveground Check Valve Assembly
7.1Furnish & Install 16" DIP Check Valve Assembly on SWSRF By-Pass LineLS1$ - 0$ - 0
8Aboveground Solenoid Controlled Back Pressure Sustaining Valve and Flow Meter Assembly
8.1Furnish & Install 16" DIP Solenoid Controlled Back Pressure Sustaining Valve and Flow Meter Assembly on Supply LineLS1$ - 0$ - 0
9Aboveground Chemical Injection Assembly
9.1Furnish & Install 24" DIP Chemical Injection Assembly with Static Mixer and Injection Quills (Chlorine & Ammonia)LS1$ - 0$ - 0
10Aboveground Finished Water Flow Meter Assembly
10.1Furnish & Install 24" DIP Finished Water Flow Meter AssemblyLS1$ - 0$ - 0
11Chlorine & Ammonia Chemical Feed System & Storage
11.1Furnish & Install Single Wall Chlorine Storage Tank (500 gal)EA1$ - 0$ - 0
11.2Furnish & Install Single Wall Ammonia Storage Tank (100 gal)EA1$ - 0$ - 0
11.3Furnish & Install Chlorine Chemical Feed SkidEA1$ - 0$ - 0
11.4Furnish & Install Ammonia Chemical Feed SkidEA1$ - 0$ - 0
11.5Furnish & Install Water Quality AnalyzersLS1$ - 0$ - 0
11.6Furnish & Install Chemical Yard PipingLS1$ - 0$ - 0
11.7Furnish & Install Water Quality Sampling Yard PipingLS1$ - 0$ - 0
11.8Furnish & Install Safety Shower and EyewashEA1$ - 0$ - 0
11.9Furnish & Install Hose Bib AssemblyEA3$ - 0$ - 0
12High Service Pumps
12.1Furnish & Install HSP Piping AssemblyEA3$ - 0$ - 0
12.2Furnish & Install High Service Pumps & MotorsEA3$ - 0$ - 0
12.3Furnish & Install Adjustable Pipe SupportEA6$ - 0$ - 0
12.4Form & Pour Three (3) Concrete Pads for HSPsCY9$ - 0$ - 0
13Sanitary Sump Pump Station and 2-inch Force Main
13.1Sanitary Sump PumpLS1$ - 0$ - 0
13.22-inch Force MainLF260$ - 0$ - 0
14Operations Building
14.1Furnish & Install Operations Building (62 x 50 SF)SF3100$ - 0$ - 0
14.2Furnish & Install HVAC for Operations Building - Electrical & I&C and IT RoomsLS1$ - 0$ - 0
14.3Furnish & Install Louvres Exhaust Fan for HSP RoomLS1$ - 0$ - 0
15Electrical & I/C SCADA
15.1Furnish & Install Electrical & I&C , GST, HSP, & Chemical Feed SystemsLS1$ - 0$ - 0
15.2Furnish & Install Electrical & IT RoomLS1$ - 0$ - 0
15.3Furnish & Install 250 kW GeneratorLS1$ - 0$ - 0
15.4Grounding & Lightening ProtectionLS1$ - 0$ - 0
15.5Furnish & Install Exterior and Interior LightingLS1$ - 0$ - 0
15.6Furnish & Install FPL Power Feed & TransformerLS1$ - 0$ - 0
15.7Furnish & Install Security SystemLS1$ - 0$ - 0
Base Bid Subtotal Construction$ - 0
Payment and Performance bond$ - 0
Total Bid Price (inclusive of payment and performance bond)$ - 0