This is a Construction Manager Cost Allocation Matrix for the Katharine Hepburn Cultural Arts Center Expansion project in Old Saybrook, Connecticut. The matrix allocates project costs across three primary cost categories: General Conditions/General Requirements (GC/GR), Construction Manager (CM) Fee, and Cost of Work. The document delineates 57 line items categorized into five sections: Construction Manager's Staff, Construction Manager's General Requirements, Off-Site Construction Services and Staff, Temporary Facilities, and Insurance/Bonds/Fees, with Trade Contractor Costs listed as the final section. Each line item is designated to one of the three cost categories, establishing which party bears the financial responsibility. The allocation specifies that CM staff positions (such as Project Executive, Senior Project Manager, Project Managers, and various site personnel) are charged to General Conditions, while CM office operations, temporary facilities, and trade contractor support costs are similarly allocated. The matrix ensures clear cost segregation for the two-story, 7,290 square-foot addition and 1,396 square-foot interior renovation project, which must proceed while maintaining full operational continuity of the existing facility that hosts hundreds of annual events.
The cost allocation matrix operates in conjunction with Exhibit E pricing and establishes the framework for a fixed-price, cost-of-work Construction Manager at Risk (CMaR) contract with no adjustment or escalation provisions for the full project duration. All hourly rates and pricing submissions are held firm through project completion, anticipated for mid-December 2027. The matrix differentiates between reimbursable general conditions costs, the CM's fee component, and the cost of work performed by trade contractors, enabling transparent cost tracking and payment distribution. This structured allocation mechanism supports the project's modified AIA Document A133-2019 contract terms and accommodates the complex operational requirements necessitated by the cultural arts center's continuous use during construction, with critical long-lead material releases beginning November 27, 2026, and primary construction activities spanning March through August 2027.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Exhibit F CM Cost Allocation Matrix
GC/GR = General Conditions and General Requirements Construction Manager’s Staff (General Conditions)
Item # Description
GC/GR
CM Fee Cost of Work 1 Project Executive X 2 Senior Project Manager X 3 Project Manager X 4 Assistant Project Manager X 5 General Superintendent X 6 Project Superintendent X 7 Assistant Project Superintendent X 8 MEP Coordinator X 9 Project Engineer X
10 Office Engineer X 11 Scheduling Personnel X 12 Field Engineer X 13 Admin. Asst./ Receptionist/Secretary X 13 Plan Clerk/ Document Management X 14 MEP/FP Coordination/BIM/Coordination Drawings X 15 Accounting X 16 Reporting, Submissions, Change Management X 17 Safety Manager/Personnel/OSHA Compliance X 18 QA/QC Manager/Personnel X 19 Staff Travel, Transportation, Lodging, Meals, T i i X
20 All other staff dedicated to the Project X
Construction Manager’s General Requirements
Item # Description
GC/GR
CM Fee Cost of Work 21 CM Office/ Trailer Rental, Furnishings, and Cleaning X 22 Copy/Fax/Printer & Supplies X 23 Safety Equipment, Fire Ext & First Aid X 24 Temporary Toilets for CM use X 25 Computer Equipment and all necessary Software X 26 Water, Ice, Coffee, Cups, Etc. X 27 Project Signs and Bulletin Boards X 28 Mobilization and Demobilization X 29 Utilities for CM Offices (set up and consumption) X 30 Document Management Programs/Costs X 31 Construction Progress Photos X 32 Radio, Phones, and Communications Equipment X
Off-Site Construction Services and Staff (CM’s Corporate Office)
Item # Description
GC/GR
CM Fee Cost of Work 33 Any Home Office Personnel supporting the Project h H Offi X 34 Home Office Overhead and Other Costs X 35 CM’s Profit and Overhead X
Temporary Facilities
Item # Description General
Conditions CM Fee Cost of Work
36 Temporary Toilets for Trade Contractor Use X 37 Opening Protec�on X 38 Handrails and Toe Boards X 39 Opening Protec�on X 40 Temporary Stairs X 41 Temporary Enclosures/Weather Protec�on X 42 Temporary Heat X 43 Project Fencing/Safety Fencing/Security Fencing X 44 Temporary Stairs X 45 Safety Ne�ng/Fall Protec�on X 46 Dumpsters/Debris Removal/Chutes X 47 Dust Control/Street Cleaning X 48 Off-Site Storage for Trade Contractors X 49 On Site Storage for Trade Contractors X 50 Tools and Equipment X 51 Temporary Power for the Project X 52 Temporary Water for the Project X
Insurance, Bonds, Fees
Item # Description General
Conditions CM Fee Cost of Work 53 CM’s Performance and Payment Bonds X 54 Trade Contractor Perf. and Pmt. Bonds (if required) X 55 State of Connecticut Educational Fee X
55a CM’s insurance costs X
Trade Contractor Costs
Item # Description General
Conditions CM Fee Cost of Work 56 Trade Contractor Contracts for the Work X 57 Final Cleaning X