Exhibit B Schedule.pdf

PDF 68 KB Posted

Attached to
Katharine Hepburn Cultural Arts Center Expansion
Solicitation number
39702
Issued by
Middlesex County, Connecticut

About this file

This is a construction project schedule document (Exhibit B Schedule) outlining the timeline and sequencing for a building construction and permitting project. The project commences with long lead time material and equipment releases beginning November 27, 2026, and progresses through multiple construction phases including selective demolition, site work, structural steel erection, building envelope installation, and interior construction activities. Key milestones include structural steel erection scheduled from March 26 through June 3, 2027; building envelope work from June 4 through August 5, 2027; and interior finishes and MEP (mechanical, electrical, plumbing) systems completion by mid-November 2027. The schedule incorporates overlapping work phases for efficiency, with interior partitions, MEP rough-in, interior finishes, and MEP finishes occurring concurrently during late summer and fall 2027. Final project activities include a 90-day temporary certificate of occupancy process (November 22-24, 2027), punchlist contractor work, and owner furniture installation, both extending through December 17, 2027, with the overall project completion targeted for mid-December 2027.

The schedule presents no information regarding pricing terms, set-asides, funding sources, or contract value. The document serves solely as a project timeline reference tool and does not contain budget allocation, financing details, or other financial specifications necessary for bid preparation or contract award determination.

View the file

Other files

File Type Posted
39702_Nov_3_26_solicitation_doc.pdf PDF
39702_Nov_4_26_solicitation_doc.pdf PDF
39702_Nov_2_26_solicitation_doc.pdf PDF
KHCAC CD PROJECT MANUAL.pdf PDF
39702_Nov_5_26_solicitation_doc.pdf PDF
KHCAC RFQP.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task Name Duration Start Finish

2 CONSTRUCTION & PERMITTING

3 Long Lead Time Release

Materials, Equip, Elevator

47 days Fri 11/27/26 Mon 2/1/27

4 Selective Demolition, Make Safe, Construction Barricades

15 days Mon 12/7/26 Fri 12/25/26

5 Site Work, Underground Utilities, Ecavation, Foundations

60 days Fri 1/1/27 Thu 3/25/27

6 Structural Steel Erection 50 days Fri 3/26/27 Thu 6/3/27

7 Building Envelope 45 days Fri 6/4/27 Thu 8/5/27

8 Interior Partitions 30 days Fri 8/6/27 Thu 9/16/27

9 MEP rough-in 30 days Fri 8/27/27 Thu 10/7/27

10 Interior Finishes 35 days Mon 9/20/27 Fri 11/5/27

11 MEP Finishes 40 days Mon 9/27/27 Fri 11/19/27

12 TCO (90day) 3 days Mon 11/22/27 Wed 11/24/27

13 Punchlist Contractors 20 days Mon 11/22/27 Fri 12/17/27

14 Owner Furniture 20 days Mon 11/22/27 Fri 12/17/27

11/2912/612/1312/2012/27 1/3 1/10 1/17 1/24 1/31 2/7 2/14 2/21 2/28 3/7 3/14 3/21 3/28 4/4 4/11 4/18 4/25 5/2 5/9 5/16 5/23 5/30 6/6 6/13 6/20 6/27 7/4 7/11 7/18 7/25 8/1 8/8 8/15 8/22 8/29 9/5 9/12 9/19 9/26 10/310/1010/1710/2410/3111/711/1411/2111/2812/512/1212/19

December January February March April May June July August September October November December

SCHEDULE EXHIBIT B