Interdisciplinary Research Building Replacement of the Fire Alarm System
Solicitation number
PE-51200-RFQ-2027-000000040
Issued by
Richmond County, Atlanta City, Georgia

About this file

Exhibit D is a Preconstruction Costs and Expenses Breakdown form associated with the Interdisciplinary Research Building Fire Alarm System Replacement project in Georgia. The form provides a structured template for bidders to itemize preconstruction expenses across two primary categories: Supervision and Management, and Miscellaneous costs. The Supervision and Management section includes line items for staffing such as Senior Project Manager, Project Manager, Preconstruction Manager, Project Superintendent, Cost Control personnel, Scheduling staff, Secretary, and Consultants, with quantities measured in months. The Miscellaneous section encompasses operational expenses including office supplies, postage and shipping, blueprint and photostat services, phone charges, courier services, and travel expenses, also measured in monthly or lump sum increments.

The form is designed to capture labor costs, material costs, subcontractor labor, and combined subtotals for each expense category, with a final total for all preconstruction costs and expenses. As presented, all line items display zero dollar values, indicating this is a blank template or placeholder awaiting bidder completion. The form allows bidders to provide detailed cost breakdowns across multiple cost categories to facilitate accurate project budgeting and expense tracking during the preconstruction phase of the fire alarm system replacement project. The document is dated August 25, 2026.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Description Qty Unit Labor* Mat'l** Sub Labor

Subtotal Mat'l

Subtotal Sub

Subtotal Total Notes A. Preconstruction - Supervision & Management:

1 Senior Project Mgr. mos $0 $0 $0 $0 2 Project Mgr. mos $0 $0 $0 $0 3 Preconstruction Manager mos $0 $0 $0 $0 4 Project Supt. mos $0 $0 $0 $0 5 Cost Control mos $0 $0 $0 $0 6 Scheduling mos $0 $0 $0 $0 7 Secretary mos $0 $0 $0 $0 8 Consultant mos $0 $0 $0 $0 9 Other (Identify) mos $0 $0 $0 $0

Subtotal $0

B. Preconstruction - Miscellaneous 10 Office Supplies mos $0 $0 $0 $0 11 Postage & Shipping mos $0 $0 $0 $0 12 Blueprint/Photostat. ls $0 $0 $0 $0 13 Phone Charges mos $0 $0 $0 $0 14 Phone Charges-Long Dist. mos $0 $0 $0 $0 15 Courier Service mos $0 $0 $0 $0 16 Travel Expenses mos $0 $0 $0 $0 17 Other (Identify) mos $0 $0 $0 $0

Subtotal $0

TOTAL ALL PRECONSTRUCTION COST AND EXPENSES $0

PRECONSTRUCTION COSTS AND EXPENSES BREAKDOWN

EXHIBIT D