This document is a CM/GC Fee Proposal form used by the State of Georgia for construction management/general contractor compensation on the Interdisciplinary Research Building Fire Alarm System Replacement project. The project involves replacing the fire alarm system in a 211,000 gross square foot research building on the Health Science campus, including the fire alarm panel, sensors, horns, strobes, detectors, communication backbone, and integration into the existing campus fire alarm mesh network. The fee proposal structure requires the CM/GC to establish and agree upon compensation with the Owner that represents the full amount of gross profit and covers all project expenses not identified as Costs of the Work, provided the CM/GC performs all contract requirements within established time limits. The proposal separates compensation into two components: a fixed Preconstruction Fee for consulting services during the preconstruction phase and a fixed Construction Fee for services during the construction phase.
The CM/GC's compensation model also includes a maximum amount for Preconstruction Costs and Expenses and Construction Overhead Costs, which are detailed in separate attachments and must not include the respective fees themselves. The form requires the CM/GC to complete the dollar amounts for each fee category and overhead cost component, with signature authority from a designated CM/GC officer. This structure allows for transparent cost accounting and ensures that direct and incidental expenses are capped and separately identified from the CM/GC's gross profit fees, establishing clear financial boundaries between fee compensation and reimbursable costs throughout the preconstruction and construction phases of the project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT C
Project #, Project Name, Institution, City, Georgia
CM/GC FEE PROPOSAL
1. CM/GC’S FEE:
Basis of Fee. The CM/GC’s fee is the amount, established by and agreed to by both parties, which is the full amount of compensation due to the CM/GC as gross profit, and for any and all expenses of the Project not included and identified as a Cost of the Work, provided that the CM/GC performs all the requirements of the Contract Documents within the time limits established. (See Article 4.1.1 of the General Requirements.) If applicable, the fees and costs should be broken down by each site within a multi-site project.
A. PRECONSTRUCTION FEE:
Pre-Construction Fee. Representing the gross profit for the pre-construction consulting services provided by CM/GC as set forth in Section 2, Parts 1 and 2 of the General Requirements, and as described in Paragraph 4.1.1.1(a), Owner shall pay to CM/GC a Preconstruction Fee:
TOTAL
Pre-Construction Fee (fixed fee)
B. CONSTRUCTION FEE:
Construction Fee. Representing the gross profit for the construction services provided by CM/GC as set forth in Section 3, Part 1 of the General Requirements, and as described in Paragraph 4.1.1.1(b) Owner shall pay to CM/GC a Construction Fee.
TOTAL
Construction Fee (fixed fee)
2. CM/GC’S PRECONSTRUCTION COSTS AND CONSTRUCTION OVERHEAD COSTS:
The CM/GC’s Overhead Costs. The maximum amount for the CM/GC’s Pre-Construction Costs and Expenses and Construction Overhead Costs are inclusive of all direct and incidental expenses are as described in Paragraph 4.1.1.2 .
AMOUNT
A. Maximum Pre-construction Costs & Expenses (From Attachment A. Do not include the Pre- Construction Fee in this amount)
B. Maximum Construction Overhead Costs (From Attachment B. Do not include the Construction Fee in this amount)
Total Maximum Overhead Cost (Sum of A & B)
CM/GC Name
By:_________________________________________________________ Signature of CM/GC Officer
Title of CM/GC Officer
| EXHIBIT C |
| 1. CM/GC’S FEE: |
| A. PRECONSTRUCTION FEE: |
| B. CONSTRUCTION FEE: |
| 2. CM/GC’S PRECONSTRUCTION COSTS AND CONSTRUCTION OVERHEAD COSTS: |
File details come from the government source that posted it. Updated .