Exhibit_D_Ovivo_Mechanism_Components_(Revised).pdf

PDF 398 KB Posted

Attached to
Northwest Water Reclamation Facility Clarifier #4 Rehabilitation
Solicitation number
IFB- 25 - 257
Issued by
Pinellas County, Florida

About this file

This document is a budget proposal from Ovivo for the City of St. Petersburg, specifically addressing the Northwest Water Reclamation Facility's request for a replacement secondary clarifier mechanism. The proposal details the supply of one 135-foot diameter C4D-CMD type spiral blade clarifier mechanism for Secondary Clarifier #4. The proposed equipment includes comprehensive components such as a walkway superstructure, platform, center column, sludge raking arms, and various submerged and non-submerged steel components. Ovivo estimates a 10-week timeline for submittal drawings after purchase order receipt and a 28-week timeline to begin shipping the products after approved drawings are received.

The proposal includes detailed specifications for surface preparation, painting, and equipment coating, with a total mechanism weight of approximately 54,000 pounds. Field service is included, comprising two days and two trips to the site for adjusting, servicing, and checking out the mechanisms, with static torque testing included. The document outlines numerous included components and services such as anchor bolts, electrical controls, VFD controller, operation and maintenance manuals, and freight to the jobsite. Notably, several items are explicitly not included, such as demolition services, finish painting, stairways, and scum piping, which would be the responsibility of the purchaser.

View the file

Other files

File Type Posted
Northwest_Water_Reclamation_Facility_Clarifier_#4_Rehabilitation_(Addendum_#5_Revision).pdf PDF
Pre-bid_8-21_sign_in_sheet.pdf PDF
Pre-bid_sign_in_sheet.pdf PDF
Exhibit_A_Technical_Specifications_Clarifier_No._4_(revised).docx DOCX document
Exhibit_G_JWC_Environ_Muffin_Monster_Grinder_Pump_Control_Panel.pdf PDF
Exhibit_F_Contract_Plans_Clarifier_No._5_NEWRF_(reference_only_of_similar_project).pdf PDF
Exhibit_E_Photo_Documentation_NE_NW_WAS_Pumping_Station_Pads_(Reference_only_of_similar_installation)_.pdf PDF
Exhibit_C_As_Built_Prints,_Clarifier_No._4_(Revised).pdf PDF
Exhibit_B_Coating_Specifications_(Revised).pdf PDF
Exhibit_A_Technical_Specifications_Clarifier_No._4.pdf PDF
Exhibit_A_Technical_Specifications_Clarifier_No._4.pdf PDF
Northwest_Water_Reclamation_Facility_Clarifier_#4_Rehabilitation_(Addendum_#1_Revision).pdf PDF
Pre_Bid_Sign_in_Sheet_Clairifier.pdf PDF
Agreement__Clarifier_#4_Rehabilitation_RM_Comments_8-5-25.docx DOCX document
Ovivo_Mechanism_&_Component_Info_(Exhibit_A).docx DOCX document
200218_NWWRF_Clarifier_4_Technical_Specs.pdf PDF
NWWRF_Clarifer_#4_As_Built_Prints_(Exhibit_B).pdf PDF
09_96_00_Spec_NWWRF_Clarifier_4_(Exhibit_C).docx DOCX document
NWWRF_Clarifier_#4_Rehab_Bid_Proposal_Form.xlsx XLSX spreadsheet
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NORTHWEST WATER RECLAMATION FACILITY

SECONDARY CLARIFIER #4

135’ OVIVO TYPE C4D

REQUEST:

The City of St Petersburg. is requesting the supply of one new replacement secondary clarifier mechanism at the Northwest WRF.

DESIGN:

OVIVO proposes the supply one (1) 135 diameter C4D-CMD type spiral blade clarifier mechanism.

http://www.ovivowater.com

SCOPE OF SUPPLY: ITEM I – SECONDARY CLARIFIER – OVIVO TYPE C4D

Ovivo (formerly EIMCO Water Technologies) proposes mechanisms which are based upon our standard engineering practices and details. Specifics are shown below:

DESIGN CRITERIA AND DRIVE INFORMATION:

Number of Clarifiers 1

Clarifier Type C4D – Spiral scraper Secondary Clarifier

Clarifier Diameter 135’

SWD 15.15’ (approx.)

Freeboard 2’-0” ft (approx.)

Tank Bottom Slope 1:12

Walkway configuration Center support w/single side half bridge

AGMA Continuous Design Torque 33,400 ft-lb (Between 14 -18 ft/min tip speed)

Concrete Tank (New or Existing) exiting

NON-SUBMERGED COMPONENTS (INCLUDED):

COMPONENT TYPE COMPONENT DESCRIPTION

Walkway Superstructure (Truss Style)

3ft wide walking surface. Half bridge design extending from tank wall to center platform. Truss members to serve as handrail system

Platform Superstructure 9ft square with approximately 24” drive clearance

Walkway walking surface type ALUMINUM -- 1-1/4" I-Bar grating

Platform walking surface type ALUMINUM – 11-1/4" I-Bar grating

Handrail design/type ALUMINUM – Platform ONLY. 1-1/2" diameter 2-rail with 4" toe channel, field/sub-assembled mechanical system. No handrail along walkway. Walkway truss members to serve as handrail system

Non-Submerged construction materials (unless otherwise noted)

Stainless steel

SUBMERGED COMPONENTS (INCLUDED):

COMPONENT TYPE COMPONENT DESCRIPTION

Center column (Stationary) 48” diameter x ¼” thick with (4) influent port sized at 135% of the column area; with CMD adapter.

Center cage (Rotating) 5ft square.

Feedwell (Rotating) 40ft diameter x 7.5ft depth x 3/16” thick w/ supports from truss rake arms.

EDI (Rotating) 13ft diameter x 3ft depth x 1/4” thick w/ tangential scoop outlet ports.

Sludge raking arms (Rotating)

Two (2) full radius and (2) partial radius (square box truss design) with 3/16” thick spiral raking blades and 20 gauge 304 SS attachment squeegees.

Sludge manifold (Rotating) Approx. 7ft-4in diameter x ¼” thick (Size to be confirmed by tank floor layout).

Skimming Design (Stationary and Rotating)

One (1) 8ft scum box(Stationary) with a mechanical flush actuated by an adjustable actuator from the skimmer arm (Rotating) and two (2) skimming blade/mechanism systems (Rotating).

Submerged construction materials (unless otherwise noted)

Stainless steel.

OTHER COMPONENTS, SERVICES AND INFORMATION (INCLUDED):

-Drive Mechanism – C60LT

-Anchor bolts in 316 stainless steel.

-Assembly fasteners in 316 stainless steel.

Effluent launders and 316 stainless steel launder brackets

-Effluent weirs and scum baffles

-Density current baffles

-Electrical controls or control panels, push button stations, alarms, starters, mounting plates or brackets, conduit, wiring, mounting channels, photocells, etc… other than clarifier local control panel.

-Field welding. Minimal field welding will be necessary.

-VFD controller.

-Lubricants.

-Effluent Trough

-Local control panel

-Operation and Maintenance manuals.

-Service trips as noted in the “Field Service” section of this proposal.

-Surface preparation and paint as noted in the “Surface Preparation and Paint” section of this proposal.

-Any field measurements required for provision of this equipment.

-Anything else not explicitly included in the list of items included above.

-Freight, FCA factory, freight allowed to jobsite.

ITEMS NOT INCLUDED (But not limited to the following):

-Anchor templates and grout shield. We provide bolt circle dimensions for the center column and anchor positions.

-Demolition or erection services.

-Finish painting.

-Lamp posts.

-Weir, launder or baffle cleaning equipment.

-Stairways, access walkways, interconnecting walkways, gratings, etc., outside tank.

-Handrail around tank.

-Scum piping below or flexible connector to scum box stub nozzle.

-Dissimilar metals protection of any kind and for aluminum handrail and grating mounted to steel walkway members. Mastic/sealant/packing is also by others.

-Tank, platform or feedwell covers of any kind.

-Scum spray system

WEIGHTS:

APPROXIMATE TOTAL WEIGHT OF ONE (1) MECHANISM 54,000 LBS.

APPROXIMATE WEIGHT OF THE HEAVIEST SINGLE COMPONENT 6,100 LBS.

FIELD SERVICE:

Our proposal includes the service of a qualified service engineer for the following:

- Two (2) Days / Two (2) Trips at the site to assist in adjusting, servicing, and checking out these mechanisms, and in training the operators in maintenance, troubleshooting, and repair of the equipment. Static torque testing is included in these services.

- Additional service days can be purchased at the current rate.

SURFACE PREPARATION AND PAINT

Please see below for a rough visual representation of a similar unit to the proposed mechanism:

COMPONENTS SURFACE

PREP.

PRIME

COAT

2ND COAT 3RD COAT

DRIVE UNIT SSPC-SP-06 Tnemec N69 Tnemec N69 Tnemec Endura-shield

GEARMOTOR STANDARD COATING BY GEARMOTOR MANUFACTURER

SUBMERGED STEEL Stainless steel

NON-SUBMERGED

STEEL

Stainless steel

BUDGET PROPOSAL PRICING

ITEM EQUIPMENT

ESTIMATED

SHIP DATE*

PRICE

I

(1) 135ft dia. Spiral blade clarifier

TYPE - C4D-CMD

ESTIMATED LEAD TIMES

*Ovivo’s estimated timeline for submittal drawings is ten (10) weeks after Purchaser’s receipt of Ovivo’s written acknowledgement of an approved purchase order. Ovivo’s estimated timeline to start shipping the products is about twenty-eight (28) weeks after receipt of approved drawings from Purchaser.