About this file

This solicitation is for an Indefinite Delivery Indefinite Quantity Multiple Award Construction Contract for design-build and design-bid-build construction projects at Marine Corps Air Station Iwakuni, Japan. The contract has a total not-to-exceed amount of $495 million to be awarded across multiple contracts, with individual task order values ranging from $50 million to $2.5 billion. The Naval Facilities Engineering Command will issue task orders under the contract for new construction, renovation, maintenance, and repair projects like building demolition, equipment repair, piping work, electrical work, roadwork and more. There is one seed project titled "Repair to Barracks B#314 Enlisted Quarters" valued between $1 million and $2.5 billion that will be awarded concurrently with the initial MACCs. Offers are due by October 24, 2022 at 1430 Japan Standard Time. The minimum contract guarantee is $500,000 and a task order for the minimum will be issued with any MACC awards that do not include the seed project.

View the file

Other files

File Type Posted
QA2_N4008422R0041_10142022.pdf PDF
QA1_N4008422R0041_10132022.pdf PDF
N4008422R0041_RFP.pdf PDF
EXHIBIT_F_Price Proposal Form_.doc DOC document
EXHIBIT_B_Construction and Design Experience Project Data Sheet.doc DOC document
EXHIBIT_D_Past Performance.docx DOCX document
EXHIBIT_E_Technical Solution Submittal.docx DOCX document
Attach_1_Pre-Bid_Inquiry_Form.xlsx XLSX spreadsheet
EXHIBIT_C_Safety Narrative.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CUI//FEDCON [when filled in] Source Selection Information – See FAR 2.101 & 3.104 [when filled in] N4008422R0041 Factor 1 - EXHIBIT A

FACTOR 1 – TECHNICAL APPROACH SUBMITTAL

Part I: ORGANIZATIONAL CHART, INCLUDING ENTITY ROLES AND RESPONSIBILITIES:

Delete information in red as necessary.

(1) Provide a simple organizational chart that clearly identifies the lines of authority between the proposed primary construction firms and primary design firms for this contract. The organization chart shall also include the following:

(a) A brief description of the role and responsibility of each entity identified in the organizational chart, and

(b) If claiming the experience of an entity under Factor 2 that entity’s name must also be included in the organizational chart.

The organization chart shall not exceed (1) one single-sided page. Pages in excess of the page limit specified will not be considered/evaluated.

FACTOR 1 – TECHNICAL APPROACH SUBMITTAL

Part II: AGREEMENTS BETWEEN OFFEROR AND ENTITIES INCLUDED IN ORGANIZATIONAL CHART Delete information in red as necessary.

(2) Provide signed copies of the agreements between the Offeror and the entities included in the Offeror’s organizational chart. These agreements include but are not limited to the following:

(a) joint venture agreement (JVA), partnership agreement (PA), teaming agreement (TA), approved mentor protégé agreement (MPA), Letter of commitment (LOC), etc.

NOTE:

· All submitted agreements shall be signed by each member of the offeror’s team, i.e., by each JVA member, PA partner, TA team member, subcontractor, parent company, subsidiary, or other affiliated company, etc., as applicable.

· The Designer of Record’s (DOR) LOC shall be addressed from the DOR to the Offeror. The DOR’s authorized signing authority shall sign the LOC.

Revised April 2011

CUI//FEDCON [when filled in] Source Selection Information – See FAR 2.101 & 3.104 [when filled in]