About this file
This is a Special Provisions document from the Oregon Department of Transportation (ODOT) for the District 13 Rock Production 2025 Project in Union and Baker Counties. The project involves rock production and stockpiling of aggregate materials at the Clover Creek Quarry, with delivery to two locations: North Powder Stockpile Site and Baker Maintenance Station. The project requires production and delivery of up to 15,000 cubic yards of Graded Medium Chip Rock and 5,000 cubic yards of Sanding Rock at each location, for a total potential of 30,000 cubic yards of Graded Medium Chip Rock and 10,000 cubic yards of Sanding Rock. The work includes site preparation, rock extraction, crushing, stockpiling, and environmental protection measures.
The contractor must comply with specific technical requirements for aggregate gradation, quality, and handling. Environmental considerations include erosion control, pollution prevention, protection of cultural resources, and migratory bird protection. The project requires coordination with multiple utilities including Marathon Petroleum, Williams NW Pipeline, Avista Utilities, and others. The contractor must also implement specific site rehabilitation measures including seeding with prescribed native grass mixtures and site cleanup upon completion. No separate payment will be made for environmental protection or source site preparation work, as these costs are to be included in the appropriate bid items.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Exhibit B Plans~7.pdf | ||
| Award Letter.pdf | ||
| 00012703 Invitation.To.Bid~1.docx | DOCX document | |
| Required Supplemental Request Form - Goods and Trade Services.dat | — | |
| 00012703 Preliminary Results.xlsx | XLSX spreadsheet | |
| 00012703 Bid Cover Sheet.docx | DOCX document | |
| 00012703 Sample.Contract.docx | DOCX document | |
| 00012703 Intent To Award.xlsx | XLSX spreadsheet | |
| Exhibit E Material Source Narrative~5.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIAL PROVISIONS
FOR HIGHWAY CONSTRUCTION
OREGON DEPARTMENT OF TRANSPORTATION
SALEM, OREGON
ROCK PRODUCTION
DISTRICT 13 ROCK PRODUCTION 2025 PROJECT
VARIOUS HIGHWAYS
UNION & BAKER COUNTIES
MARCH 2025
District 13 Rock Production 2025 Project
TABLE OF CONTENTS FOR SPECIAL PROVISIONS
WORK TO BE DONE
SECTION 00150 - CONTROL OF WORK
SECTION 00165 - QUALITY OF MATERIALS
SECTION 00210 - MOBILIZATION
SECTION 00235 - AGENCY PROVIDED MATERIAL SOURCES
SECTION 00290 - ENVIRONMENTAL PROTECTION
SECTION 00335 - BLASTING METHODS AND PROTECTION OF EXCAVATION
BACKSLOPES
SECTION 00680 - STOCKPILED AGGREGATES
OREGON DEPARTMENT OF TRANSPORTATION
FOR
Rock Production
Various Highways Union & Baker Counties
PROFESSIONAL OF RECORD CERTIFICATION:
Seal w/signature
I certify the Special Provision Section(s) listed below are applicable to the design for the subject project for material source rock production and stockpiling. Modified Special Provisions were prepared by me or under my supervision.
Section(s) 00235, 00335 and 00680
FINAL ELECTRONIC DOCUMENT AVAILABLE UPON REQUEST
2025.01.23 15:07:26 -08'00'
SPS_M24093, District 13 Rock Production 2025 Project, Contract, March 2025 1
WORK TO BE DONE
The Work to be done under this Contract consists of the following:
1. Provide aggregate in stockpile, at the specified place of delivery.
2. Perform additional and Incidental Work as called for by the Specifications and Plans.
APPLICABLE SPECIFICATIONS
The Specifications that are applicable to the Work on this Project is the 2024 edition of the "Oregon Standard Specifications for Construction", as modified by these Special Provisions.
All number references in these Special Provisions shall be understood to refer to the Sections and subsections of the Standard Specifications bearing like numbers and to Sections and subsections contained in these Special Provisions in their entirety.
CLASS OF PROJECT
This is a State Project.
SPS_M24093, District 13 Rock Production 2025 Project, Contract, March 2025 2
SECTION 00150 - CONTROL OF WORK
Comply with Section 00150 of the Standard Specifications modified as follows:
00150.50(c) Contractor’s Responsibilities – Replace the bullet that begins “In addition to the notification required…” with the following bullet:
• In addition to the notification required in OAR 952-001-0090(7), notify the Engineer and the Utility as soon as the Contractor discovers any previously unknown Utility conflicts or issues. Contrary to the OAR, stop excavating until directed by the Engineer and allow the Utility a minimum of two weeks to relocate or resolve the previously unknown Utility issues; and
Add the following subsection:
00150.50(f) Utility Information (No Anticipated Relocations) - Within the Project limits, there are no anticipated relocations with the Utilities listed in Table 00150-1. The Contractor shall contact those Utilities having buried facilities and request that they locate and mark them for their protection prior to construction.
Table 00150-1
Utility
Contact Person's Name, Address, Email, and Phone Number
Marathon Petroleum Corporation / Tesoro Logistics NW Pro
Brandin Mann 201 N Phillippi St.
Boise, ID 83706 bmann@marathonpetroleum.com Work: (208) 373-2150 Cell: (208) 954-4999
Williams NW Pipeline Luke Danielson 606 South Oregon Ave.
Pasco, WA 99301 Luke.danielson@williams.com Work: (509) 521-3660
Avista Utilities Greg Ford 10201 South "F" St, Island City, OR 97850 gregory.ford@avistacorp.com Cell: (541) 441-0767
SPS_M24093, District 13 Rock Production 2025 Project, Contract, March 2025 3
Cascade Natural Gas Micah Blank 2100 13th St.
Baker City, OR 97814 Micah.Blank@cngc.com Work: (541) 523-1032 Cell: (541) 419-4032
Oregon Trail Electric Co-op Stephanie Elms 4005 23rd St, Baker City, OR 97814 selms@otec.coop Work: (541) 524-2829 Cell: (541) 519-1403
AT&T Alex Thompson 700 S Main St, Yreka, CA 96097 athompson@shastagroup.net Work: (530) 841-0621
Lumen John Archer 740 State St.
Salem, OR 97301 Johnathan.Archer@lumen.com relocations@centurylink.com Work: (503) 339-2219
MCI/Verizon Ian Lambie 2550 NE Aloclek Dr, Hillsboro, OR 97124 Ian.lambie@verizon.com Work: (503) 307-8212
Eagle Telephone Kevin Spencer 349 First Street, Richland, OR 97870 kevin@eagletelephone.net Work: (541) 540-5120
The Contractor shall notify, in writing, the Utilities listed above, with a copy to the Engineer, at least 14 Calendar Days before beginning Work on the Project. Utilities may require an on-site observer, at no cost to the Contractor.
Marathon Petroleum Corporation / Tesoro Logistics NW Pro, Williams NW Pipeline, Avista Utilities, & Cascade Natural Gas - Gas Utilities -
In the event of an emergency, and in addition to the calls required by the Utilities notification system, the Contractor shall call:
• Marathon Petroleum Corporation / Andeavor 1-800-725-1514; or
• Avista Corporation 1-800-227-9187; or
• Cascade Natural Gas Corporation 1-888-522-1130; or
• Williams Pipeline 1-801-584-6948.
SPS_M24093, District 13 Rock Production 2025 Project, Contract, March 2025 4
Oregon Trail Electric Co-op - Power Suppliers -
Energized power lines overhang portions of the Work with a minimum vertical clearance of 18 feet. The Contractor shall maintain at least 10 feet of safety clearance. Exceptions require written approval from the Power Supplier(s) and may require an on-site safety watcher, at no cost to the Contractor. The Contractor shall provide the Engineer a copy of the written approval of exception before beginning Work.
AT&T, Lumen, MCI/Verizon, & Eagle Telephone - Telecommunication Utilities -
The Contractor shall obtain written approval from Telecommunication Utilities that have fiber optic communication cable facilities, for excavating within 10 feet of a buried fiber optic communications cable. Telecommunication Utilities may require an on-site safety representative at no cost to the Contractor for monitoring purposes. The Contractor shall provide the Engineer a copy of the written approval before beginning Work.
SECTION 00165 - QUALITY OF MATERIALS
Comply with Section 00165 of the Standard Specifications modified as follows:
00165.35(e) Certificate of Origin of Construction Materials – Replace this subsection, except for the subsection number and title, with the following:
When a certificate of material origin for construction materials is specified, complete the form furnished by the Engineer as required by 00160.20(d) for Federal-aid projects.
SPS_M24093, District 13 Rock Production 2025 Project, Contract, March 2025 5
SECTION 00210 - MOBILIZATION
Comply with Section 00210 of the Standard Specifications.
SECTION 00235 - AGENCY PROVIDED MATERIAL SOURCES
Section 00235, which is not a Standard Specification, is included in this Project by Special Provision.
Description
00235.00 Scope - This Work consists of utilizing Agency provided prospective or mandatory material source as the Contractor elects or as required for the construction of the Contract.
00235.01 Material Source Specific Requirements - The following prospective material source, for the production of all Aggregate products for this Project, that may warrant investigation and consideration for use by the Contractor on this Project is as follows:
(a) Prospective Material Source, Clover Creek Quarry:
• Source Number - OR-31-004-5
• DOGAMI Number - 31-0001
• Location - Approximately 7 miles north of North Powder on Interstate_84 in the
SW1/4 NE1/4 of Section 07, T. 05 S., R. 39 E., W.M.
• Access - At Exit 278 of Interstate 84, travel approximately 1.8 miles north on
Oregon Trail Road, then west approximately 0.4 miles on the access road.
• Available Area for Equipment Setup, Stockpiling, and Processing Aggregate:
• Existing - 3.5 acres
• Development - 3.0 acres
00235.03 Laws - Conduct operations within the material source according to all applicable State, county, and federal laws including mining and fire laws. Provide, operate, and maintain wildland firefighting equipment appropriate for the current fire levels on-site at all times during all material source operations.
SPS_M24093, District 13 Rock Production 2025 Project, Contract, March 2025 6
00235.04 Permits - Copies of the Plans, permit, and the material source narrative for the material source are available for inspection at the Project Manager's office. Operations within the material source shall conform to the stipulations and conditions of these documents and to all of the requirements of the Contract.
Subsection Source Name Documents 00235.01(a) Clover Creek
Quarry Department of Geology and Mineral Industries (DOGAMI) Permit County Land Use Permit
00235.05 Pre-Work Meeting - Before occupying the material source, attend a pre-work meeting at the material source with the Engineer and the following owners or representatives:
Subsection Source
Name Contact Names and phone numbers
00235.01(a
Clover Creek Quarry
ODOT Geologist: Scott Billings, (541) 410-6693
00235.06 Source Occupancy - Coordinate material source occupancy with the Engineer.
The material source information listed in Table 00235-1 below shall be as shown. Do not operate beyond the material source Work area boundary as shown unless otherwise directed in writing.
Table 00235-1
Subsection Source Name Source items shown 00235.01(a) Clover Creek
Quarry Work area boundary Excavation area Safety berm Access roads Overburden storage area Scalpings stockpile Reject fines stockpile Oversize stockpiles Equipment and Processing areas
00235.07 Source Development - If proposing changes to the material source development plan, submit a source development plan as an unstamped Working Drawing according to
00150.35. Do not begin Work in the material source until the source development plan has been approved in writing by the Engineer.
Develop a site-specific Erosion and Sediment Control Plan for the material source according to 00280.04 and submit it to the Engineer at or before the pre-work meeting. Construct stormwater control berm(s) as needed to control runoff. Do not allow any materials, including sediments, Aggregate or crushing by-products to enter into waterways or Wetlands.
SPS_M24093, District 13 Rock Production 2025 Project, Contract, March 2025 7
Develop a site-specific Pollution Control Plan for the material source according to 00290.30(b), and submit it to the Engineer at or before the pre-work meeting. Include the following requirements in the Pollution Control Plan:
• Do not discharge waste or by-product if it contains any substance in concentrations that could contaminate Soils or result in harm to fish, wildlife, or water sources.
• Store all potentially hazardous materials and solid waste in a manner that prevents seepage into the ground or groundwater sources. Lined sumps or pits are allowable options for storage. If pits or sumps are used, construct adequate berms or provide other measures to prevent breaching of the pits or sumps.
• For materials capable of causing water pollution if discharged, locate storage facilities in an area that prevents spillage into waterways or Wetlands.
Construction
00235.40 General - All vehicles and Equipment, prior to entering the site for the first time, and each subsequent time if the vehicle has left the Roadway outside the construction Project limits, shall be steam cleaned of all debris (soil, dirt, plant parts, and vegetative matter) before being brought back to the site. Notify the Engineer before moving each vehicle onto the site.
Certify, in writing, that the Equipment has been steam cleaned.
00235.41 Restrictions and Protection of Resources - Comply with the following for all operations within the material source:
• Protect cultural resources according to 00290.50.
• Protect migratory birds according to 00290.36(a).
• Clear trees between September 1 and March 1. If operations are outside this time frame, notify the Engineer 14 calendar days prior to source occupancy. The Engineer will arrange to have an ODOT biologist conduct a required nesting bird survey throughout the site and relocate the nests if they are present.
• Do not utilize, contaminate, or disperse material from existing stockpiles. If existing stockpiles interfere with the Contractor’s operations, move the stockpiles to other locations within the material source area as directed, at no additional cost to the Agency.
00235.42 Source Setup - Before proceeding with Work in the material source, the following apply:
(a) Access:
• Develop and maintain an access road from the developed equipment and processing area to top of the proposed excavation and overburden storage area as applicable. Construct this road with a width of 12 feet and reasonably uniform grade, no steeper than a 16 percent grade (1V:6H), for access to the quarry floor. An approximate location for development of this road is shown on the Plans. Determine the exact location in the field. Obtain the Engineer's approval before constructing the access road.
SPS_M24093, District 13 Rock Production 2025 Project, Contract, March 2025 8
• Routine road maintenance activities such as grading and watering of the main access road do not need review or approval. Maintain or develop drain dips, water bars, road crowning, in-slopes and out-slopes during road maintenance.
• Use overburden or existing, loose and non-stockpiled material or imported or clean soil or a combination of clean soil and rock, to construct a safety berm along the top edge of the new excavation or existing slopes as shown. Maintain a 10-foot buffer between the top edge of the excavation or slope and the toe of the safety berm.
Construct the berm 3 feet high, with side slopes of 1V:2H.
(b) Clearing and Grubbing - Before stripping of overburden clear and grub all trees within the excavation area, to be developed for equipment and processing and the area to be developed as access roads.
(c) Overburden - Before excavating, including drilling and blasting when required, strip and stockpile all soil overburden from within the excavation area, from the area to be developed for equipment and processing, and from areas to be developed as access road(s). Incorporate grass and small shrubs into the stockpiles. Do not remove grass or small shrubs from the overburden. Place stockpiles in the overburden storage area.
Maintain a minimum 10-foot buffer strip between the toe of the overburden storage area and the excavation area. Store overburden stripped from the equipment and processing area as shown, a minimum of 10 feet from the toe of the Aggregate stockpiles. Smooth and contour overburden storage berms to form side Slopes no steeper than 1V:2H.
00235.43 Blasting - Perform blasting operations according to this Section and Section 00335, except that perimeter controlled blasting as described in 00335.40(a) is not required in the material source.
Restrict blasting to the hours of half-hour after sunrise to half-hour before sunset, Monday through Friday. Do not blast on Saturdays, Sundays, or legal holidays as defined in ORS 279C.540.
00235.44 Source Operations - The following apply during material source operations:
• Construct slopes and floor of the excavation area as shown.
• To control dust, apply water to material source access, internal haul road(s), and crushing and processing operations.
• Stockpile scalpings and reject fines in separate and accessible stockpiles as shown.
• If the Contractor chooses to utilize this material source, maintain the condition of
Oregon Trail Road at all times. Provide traffic control related to ingress and egress movements in a manner that allows a safe work zone and safe passage of vehicles.
• Maintain the cattle guard and livestock gate into the source at all times.
00235.45 Source Clean-up - The following apply at the completion of operations:
• Leave no loose material on the site exceeding 1 foot diameter, except as noted below.
Process all material loosened in the source by the Contractor that meets quality requirements, with the following exception(s):
SPS_M24093, District 13 Rock Production 2025 Project, Contract, March 2025 9
• No additional oversize material with a maximum dimension of 2.5 feet may be stockpiled in the material source. Consolidate existing oversize material as shown.
• Place all excess produced Aggregate remaining at the end of operations in separate and accessible stockpiles on Agency owned or controlled property in areas designated by the Engineer, at no additional cost to the Agency.
• Leave the material source internal haul roads and bench access road open. Do not rip or block the roads except a few boulders greater than approximately three feet in diameter may be used to block off access to the upper bench areas.
• Remove all loose, hanging or potentially dangerous Rock on or above the excavated surface.
• Final maintenance on the main access road, such as regrading and/or spot surfacing, to restore to pre-operation condition, is required.
• Pile and burn all construction slash and combustible debris resulting from use and development of the source, including the preexisting refuse identified at the pre-work meeting, even if it is from outside the material source Work area boundary except for grass and small shrubs that are incorporated into the overburden. Comply with all open burning regulations in effect at the time of source occupancy. If burning is not allowed, all construction slash and combustible debris become the property of the Contractor, to be treated as noncombustible and removed from the material source.
00235.46 Seeding:
• In addition to other areas with soil cover within the site disturbed by the Contractor's operations, stabilize the overburden storage area, safety berms, and scalpings stockpile by seeding, mulching, and tackifying, as directed.
• Provide the following seed mixture:
BROADCAST RATE COMMON NAME SCIENTIFIC NAME
1.5 PLS lb/ac indian ricegrass Achnatherum hymenoides
2.0 PLS lb/ac squirreltail Elymus elymoides
1.4 PLS lb/ac slender wheatgrass Elymus trachycaulus ssp. trachycaulus
1.7 PLS lb/ac Idaho fescue Festuca idahoenis
1.7 PLS lb/ac basin wildrye Leymus cinereus
1.1 PLS lb/ac Sandberg bluegrass Poa secunda
5.1 PLS lb/ac bluebunch wheatgrass Pseudoroegneria spicata ssp. spicata
• Use only certified weed free seed. Provide copies of the certification to the Engineer.
Inoculate the clover and alfalfa prior to incorporation into the seed mixture.
• Provide straw mulch according to 01030.15(b).
• Apply a commercial straw mulch tackifier according to the manufacturer’s directions and at the recommended rate.
• Apply seed and mulch according to Section 01030.
• If conditions allow and the Contractor chooses, the area may be stabilized by applying seed using a range drill with a roller attachment. All areas seeded with the range drill and roller do not need to be subsequently covered with mulch and tackifier.
• All variations to these requirements require written approval by the Engineer.
SPS_M24093, District 13 Rock Production 2025 Project, Contract, March 2025 10
00235.47 Source Vacating - Before vacating the material source the following apply:
• Remove all structures, noncombustible debris, and equipment from the material source, even if it was pre-existing, except for grass and small shrubs incorporated into the overburden.
• Remove solid waste and hazardous material from the site and dispose of properly.
These include, but are not limited to, fuel spills, machinery leaks, plant cleanings, materials placed in sumps, tires, pipes, belts, screens and truck cleanings. Provide documentary evidence of proper disposal and verify the amount of material removed.
• If a spill or dumping has occurred or if a spill or dumping is suspected to have occurred, the Contractor shall clean up the contaminated materials according to Section 00290.
After clean up, the Engineer may, sample and test materials at the spill or dumping locations to verify the clean up has been completed. If the Engineer’s verification testing demonstrates remaining contamination, the Contractor shall perform additional clean up until the requirements of Section 00290 including 00290.20(g) are met
• Attend a post-work meeting at the material source to evaluate material source rehabilitation work with the Engineer and attendees listed under 00235.05.
Measurement
00235.80 Measurement - No measurement of quantities will be made for Work performed under this Section.
Payment
00235.90 Payment - No separate or additional payment will be made for Work performed under this Section. Payment will be included in payment made for the appropriate items under which this Work is required.
SECTION 00290 - ENVIRONMENTAL PROTECTION
Comply with Section 00290 of the Standard Specifications.
SPS_M24093, District 13 Rock Production 2025 Project, Contract, March 2025 11
SECTION 00335 - BLASTING METHODS AND PROTECTION OF EXCAVATION
BACKSLOPES
Comply with Section 00335 of the Standard Specifications.
SPS_M24093, District 13 Rock Production 2025 Project, Contract, March 2025 12
SECTION 00680 - STOCKPILED AGGREGATES
Comply with Section 00680 of the Standard Specifications modified as follows:
Add the following subsections:
00680.11(c) Sanding Aggregates - Provide sanding Aggregates meeting the following requirements:
(1) Grading - Furnish clean, hard, and durable Aggregate in stockpiles meeting the following grading requirements:
Percent Passing Sieve Size (by Weight)
1/2" 100 3/8" 85 - 100 No. 8 0 - 10 No. 40 0 - 2
Perform sieve analysis according to AASHTO T 27.
Scalp the Rock or Gravel material from which the Aggregates are produced on a screen, the entire surface of which has openings not less than 1/2 inch in size. After the material has passed over the scalping screen, it shall contain not more than 5% by weight of material passing the 1/2 inch sieve. If quarry Rock is furnished, apply this requirement to the material after it has passed through the primary crusher. In addition 95% of the quarry Rock shall pass a 8 inch sieve following primary crushing.
(2) Elongated Pieces - Elongated pieces in Aggregate larger than 1/4 inch shall be determined according to ODOT TM 229, with the proportional caliper device set at a ratio of 5:1, and shall not exceed 10 percent by weight of the material retained on the1/4 inch sieve.
(3) Fractured Faces - Provide Aggregates consisting of broken stone, crushed gravel, or a combination of both. Crush Aggregate such that at least 90% by weight of the total aggregate retained on the No. 8 and larger sieves is fractured on two faces, as determined according to AASHTO T 335.
00680.11(d) Graded Medium Chip Aggregate – Provide graded medium chip aggregate according to 00710.10.
00680.40(a) Source Sites - Replace this subsection, except for the subsection number and title, with the following:
Prepare and develop the source site according to Section 00235.
SPS_M24093, District 13 Rock Production 2025 Project, Contract, March 2025 13
00680.42 Places of Delivery - Add the following to the end of this subsection:
Deliver and stockpile total Aggregate quantities at either or both of the following locations:
Stockpile Site Location Quantity and Material to be Stockpiled North Powder Stockpile Site
I-84, MP 285.80
Up to a combined total of 15,000 cubic yards Graded Medium Chip Rock
North Powder Stockpile Site
I-84, MP 285.80
Up to a combined total of 5,000 cubic yards Sanding Rock
Baker Maintenance Station
OR 86, MP 2.62
Up to a combined total of 15,000 cubic yards Graded Medium Chip Rock
Baker Maintenance Station
OR 86, MP 2.62
Up to a combined total of 5,000 cubic yards Sanding Rock
00680.70 Cleaning Up Source Sites - Replace this subsection, except for the subsection number and title, with the following:
Clean up the source sites according to Section 00235.
***END SPECIAL PROVISIONS***