This Statement of Work (SOW) details an asphalt paving project for Fermilab's Batavia Road, spanning from Sauk Blvd. to the eastern site boundary. The project requires a subcontractor to perform a comprehensive road overlay, including grinding approximately 9,062 square yards of existing surface asphalt to a depth of 1.9 inches, applying a prime coat, and installing a new 1.9-inch asphalt surface course. Additional scope includes traffic control, thermoplastic pavement markings (including center lines, shoulder lines, and stop bars), and installing warning markers for railroad tracks.
The project is scheduled for the 2025 paving season, with a specific performance period from September 25 to November 28, 2025. The subcontractor must coordinate with the Fermi Forward Discovery Group (FFDG) Construction Coordinator, provide daily weight tickets for asphalt loads, and adhere to strict site access and safety requirements. This includes using Real ID for site access, maintaining clean work areas, providing appropriate personal protective equipment, and ensuring all equipment is well-maintained and used safely. Quality assurance responsibilities include managing work documentation, ensuring quality control services, and maintaining high standards of workmanship.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
F e r m i F o r w a r d D i s c o v e r y G r o u p | K i r k R o a d a n d P i n e S t r e e t | B a t a v i a , I L 6 0 5 1 0
Batavia Road Asphalt Overlay
FESS Point of Contact (POC): William Alvarez Procurement Administrator: TBD Period of Performance: September 25, 2025- November 28, 2025 Place of Performance: Fermilab Site
Statement of Work Infrastructure Services Division
Fermilab Asphalt Paving
March 1, 2025
Table of Contents
Overview………………………………………………………………………………………………………………………..3
Scope of Work
Deliverables
Schedule
Special Instructions
Quality Assurance Requirements
A. Overview
Superior paving services are required to asphalt overlay Batavia Rd, from Sauk Blvd. to the eastern boundary of site, to provide safe travel for our many employees, visitors, and guests.
Definitions:
Customer: Fermi Forward Discovery Group (FFDG) Subcontractor: The company responding to this inquiry and providing asphalt paving Second Tier Subcontractor: Services directly contracted by the Subcontractor Site Location: Fermilab Site
B. Scope of Work
Furnish all labor, materials, and equipment necessary to asphalt overlay Batavia Road, including striping and related work, from Sauk Blvd. to the east property line. Reference provided map.
1. Asphalt Overlays
a. Grind or plane approximately 9,062 square yards of existing surface coat asphalt at a depth of approximately 1.9” and haul from Fermilab site for recycling.
a. Use of a skid-steer front-mounted grinder for butt joints and small grind work.
b. A large commercial road grinder with minimum 7ft grind width shall be used.
c. A fleet of trucks will be required to haul material for recycling.
b. Sweeping of pavement areas to be over-layed before priming. A self-propelled, commercial unit shall be used.
c. Furnish and apply approximately 5,830 lbs. of prime (tack) coat.
d. Manhole and Valve Box Leveling Adjustments (if needed)
a. Perform leveling of manholes and valve boxes where necessary, using leveling risers, to provide a smooth transition with any new asphalt overlays or patching.
e. Furnish and apply surface course leveling mix, as needed.
f. Apply approximately 9,062 square yards of 1.9-inch asphalt surface course with self-propelled paver (minimum 10ft. screed) for road and large parking lot jobs and compact with roller equipped with vibrapac.
2. Related Work
a. Furnish and install temporary traffic control devices, at no additional cost.
b. Furnish and install Thermoplastic Four (4) inch wide pavement markings when pavement is clean and dry with temperatures rising above 50 degrees.
i. Approximately 1,400 linear feet of 4” (each) yellow double center lines.
ii. Approximately 2,333 linear feet of 4” (each) yellow dash lines.
iii. Approximately 6,562 linear feet of 4” white shoulder lines.
c. Furnish and install approximately 70 linear feet of Thermoplastic Eighteen (18) inch wide stop bars when pavement is clean and dry with temperatures rising above 50 degrees.
d. Furnish and install two Thermoplastic “R”s at a height of 72 inches, which will serve as a warning for railroad tracks ahead, when pavement is clean and dry with temperatures rising above 50 degrees.
e. Provide two laborers for traffic control.
f. Perform additional sweeping, as requested, using a self-propelled sweeper.
C. Deliverables
The following standards apply to all deliverables in the contract. See the individual deliverable description for more specific deliverable standard requirements.
1. The Subcontractor shall coordinate scheduled work activities with the FFDG Construction
Coordinator or the FFDG task manager overseeing the work.
2. The Subcontractor shall report any existing abnormal condition(s) they might observe to the
FFDG Construction Coordinator or FFDG Task Manager that, if not corrected, could result in undesirable outcomes.
3. Daily, weight tickets for incoming asphalt loads shall be provided to the FFDG Construction Coordinator or the FFDG Task Manager overseeing the work.
D. Schedule
1. The Subcontractor is expected to complete requested work within that given paving season, unless otherwise coordinated with FFDG Construction Coordinator or the FFDG Task Manager overseeing the work.
E. Special Instructions
Listed below are the special instructions specific to this subcontract.
1. Real ID is required for all Subcontractors and second tier Subcontractors to access the
Fermilab site.
2. Any second-tier services that are utilized by the Subcontractor must be listed and approved by FFDG.
3. All employees of the Subcontractor, including second tier Subcontractors, shall conform to any rules of conduct, etc., established by FFDG. Failure to do so will be sufficient cause for removal from site.
4. Subcontractor and their second-tier Subcontractors shall keep the work site, storage areas, and public and private areas free from accumulations of waste material or rubbish caused by the services activities. Daily clean-up to the satisfaction of the FFDG Representative is expected.
5. Subcontractor shall provide all applicable personnel protection equipment for their work force. This is to include steel-toed boots, hard hat, high visibility reflective vest/clothing, protective eye-gear, face shields/goggles, gloves, respiratory protection and hearing protection and as required by appropriate site safety standards.
6. The Subcontractor's vehicles used on site must have the Subcontractor's business name displayed prominently for identification purposes. Second tier Subcontractors are exempt from this requirement, as many of the drivers are independent owner/operators.
7. The Subcontractor shall have the responsibility to provide all supplies and equipment normally required for asphalt related work. All equipment shall be maintained, kept in good repair, and in safe working condition. Equipment shall only be used in a safe manner, consistent with industry standards and in compliance with FFDG safety requirements.
F. Quality Assurance Requirements
In conjunction with the General Terms and Conditions Quality Requirements, unless otherwise specified by the work order or the FermiForward Task Manager, the Subcontractor’s on-site supervision will be responsible for the following.
1. All activities necessary to manage, control and document work to ensure compliance with the Subcontract requirements.
2. Ensuring adequate Quality Control services are provided for work accomplished on and off site by his/her organization, suppliers, sub-tier Subcontractors, technical laboratories, and consultants.
3. The work activities include safety, testing and inspection and all other functions relating to the requirements for quality work.
4. The quality and timely provision of workmanship and material provided under this subcontract.
| A. Overview |
| B. Scope of Work |
| C. Deliverables |
| D. Schedule |
| E. Special Instructions |
| F. Quality Assurance Requirements |
File details come from the government source that posted it. Updated .