EXHIBIT A - Calculation of Self-Performed Work.docx

DOCX document 39 KB Posted

Attached to
Z2DA--693-23-3-594-0109 | 693-19-106 | Renovate 9th Floor Mental Health | NCO 4 Construction East (VA-23-00072585)
Solicitation number
36C24424R0007
Issued by

About this file

This document is an Exhibit A - Calculation of Self-Performed Work that is required to be submitted in response to RFP 36C24424R0007 for the renovation of the 9th Floor Mental Health Unit for the Department of Veterans Affairs, Veterans Health Administration, Veterans Integrated Service Network 4.

The exhibit outlines the instructions for calculating the percentage of work to be self-performed by the prime contractor. Offerors must demonstrate that they have the capability to self-perform at least 15% of the total contract value using their own resources, including labor, materials, equipment, and job overhead costs. The document provides a format for the offeror to show the calculation, where the total offer price, specialty trade work, and other markups are subtracted to determine the "Total amount of work to be performed under the Contract". The offeror must then identify the "Work to be self-performed" and show that it equals at least 15% of the total contract value. Additional consideration may be given to offerors who can self-perform a major element of the construction work.

View the file

Other files

File Type Posted
36C24424R0007 0006.pdf PDF
Amend 6 - Updated Pricing Sheet.pdf PDF
RFI Responses 3.pdf PDF
36C24424R0007 0005.pdf PDF
Amend 4 - 1. RFI Responses 2.pdf PDF
Amend 4 - 2. Pricing Sheet.pdf PDF
36C24424R0007 0004.pdf PDF
12 ICRA.pdf PDF
5 ALUMINUM CANOPY SYSTEM.pdf PDF
36C24424R0007 0003.pdf PDF
3 SOLID SURFACING FABRICATIONS.pdf PDF
1 000110 Table of Contents.pdf PDF
9 17-H4 ICRA.pdf PDF
8 A3 ICRA.pdf PDF
2 Addendum 1 Drawings.pdf PDF
10 01-A ICRA.pdf PDF
6 Noise and Vibration Control.pdf PDF
11 G-009 ICRA.pdf PDF
13 ICRA.pdf PDF
4 Door Hardware.pdf PDF
7 RFI RESPONSES.pdf PDF
01-20-083-pGen100.pdf PDF
221100 FacWaterDistr MH.pdf PDF
36C24424R0007 0002.pdf PDF
Drawings General.pdf PDF
Wilkes Barre PA Campus Site Plan crane locations.pdf PDF
17-E43 Revisions 2024-05-30.pdf PDF
17-A15 Revisions 2024-05-30.pdf PDF
220523 GenDut ValvesPlumbPiping MH 9th.pdf PDF
36C24424R0007 0001.pdf PDF
Drawings 1.2 33-60.pdf PDF
P03 Brand Name JA 9F MHU 20241804.pdf PDF
S02 SafetyHealthDuringConstruction 18S-15-346.pdf PDF
Cut Sheets.pdf PDF
P07 4.5.24 Wage Determination.pdf PDF
Drawings 1.1 1-32.pdf PDF
Specs.pdf PDF
EXHIBIT B - Subcontractor Info Consent.docx DOCX document
EXHIBIT C - Performance Relevancy Info.docx DOCX document
ICRA.docx DOCX document
Structural Calcs.pdf PDF
Drawings 2.pdf PDF
Safety.pdf PDF
Drawings 1.3.pdf PDF
Estimate - 693 19 106 M P Calcs.pdf PDF
36C24424R0007.docx DOCX document
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT A - CALCULATION OF SELF-PERFORMED WORK

SUBMIT IN RESPONSE TO RFP 36C24424R0007

Use a format similar to the following to identify and calculate cost of the work to be self-performed. Refer to the definitions pertaining to “Self-performance of work”, “On the Site” and “Total amount of work to be performed under the contract”.

Explain in detail how you will perform the minimum percentage required (15% GC) with your own resources. Note: An offeror who has the capability to perform both as a General contractor and self-perform a major element of construction, for example, pre-fabricated concrete, may be afforded additional consideration in the evaluation. You should address your general self-performance capability.

(Includes mobilization and utilization of owned or rented plant and equipment to be operated by the prime contractor’s own employees; only those materials which will be both purchased and installed by the prime’s own forces; labor associated with those aforementioned materials or equipment; only those supplies to directly support work performed by the contractor’s own employees; and the contractor’s own job overhead costs.)

Clearly describe the work to be self-performed:

Show Calculation of Self-Performed work:

B.1 Total Offer Price: $

B.2 If applying for consideration as a General Contractor subtract Specialty Trades (Unless being self performed)

B.3 Subtract G&A, home office overhead, prime contractor’s markups for profit, bond, state use tax, etc. ($)

B.4 Remainder is “Total amount of work to be performed under the Contract” = $

B.5 “Work to be self-performed”: = $ Amount shown on this line should match the amount shown for “Show Calculation of Self-Performed work”.

(Includes mobilization and utilization of owned or rented plant and equipment to be operated by the prime contractor’s own employees; only those materials which will be both purchased and installed by the prime’s own forces; labor associated with those aforementioned materials or equipment; only those supplies to directly support work performed by the contractor’s own employees; and the contractor’s own job overhead costs.)

B.6 15 % Self-performed Work = Line B.5 / B.4 X 100% = %

File details come from the government source that posted it. Updated .