About this file

This document is a Table of Contents for a federal construction solicitation related to the renovation of the 9th floor mental health unit. The solicitation, identified as Solicitation Number 36C24424R0007, is being issued by the Department of Veterans Affairs Veterans Integrated Service Network 4 for the Renovate 9th Floor Mental Health Unit project.

The Table of Contents outlines the various divisions and sections included in the construction documents, covering topics such as general requirements, demolition, concrete, masonry, metals, wood/plastics/composites, thermal and moisture protection, openings, finishes, specialties, equipment, furnishings, fire suppression, plumbing, HVAC, electrical, communications, and electronic safety and security. Key sections include the Statement of Work, shop drawings and submittals, safety requirements, quality control, and commissioning requirements. No specific pricing terms, set asides, or incumbent information is provided in this document.

View the file

Other files

File Type Posted
36C24424R0007 0006.pdf PDF
Amend 6 - Updated Pricing Sheet.pdf PDF
RFI Responses 3.pdf PDF
36C24424R0007 0005.pdf PDF
Amend 4 - 1. RFI Responses 2.pdf PDF
Amend 4 - 2. Pricing Sheet.pdf PDF
36C24424R0007 0004.pdf PDF
12 ICRA.pdf PDF
5 ALUMINUM CANOPY SYSTEM.pdf PDF
36C24424R0007 0003.pdf PDF
3 SOLID SURFACING FABRICATIONS.pdf PDF
9 17-H4 ICRA.pdf PDF
8 A3 ICRA.pdf PDF
2 Addendum 1 Drawings.pdf PDF
10 01-A ICRA.pdf PDF
6 Noise and Vibration Control.pdf PDF
11 G-009 ICRA.pdf PDF
13 ICRA.pdf PDF
4 Door Hardware.pdf PDF
7 RFI RESPONSES.pdf PDF
01-20-083-pGen100.pdf PDF
221100 FacWaterDistr MH.pdf PDF
36C24424R0007 0002.pdf PDF
Drawings General.pdf PDF
Wilkes Barre PA Campus Site Plan crane locations.pdf PDF
17-E43 Revisions 2024-05-30.pdf PDF
17-A15 Revisions 2024-05-30.pdf PDF
220523 GenDut ValvesPlumbPiping MH 9th.pdf PDF
36C24424R0007 0001.pdf PDF
Drawings 1.2 33-60.pdf PDF
P03 Brand Name JA 9F MHU 20241804.pdf PDF
S02 SafetyHealthDuringConstruction 18S-15-346.pdf PDF
Cut Sheets.pdf PDF
P07 4.5.24 Wage Determination.pdf PDF
Drawings 1.1 1-32.pdf PDF
Specs.pdf PDF
EXHIBIT B - Subcontractor Info Consent.docx DOCX document
EXHIBIT C - Performance Relevancy Info.docx DOCX document
ICRA.docx DOCX document
EXHIBIT A - Calculation of Self-Performed Work.docx DOCX document
Structural Calcs.pdf PDF
Drawings 2.pdf PDF
Safety.pdf PDF
Drawings 1.3.pdf PDF
Estimate - 693 19 106 M P Calcs.pdf PDF
36C24424R0007.docx DOCX document
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01-01-20

00 01 10 - 1

TABLE OF CONTENTS

Section 00 01 10

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 15 List of Drawing Sheets 07-15

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 12-18

01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 02-15

01 33 23 Shop Drawings, Product Data, and Samples 05-17

01 35 26 Safety Requirements 02-17

01 42 19 Reference Standards 09-19

01 45 00 Quality Control 03-19

01 57 19 Temporary Environmental Controls 01-11

01 74 19 Construction Waste Management 09-13

01 81 13 Sustainable Construction Requirements 10-17

01 91 00 General Commissioning Requirements 10-15

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17

02 82 11 Traditional Asbestos Abatement 04-19

02 82 13.31 Asbestos Transite Abatement 09-15

DIVISION 03 – CONCRETE

03 30 53 (Short-Form) Cast-in-Place Concrete 02-16

DIVISION 04 – MASONRY

04 20 00 Unit Masonry 08-17

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 11-18

05 31 00 Steel Decking 02-16

05 40 00 Cold-Formed Metal Framing 05-16

05 50 00 Metal Fabrications 08-18

05 51 00 Metal Stairs 10-15

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 10-17

06 61 16 Solid Surface Fabrications CUSTOM

ZMiller Cloud

Snapshot

00 01 10 - 2

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 13 Thermal Insulation 10-17

07 22 00 Roof and Deck Insulation 02-16

07 27 27 Fluid-Applied Membrane Air Barrier, Vapor Retarding 02-16

07 40 00 Roofing and Siding Panels 10-15

07 54 23 Thermoplastic Polyolefin (TPO) Roofing 08-16

07 60 00 Flashing and Sheet Metal 07-14

07 71 00 Roof Specialties 10-15

07 72 00 Roof Accessories 10-15

07 76 11 Pedestal Artificial Turf Tray System 12-21

07 81 00 Applied Fireproofing 10-17

07 84 00 Firestopping 02-16

07 92 00 Joint Sealants 10-17

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 08-16

08 14 00 Interior Wood Doors 02-16

08 31 13 Access Doors and Frames 02-16

08 33 13 Coiling Counter Doors 02-16

08 41 13 Aluminum-Framed Entrances and Storefronts 08-16

08 44 13 Glazed Aluminum Curtain Walls 03-17

08 51 13 Aluminum Windows 02-16

08 71 00 Door Hardware 01-20

08 71 13 Automatic Door Operators 02-16

08 80 00 Glazing 10-15

08 90 00 Louvers and Vents 05-15

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 02-15

09 22 16 Non-Structural Metal Framing 06-18

09 29 00 Gypsum Board 06-18

09 30 13 Ceramic/Porcelain Tiling 09-15

09 51 00 Acoustical Ceilings 12-18

09 65 13 Resilient Base and Accessories 02-16

09 65 16 Resilient Sheet Flooring 05-18

09 65 19 Resilient Tile Flooring 05-18

09 67 23.60 Resinous (Urethane and Epoxy Mortar) Flooring (RES-6) 07-14

09 68 00 Carpeting 10-15

09 78 23 Phenolic Interior Wall Paneling 01-21

09 91 00 Painting 01-16

09 96 59 High-Build Glazed Coatings 07-14

DIVISION 10 – SPECIALTIES

10 22 39 Folding Panel Partitions 01-21

00 01 10 - 3

10 26 00 Wall and Door Protection 10-15

10 28 00 Toilet, Bath, and Laundry Accessories 02-16

10 44 13 Fire Extinguisher Cabinets 08-18

10 73 16 Aluminum Canopy System CUSTOM

DIVISION 11 – EQUIPMENT

11 41 00 Food Storage Equipment 11-11

DIVISION 12 – FURNISHINGS

12 32 00 Manufactured Wood Casework 09-15

12 36 00 Countertops 12-18

DIVISION 13 - SPECIAL CONSTRUCTION

13 05 41 Seismic Restraint Requirements for Non-Structural

Components

01-14

DIVISION 14 – CONVEYING EQUIPEMENT (NOT USED)

DIVISION 21 - FIRE SUPPRESSION

21 13 13 Wet-Pipe Sprinkler Systems 06-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 07-16

22 05 12 General Motor Requirements for Plumbing Equipment 09-15

22 05 19 Meters and Gages for Plumbing Piping 09-15

22 05 23 General-Duty Valves for Plumbing Piping 09-15

22 05 33 Heat Tracing for Plumbing Piping 09-15

22 07 11 Plumbing Insulation 09-19

22 08 00 Commissioning of Plumbing Systems 11-16

22 11 00 Facility Water Distribution 11-19

22 11 23 Domestic Water Pumps 09-15

22 13 00 Facility Sanitary and Vent Piping 09-15

22 14 00 Facility Storm Drainage 09-15

22 33 00 Electric Domestic Water Heaters 09-15

22 40 00 Plumbing Fixtures 09-15

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 08-17

23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment

08-17

ZMiller Cloud

Snapshot

00 01 10 - 4

23 05 41 Noise and Vibration Control for HVAC Piping and

Equipment

02-15

23 05 93 Testing, Adjusting, and Balancing for HVAC 02-15

23 07 11 HVAC Insulation 02-15

23 08 00 Commissioning of HVAC Systems 11-16

23 09 23 Direct-Digital Control System for HVAC 09-11

23 21 13 Hydronic Piping 08-17

23 22 13 Steam and Condensate Heating Piping 08-17

23 23 00 Refrigerant Piping 02-15

23 31 00 HVAC Ducts and Casings 03-13

23 34 00 HVAC Fans 02-15

23 36 00 Air Terminal Units 02-15

23 37 00 Air Outlets and Inlets 02-15

23 40 00 HVAC Air Cleaning Devices 02-12

23 73 00 Indoor Central-Station Air-Handling Units 04-11

23 74 13 Packaged, Outdoor, Central-Station Air-Handling Units 04-11

23 81 00 Decentralized Unitary HVAC Equipment 02-11

23 82 00 Convection Heating and Cooling Units 04-11

23 82 16 Air Coils 04-11

DIVISION 25 – INTEGRATED AUTOMATION (NOT USED)

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16

26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17

26 05 26 Grounding and Bonding for Electrical Systems 01-17

26 05 33 Raceway and Boxes for Electrical Systems 01-18

26 05 73 Overcurrent Protective Device Coordination Study 01-18

26 08 00 Commissioning of Electrical Systems 11-16

26 09 23 Lighting Controls 01-18

26 22 00 Low-Voltage Transformers 01-18

26 24 16 Panelboards 01-18

26 27 26 Wiring Devices 01-18

26 29 11 Motor Controllers 01-18

26 29 21 Enclosed Switches and Circuit Breakers 01-17

26 43 13 Surge Protective Devices 01-17

26 51 00 Interior Lighting 01-18

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 09-19

27 05 26 Grounding and Bonding for Communications Systems 06-15

27 05 33 Raceways and Boxes for Communications Systems 10-18

27 08 00 Commissioning of Communications Systems 11-16

27 10 00 Control, Communication and Signal Wiring 06-15

27 11 00 Communications Equipment Room Fittings 06-15

27 15 00 Communications Structured Cabling 01-16

00 01 10 - 5

27 51 16 Public Address and Mass Notification Systems 10-18

27 51 23 Intercommunications and Program Systems 06-15

27 52 23 Nurse Call and Code Blue Systems 10-18

27 52 41 Miscellaneous Medical Systems 06-15

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and Security 04-18

28 05 13 Conductors and Cables for Electronic Safety and

Security

10-18

28 05 26 Grounding and Bonding for Electronic Safety and

Security

09-11

28 05 28.33 Conduits and Backboxes for Electronic Safety and

Security

09-11

28 08 00 Commissioning of Electronic Safety and Security Systems 11-16

28 13 00 Physical Access Control System 10-11

28 23 00 Video Surveillance 09-11

28 26 00 Electronic Personal Protection System 09-11

28 31 00 Fire Detection and Alarm 10-11

DIVISION 31 – EARTHWORK (NOT USED)

DIVISION 32 – EXTERIOR IMPROVEMENTS (NOT USED)

DIVISION 33 – UTILITIES (NOT USED)

DIVISION 34 – TRANSPORTATION (NOT USED)

DIVISION 48 – ELECTRICAL POWER GENERATION (NOT USED)

File details come from the government source that posted it. Updated .