Exhibit 1 - Seattle FOB ABAAS Upgrades - HUD-DOL TI SOW.docx

DOCX document 324 KB Posted

Attached to
Seattle FOB ABAAS Upgrades and HUD/DOL Space Build-out (Bid-Build)
Solicitation number
EQ10PCPB1-21-0016
Issued by

About this file

This statement of work and related federal contract opportunity document outline requirements for construction services to renovate space and upgrade accessibility standards at the Seattle Federal Office Building. The General Services Administration seeks to reduce office footprints for the Department of Labor and Housing and Urban Development through interior tenant improvements and reconfiguration of approximately 30,534 square feet for HUD and 28,000 square feet for DOL. Additionally, upgrades are required to bring the historic building into compliance with accessibility standards including new restrooms on each floor and a lactation room. The contractor must coordinate work with tenants to minimize disruptions and maintain egress requirements. A critical deadline for substantial completion of the DOL space is August 15, 2023 to allow relocation prior to an existing lease expiration. The solicitation number is EQ10PCPB1-21-0016 with an anticipated award date of November 16, 2021.

View the file

Other files

File Type Posted
Amd 03 - Q and A.docx DOCX document
Amd 03 - SF30 8.25.21.pdf PDF
Amd 02 - Q and A.docx DOCX document
Amd 02 - SF30 8.20.21.pdf PDF
Amd 01 - Exhibit 2.1 - Price and Services Schedule (Partially Occupied Facility) 8.4.21.docx DOCX document
Amd 01 - Seattle FOB ABAAS Upgrade - HUD-DOL TI Site Visit Attendance Sheet.docx DOCX document
Amd 01 - Q and A.docx DOCX document
Amd 01 - Exhibit 2.2 - DOL Agency USF and Cost Share Matrix.xlsx XLSX spreadsheet
Amd 01 - SF30 8.4.21.pdf PDF
Amd 01 - 1. Seattle FOB ABAAS Upgrade & HUD-DOL TI - Solicitation 8.4.2021.docx DOCX document
Amd 01 - Exhibit 2 - Price and Services Schedule (Fully Occupied Facility) 8.4.21.docx DOCX document
Exhibit 0 - CUI Document.docx DOCX document
Exhibit 5 - GACA - GSA Affiliated Customer Accounts May 2014 (2).docx DOCX document
1. Seattle FOB ABAAS Upgrade & HUD-DOL TI - Solicitation 7.2.2021 (1).docx DOCX document
Exhibit 10 - DBA Gen Decision WA20210011 (Mod 4).pdf PDF
Exhibit 4 - Model Subcontracting Plan.pdf PDF
Exhibit 9 - Performance Evaluation Survey - Commercial Client.docx DOCX document
Exhibit 2 - Price and Services Schedule 7.2.21.docx DOCX document
Exhibit 3 - SF1442.pdf PDF
Exhibit 6 - Reps and Certs 7.2.21.docx DOCX document
Exhibit 8 - Project Experience.pdf PDF
Exhibit 7 - Key Personnel Resume Format.docx DOCX document
2. Seattle FOB ABAAS Upgrade & HUD-DOL TI - Agreement 7.2.2021 (3).docx DOCX document
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW) FOR CONSTRUCTION CONTRACT

SEATTLE FOB ABAAS UPGRADES AND DOL/HUD TI SPACE BUILD-OUT

US GENERAL SERVICES ADMINISTRATION

PUBLIC BUILDINGS SERVICE

PROJECT IDENTIFICATION

Project Name: SEATTLE FOB ABAAS UPGRADES and DOL/HUD TI SPACE BUILD-OUT

GSA Region: NORTHWEST / ARCTIC (10)

Building Name: SEATTLE FEDERAL OFFICE BUILDING (WA0036ZZ)

Building Address: 909 1st Ave, SEATTLE WA 98104

Seattle Federal Office Building ABAAS Upgrades and DOL/HUD TI Space Build-out FOB, Seattle, WA

SOW v1 25Feb2020

1 PROJECT DESCRIPTION/BACKGROUND

Project Name:ABAAS UPGRADES and DOL/HUD TI SPACE BUILD-OUT
Project Number:EQ10PCPB1-21-0016
Region:NORTHWEST / ARCTIC [Region 10]
Building Name:SEATTLE FEDERAL OFFICE BUILDING [WA0036ZZ]
Building Address:909 1st AVENUE, SEATTLE WA 98104

The United States General Services Administration requires construction services to enable the Housing & Urban Development (HUD) and the Department of Labor (DOL) agencies in Seattle to down-size and meet their OMB footprint utilization rate (UR) targets. This project also requires construction services to bring the Seattle Federal Office Building (FOB) into ABAAS (Architectural Barriers Act Accessibility Standards) compliance, in accordance with GSA policies and directives relative to Capital-Funded Repair and Alteration (R&A) projects.

The Historic Seattle Federal Office Building (FOB) was constructed in 1931 - 1933 and was the first building in Seattle specifically designed for offices of the federal government. This building is listed on the National Register of Historic Places. All work and workers are required to comply with the Secretary of Interior's Guidelines for the Treatment of Historic Properties. The Contractor is required to coordinate all construction activities with the GSA Historic Preservation Office.

The FOB is a striking example of Moderne Art Deco architectural style, with a distinct stepped massing and facades. Art Deco qualities of the design are enhanced by the cascading effect provided by light-colored terra cotta decoration applied as vertical fluting to the parapets atop the red brick-faced facades. The FOB has nine (9) floors as well as a partial basement level. It is a frame of concrete encased steel beams and columns and is supported on wood piles with concrete pile caps. The roof is multi-tiered, cascading down symmetrically from the 9-story central tower fronting 1st Ave to the two 5-story wings extending west along Madison St. and Marion St. Exterior walls are faced with masonry. Interior walls are constructed of hollow-clay and hollow terra cotta tile faced with plaster.

The exterior is currently under renovation; specific areas of work are the exterior brick, granite, terra cotta and aluminum panel restoration; roof replacement; and window restoration. Expected completion of the exterior renovation is March 2022.

The FOB is a multi-tenant facility, housing Offices, Departments, Agencies and activities/functions.

HUD is currently located in the (FOB) occupying 67,360 USF on the lower level, 1st, 2nd, 3rd, 4th, and 6th floors. The goal is for HUD to consolidate and occupy the entire 3rd floor, and part of the 4th floor, and therefore reduce HUD’s space to ~30,534 USF. HUD will reduce space by 45% with future rent costs savings. HUD’s design goals included: Maximize the amount of natural lighting throughout the office space; maximize workspace and conference room space on each floor and wing for employees to collaborate and conduct work related mission needs; and place employee workstations close to windows, with the understanding that heating and airflow requires sufficient clearance for maintenance.

DOL is currently located in the Seattle 5th and Yesler Building (leased space) occupying 74,832 USF. This project proposes to reduce DOL space to ~28,000 USF relocating the agency to the FOB Building, to occupy part of the lower level, part of the 1st floor, and all of the 2nd floor. DOL’s design goals included: Establish and apply space standards for individual workspace to create uniform workspace across all agencies; adopt the “One DOL Concept” to maximize the use of shared spaces both within the agencies and across the department; pursue federal space for long term housing solution and avoid 10-year churn; and minimize the cost throughout the project execution and maximize financial return to DOL mission and taxpayers. DOL is committed to providing their workforce a healthy, inspiring work environment.

The FOB is not ABAAS compliant. This project also includes bringing the FOB into ABAAS compliance, including the existing ABAAS entrance, and installation of new restrooms on each floor. A lactation room will also be constructed as part of this project.

1.1 PROJECT GOALS AND OBJECTIVES

1.1.1 ABAAS Upgrades and DOL/HUD TI Space Build-out (EQ10PCPB1-21-0016) Project The overall goal is to utilize a highly collaborative Integrated Project Delivery (IPD) approach for this project (ABAAS Upgrades and DOL/HUD TI Space Build-out). Accordingly, the Contractor must work closely with all the stakeholders to deliver a project that: meets the expectations and needs of all stakeholders; avoids any and all disruptions to the tenants’ ongoing operations and well-being; and satisfies GSA’s requirements for a high performing building and tenant spaces.

Care must be exercised when considering construction phasing and any potential project impact(s) to the means of egress and egress pathways from occupied space to the building exits. At no time during the project must there be less than (2) means of egress from any space to building exits. Space access and means of egress & egress pathways must be maintained throughout the project that satisfy ABAAS and GSA Fire, Life, Safety code requirements. This is of critical importance given the expectation that the project occur within a fully occupied and functional Federal Office Building.

Furthermore, in accordance with GSA policy and directives governing Capital-funded projects, the facility, where impacted by a Capital-funded project, must be upgraded to and come into compliance with ABAAS requirements to the maximum extent possible. However, it is GSA’s current expectation that, for this particular overall project, this scope would generally include, but not necessarily be limited to maintaining/upgrading any access/egress accessibility elements for the facility; and upgrading the restrooms throughout the facility, both in order to maintain/increase the facility’s ABAAS accessibility aspects.

The Contractor must work with GSA and the larger Project Delivery Team to ensure that the project:

· Complies with all project requirements, including (but not limited to) GSA PBS P-100 standards (Baseline, unless noted otherwise)

· Substantial Completion Date for the DOL/HUD TI Space Build-out no later than 15-Aug-2023, in order for DOL to vacate their existing space before existing lease expiration

· ABAAS upgrades to the building

· Minimizes impact to tenants and public users

· Maintains an adequate, code compliant number and proper configuration of access and egress pathways throughout the facility, including within tenant spaces, during and after construction

· Maintains/upgrades the facility features impacted by project work to be ABAAS compliant

1.1.1.1 DOL/HUD TI Space Build-out Substantial Completion Critical Deadline Milestone (15-Aug-2023) The DOL/HUD TI Space Build-out project’s Substantial Completion Date (SCD) is established as No-Later-Than (NLT) 15-Aug-2023, in order to permit DOL’s subsequent full occupancy of their newly renovated/constructed space, and to vacate their existing leased location, prior to their existing lease expiration date. This SCD date for DOL’s TI Space Build-out is a critical driving factor for the project’s schedule.

1.1.1.2 Project’s Development Effort, Approval and Funding History The annual Consolidation Fund Program allows Federal agencies to apply no-year funds for shell and tenant improvement (TI) costs on projects that reduce annual rent and improve office utilization rates (UR). GSA began the Consolidation Fund Program in FY14 as a way to assist our customer agencies reduce rental costs while optimizing their footprint to fit their work environments. Since its inception, the program has funded 78 projects and helped the Federal government reduce annual rent by more than $65 million- nearly $1 million per accepted project. Consolidation funds projects are required to achieve rent savings. In addition, preference is given to projects that achieve an office-only utilization rate of 130 USF per person and an estimated payback of less than seven years. Project eligibility is based on cost, consensus, and approval. The DOL is funded by the Consolidation Fund Program.

1.1.1.3 Project’s General Scope

The subject project scope includes the following:

As stated above, HUD is currently located in the (FOB) occupying 67,360 USF on the lower level, 1st, 2nd, 3rd, 4th, and 6th floors. The Contractor must provide a construction effort to build-out the lower level, 1st, and 2ND floor spaces identified for DOL’s use, prior to their existing lease expiration at a nearby leased location. Before DOL’s spaces can be built out, HUD’s space must be built out on the 3rd and 4th floors. HUD intends to keep their existing 2nd floor space fully operational during construction. HUD is currently using their 1st floor space to store their new workstations (approx.. 10,000 sq ft). Regarding HUD’s existing space on the 3rd and 4th floors, HUD will not occupy those areas during construction so the Contractor has full access. The integrated construction phasing of these (2) agencies is critical to the successful completion of this overall project.

· Tenant Furniture, Fixtures, Equipment, etc.

· Contractor must coordinate with both DOL’s and HUD’s furniture vendors, through the GSA Project Team, and execute all work associated with installation of the new workstations. HUD and DOL have different furniture vendors.

· Contractor is responsible for providing power to the workstations; Furniture vendor will connect the whips to the furniture.

· For HUD, the Contractor’s electrical subcontractor will need to be on site at the beginning to install all electrical infeeds to junction boxes. And the Contractor’s data subcontractor will need to be on site during panel install to go behind furniture installers and put wires into panel raceways.

· For DOL, the data receptacles are provided by the data cable/IT group that is installing the data cabling. The furniture installers will install the panel frames, move to another area and let the data cable installers run the cables through the open frames and out the opening for the data receptacle. The furniture installers will then go back in and put in the panel tiles and components. After this is completed the data cable/IT group will come back to install the data receptacle they are providing, test the data connection from the receptacle to the server. This process requires close coordination with the data and furniture installers.

· Contractor is responsible for inspection, testing and commissioning of any relocated, reconnected and/or reinstalled tenant furniture, fixtures, equipment, etc., impacted by the Contractor’s work.

· Contractor is responsible for temporary provisions for any furniture, fixtures, equipment, etc., that might be disconnected and/or relocated as a result of the Contractor’s work.

· Building system(s), component(s), equipment, hardware, etc. impacts

· Contractor must disconnect, relocate and reconnect any system(s), component(s), equipment, hardware, etc. necessary to perform said construction efforts.

· Contractor is responsible for inspection, testing and commissioning of any relocated and reconnected system(s), component(s), equipment, hardware, etc. impacted by the Contractor’s work.

· Contractor is responsible for temporary provisions for any system(s), component(s), equipment, hardware, etc. that might be disconnected and/or relocated as a result of the Contractor’s work. For example, this includes, but is not necessarily limited to, the following:

· If Contractor’s work impacts a fire/life/safety system(s), component, etc. such as the fire alarm control system (e.g. the fire alarm control system, or components thereof, need(s) to be secured/shut-off and/or relocated before, during or after a particular work sequence, construction element, etc.), the Contractor is responsible for providing a fire watch for the duration of the impact.

· If Contractor’s work impacts a building system or component, for example a piece of electrical equipment, the Contractor must provide temporary power and connection for that equipment’s load(s) prior to disconnecting and/or relocating said equipment.

· HUD has their own security vendor who will be doing installation of the wiring and associated hardware; HUD’s security vendor will also program the security equipment. Contractor will be responsible for any rough-in for the security system, i.e., install conduit and cable trays. HUD’s security will supply the J Hooks. Contractor must coordinate the security equipment installation with HUD’s security vendor.

· Historic Preservation Plan - Submit a written plan for each phase or process including protection of surrounding materials during operations. Describe in detail materials, methods, and equipment to be used in each phase of work. Provide sequencing of work, and how the contractor will work with GSA to assure continuity of government operations and services during the work. Describe how the Preservation Construction Manager and other supervisory personnel will minimize the risks of adverse effects on historic materials and project delays resulting from unforeseen conditions or execution challenges.

· Waste Management Plan per the PBS P-100 1.7.2.2

· Site Safety Plan - The Contractor is required to prepare and submit to the COR for approval, an Accident Prevention and Site Safety Plan within “ten” (10) calendar days following award. The Site Safety Plan is a living document and is required to be updated to address emergent, current or national conditions. The Plan is required to define how the contractor will protect the general public, their employees and the environment, to include, but not limited to:

· Responsibilities and Lines of Authority

· Prime Subcontractors and their participation in the Plan

· Accident Prevention Plan

· Construction Quality Control Plan (CQC) - The Contractor is required to prepare a CQC plan like the Army Corps of Engineer's three phase format - preparatory, initial and follow up phases within “ten” (10) calendar days following award. Detail of the plan to be commensurate with the complexity and level of the project. (See Section 5.1)

· Daily Reports - The Contractor is required to submit to the COR a daily report for days when site work is being performed. As a minimum, include the following in the daily report form: (writer discretion) report number, date, weather (if an impact to the project), work performed, numbers of workers, list of subcontractors on site, photos and test performed and results. Also include any three phase inspection performed.

1.2 PROJECT DELIVERY APPROACH

GSA envisions a highly collaborative delivery approach for this project. The expectation is that the Contractor and their team must work in close consultation and collaboration with GSA, GSA’s CMA, all project tenants and stakeholders (internal and external) to deliver a project that meets the expectations and needs of all stakeholders and GSA’s requirements.

1.3 REFERENCE MATERIALS

All efforts, materials and work performed under this contract must comply with and/or must be with knowledge and forethought of applicable Federal, State, and local building codes based on the requirements of the current edition of recognized and accepted building standards, codes and regulations, in compliance with GSA PBS P-100. Any conflicts and/or ambiguities within or among the referenced Standards and Criteria Documents, or any deviations from requirements contained therein, must be reported to the GSA Contracting Officer, in writing, for determination as to applicability.

All contractual references – documents, codes, standards, etc. – must be used to measure compliance of the construction of the building systems and DOL/HUD spaces with respect to contractual expectations.

The following documents are considered instrumental in providing guidance relative to the project’s successful completion:

· HUD’s Seattle Regional Office Space Requirements Package

· DOL’s Workplace Recommendations Final Report (June 2018); and as clarified and expounded upon herein

· GSA PBS P-100 – Facilities Standards for Public Buildings Service (2018)

· GSA PBS P-120 – Public Buildings Service Cost and Schedule Management Policy Requirements (2016)

· Division 01 Specifications

· GSA PBS – Building Commissioning Guide (BCG; 2005)

In addition to the above, GSA will, at the Contractor’s request, provide access to any other available relevant current & historical building information, reports and documentation, including, but not limited to: Asbestos Reinspection Survey Reports; Report of Hazardous Materials Survey; as-built drawings; etc.

2 GENERAL REQUIREMENTS

The requirements set forth in this section apply to all stages and phases of the contract as described in the Scope of Services section below.

2.1 PROJECT MILESTONES SCHEDULE

The anticipated award for the ABAAS Upgrades-DOL/HUD TI Build-out contract is 16-Nov-2021.

2.2 PERFORMANCE OBJECTIVES

2.2.1 Standards and Criteria Documents

2.2.1.1 Applicability

All efforts, materials and work performed under this contract must comply with and/or must be with knowledge and forethought of applicable Federal, State, and local building codes based on the requirements of the current edition of recognized and accepted building standards, codes and regulations, in compliance with GSA PBS P-100. The applicable version of each document must be the version current at the time of contract award. In the event of a conflict between the requirements stated in these documents and requirements provided elsewhere in this SOW and the Contract, the requirements of the SOW and Contract prevail.

Any conflicts or ambiguities within or among the referenced standards and criteria documents, or any deviations from requirements contained in the standards and criteria documents, must be reported to GSA’s Contracting Officer in writing, for determination as to applicability.

2.2.1.2 Document List

a. GSA PBS P-100 – Facilities Standards for Public Buildings Service (2018) (https://www.gsa.gov/real-estate/design-construction/engineering-and-architecture/facilities-standards-p100-overview)

b. GSA PBS P-120 – Public Buildings Service Cost and Schedule Management Policy Requirements (2016) (https://www.gsa.gov/directives-library/p120-public-buildings-service-cost-and-schedule-management-policy-10006-pbs)

c. GSA Pricing Desk Guide, 5TH Edition (PDG; 2019) (http://www.gsa.gov/rentpricingpolicy)

d. GSA PBS – Building Commissioning Guide (BCG; 2005) (https://www.wbdg.org/ffc/gsa/criteria)

e. GSA Accessible Facility Design (https://www.gsa.gov/cdnstatic/National_Accessibility_Program_Standards_Policies_and_Procedures_2.pdf)

f. GSA Region 10 Fire Alarm Design, Installation and Testing Policy (https://www.gsa.gov/cdnstatic/DID_Review_Guide_Final.pdf)

g. GSA Order “PBS Indoor Air Quality (IAQ) Management” (PBS 1000.8) (https://www.gsa.gov/directives-library/indoor-air-quality-management-10008-pbs)

h. GSA Technology Policy for PBS-Owned Building Monitoring and Control Systems (31Mar2011)

i. GSA PBS Key Sustainable Products Initiative (PBS Order 1096.1) (https://www.gsa.gov/directives-library/the-pbs-key-sustainable-products-initiative-10961-pbs)

j. GSA Design Guide for Operational Excellence (May 6, 2019) (https://www.wbdg.org/FFC/GSA/gsa_design_guide_for_operational_excellence_082019.pdf)

k. GSA Policy and Procedure “Document Security for Sensitive But Unclassified Building Information” (PBS P 3490.3)

l. GSA OCIO IT Security 01-05 “Configuration Management Guide” (Rev3 14Jul2015)

m. GSA IT Security Policy 2100.1K “GSA IT Security Policy” (Jun 2017)

n. GSA IT Telecommunications Distribution and Design Guide (TDDG): Telecommunications and Infrastructure Standards (Ver 8 6Aug2016)

o. GSA Smart Buildings Implementation Guide (Ver 1 16Mar2015)

p. GSA Building Technologies Technical Reference Guide (Ver 1.2 29Sep2016)

q. National Environmental Standards for Hazardous Air Pollutants (EPA)

r. Applicable State and Local Safety and Environmental laws and regulations for the Seattle, WA location

2.2.1.3 As-Built Documents

All existing as-built drawings of the facility are provided for informational purposes only. All information contained therein must be verified by the Contractor for accuracy.

2.3 PROJECT MANAGEMENT RESPONSIBILITIES

2.3.1 Communications Plan

The Contractor, in consultation with the stakeholders of the project, must assist GSA in developing and complying with a project communications plan. The Contractor must review and comply with GSA’s communication plan. This plan must be used and maintained throughout the project and modified as necessary to suit each project phase.

The Contractor must direct all questions and requests from tenant agencies and local community interests to GSA’s Project Manager. Prior to contacting any parties other than GSA Regional personnel, the Contractor must confirm all meetings and/or communications with GSA’s Project Manager.

The Contractor must not release any oral, written, or graphic information regarding this project to outside sources without obtaining prior consent from GSA. All such requests for information concerning the project must be referred to GSA’s Contracting Officer for response.

All presentations to non-GSA entities require prior written approval from GSA.

2.3.2 Detailed Project Schedule

GSA’s overall project schedule will be provided after award.

The Contractor must assist GSA in the development and maintenance of the Integrated Master Project (IMP) Schedule. The IMP Schedule must conform to the milestones and durations provided in GSA’s overall project schedule.

After the Contractor receives Notice to Proceed with the Construction Phase work, the Contractor must provide and maintain a detailed schedule for completion of all Construction Phase activities, tasks, and submissions required herein. The Contractor must also provide and maintain the construction schedules as further described elsewhere. After approval by GSA, the Contractor schedules must be incorporated into the IMP Schedule.

Contractor must provide bi-weekly (i.e. every (2) weeks) schedule updates to GSA, showing progress on and completion of all required Construction Phase work. Contractor must immediately notify GSA of any anticipated delay in performance of the work.

While the Contractor is free to use whatever scheduling software they desire, the Contractor must provide GSA with electronic copies of all schedule submittals in Microsoft Project (mpp) native file format for GSA’s internal use.

2.3.3 Project Progress Meetings/Presentations

After Construction begins, the GSA Project Manager will host regularly scheduled stakeholders meetings, and will observe the Contractor’s weekly subcontractor meeting(s). The Contractor must also attend construction oversight meetings with representatives from GSA on a weekly basis.

2.3.4 Meeting Agendas, Attendance, Minutes, and Correspondence The Contractor must prepare and distribute an agenda for each Contractor-hosted meeting, in advance of the meeting date. Contractor must coordinate agenda topics with GSA’s Project Manager for all other scheduled and unscheduled stakeholder meetings.

Contractor representation at all meetings must include those individuals having knowledge of the agenda topics and authority to make decisions and commit resources.

The Contractor must provide minutes of all Contractor-hosted project meetings and presentations to all attendees. Minutes must identify new and unresolved old action items, along with assigned responsible parties and estimated completion date(s). Contractor must distribute minutes within (5) calendar days after each meeting.

2.3.5 Electronic Project Management Information System (PMIS) Proliance® software from Meridian Systems, a secure, web-based, electronic project management (ePM) system will be provided by GSA to accommodate the information needs of all project participants. The ePM system must be maintained continuously through completion of the project. All communications among the major parties involved in the project execution must be captured and recorded in the ePM system. User licenses and training will be provided for all Government and contracted members of the Project Delivery Team who will require access to the ePM system.

The Contractor must use ePM for all necessary communications with other major parties involved in the project. Electronic storage and transmission of information via the ePM system must be compliant with the provisions of the Document Security section of these General Requirements.

2.4 ELECTRONIC/PRINT MEDIA

2.4.1 Other Electronic Documents

In addition to any hardcopy submission requirements, all submissions must be submitted in electronic format. All electronic media must be in a form readable by standard office automation applications.

2.4.2 Plans and Specifications

Provide four (4) hardcopy sets of plans (2 full-size, 2-half size) of all plans, after award.

2.5 CONTRACTOR PERSONNEL SECURITY REQUIREMENTS

Refer to the Construction Contract Agreement Section III, Terms and Conditions, for HSPD-12 suitability investigation requirements for Contract employees requiring access to the facility. Also see http://www.GSA.gov/HSPD12 for security suitability requirements. Contractor must incorporate provisions in all applicable subcontracts as necessary to ensure compliance with all requirements provided in this Contractor Personnel Security Requirements section.

2.6 DOCUMENT SECURITY

Sensitive But unclassified (SBU) building information may be generated and/or be disseminated to and stored by various parties in the course of executing this project. SBU building information is information that, if misused, poses a potential security risk to a building, its occupants and visitors, and/or its contents. The Contractor must comply with the requirements regarding handling, disseminating, and storing SBU building information as described in the most recent GSA Order (currently GSA Order PBS 3490.3 dated 16Oct2019).

2.7 RECORD KEEPING

The Contractor must prepare correspondence and other documentation and maintain accurate and detailed records of the project’s progress during all phases. The Contractor must maintain records so as to facilitate document storage and retrieval.

2.8 CONSTRUCTION SUBMITTAL AND RFI PROCESSING

On behalf of GSA, the Contractor must manage and document the processing of the Contractor submittals and requests for information (RFI’s). Refer to Division 01 Specifications for construction submittal and RFI requirements and limitations.

3 SCOPE OF SERVICES

The Contractor must perform all services described in this Scope of Services (including services required under exercised options, if any), in accordance with applicable requirements and provisions set forth in the General Requirements section above.

3.1 CONSTRUCTION STAGE

Upon receipt of Notice to Proceed, the Contractor must perform all services as described in this section and contract requirements.

The Contractor must construct the project in accordance with the SOW requirements, contract requirements, and the Construction Documents. The Contractor must provide (furnish and install, complete and ready for use) all materials, related services, and other items, as well as the means and methods of construction for all aspects of the project.

3.1.1 Construction Phase BIM Requirements

The Contractor must use BIM applications where applicable or appropriate for construction coordination. Examples include coordinated electronic product and manufacturer documentation, electronic owner’s manuals, 3D geometric models of equipment layout, collision detection, virtual construction, as-built BIM, model-integrated building automation systems, model-based building monitoring systems, etc. BIM may also be used for construction coordination among various trades and subcontractors, typically with the Contractor in the lead role.

3.1.2 Construction Start Coordination

3.1.2.1 Pre-Construction Conference

The Contractor must participate in a Pre-Construction conference.

3.1.3 Construction Stage Photographs

The Contractor must provide color digital images of the project elements in JPEG format with a minimum resolution of 1024x768 pixels. Contractor must upload images into the project’s Google Shared Drive (drive to be created by GSA and shared after contract award) and into the ePM project repository. All image file names must include a description of the image.

Images must be accompanied by a statement signed by the photographer (or his or her authorized representative) allowing GSA to reproduce the images in print and electronic media without additional compensation.

3.1.3.1 Pre-Construction Photographs

Contractor must provide color digital images of existing facility conditions in an as-is (existing) state prior to starting Construction Stage activities.

3.1.3.2 Construction Progress Photographs

At weekly intervals during construction, the Contractor must take digital images of the project’s progress from different points of view documenting progress of the work. The Contractor must take photographs weekly, adjusting the timing of the photographs each month to coincide with the cut-off date associated with each application for payment. Some photographs must be taken from the same vantage point each time to best show the status of construction and progress since taking previous photographs.

3.1.4 Construction Administration

In order to administer the construction of the project properly and efficiently, the Contractor must provide the following services and deliverables.

· Construction Site Office – The GSA may provide a project office with utilities and furnishings; however, this is not a guarantee, and any space provided will be limited in size and may, upon short notice, be rescinded due to the facility’s near-full tenant occupancy.

· The Contractor must provide GSA with any/all construction schedules in Microsoft Project file format for GSA’s internal use.

· Schedule of Values (SOV) – The Contractor must prepare and submit an SOV based on awarded contract to GSA for approval. The SOV must be maintained by the Contractor, with updates submitted to GSA on regular basis and with each pay application.

· Construction Delivery Phase Record-keeping – Refer to Division 01 specifications.

· Construction Progress Reporting – Refer to Division 01 specifications.

· Construction Safety Program – Refer to Division 01 specifications.

· Project Progress Meetings – GSA will participate with the Contractor in regularly scheduled progress meetings. Refer to Division 01 specifications.

· Construction Schedules – The Contractor must provide and maintain construction schedules in accordance with the requirements provided herein and in Division 01 specifications.

· Submittal Processing – The Contractor must prepare and submit a Submittal Schedule/Registry in accordance with Division 01 specifications. For workflow and internal/external stakeholder coordination purposes, all submittals must be submitted to GSA electronically in the project’s Google Shared Drive (to be created by GSA after contract award). Record documents for all submittals must be processed in the ePM system in accordance with the procedures developed and approved by GSA.

· Inspections and Testing – The Contractor must develop an overall inspections and testing plan in accordance with the SOW and contract. The Contractor must conduct all inspections and tests as required by the construction specifications.

· The Contractor must conduct construction safety (OSHA) inspections as required.

· Clarifications/Requests for Information/Change Orders – Using ePM and the project’s Google Shared Drive, and in accordance with procedures developed and approved by GSA, the Contractor must promptly submit to GSA a written request for information (RFI) to request clarification of any owner-related issues, apparent conflicts, ambiguities, or omissions in the DB contract requirements.

· The Contractor must ensure that all subcontractors understand, agree to, and conform to their respective roles, responsibilities, and timeliness requirements for RFI processing.

· Each RFI must include a specific description of the issue requiring clarification, citing the specific related contract documents requiring clarification. RFIs must only be submitted after performing due diligence to confirm that the contract requirements in question are in fact unclear or otherwise inadequate.

· Upon receipt of the response to each RFI submitted, the Contractor must coordinate the response with all involved subcontractors to ensure understanding and appropriate action.

· Contractor must store all record documents for all RFIs in the ePM system.

· Contractor As-Built Drawings and Specifications – The Contractor must update the CAD drawings (as-built drawings) and electronic specifications at least monthly in order to document the changes that occur during construction.

3.1.4.1 Payment Requests

The Contractor must update the construction schedules monthly, prior to each payment request and provide an advance copy of the construction progress report to the Project Manager. The Contractor must provide documentation evidencing the cost of work performed to be included in the payment request, i.e. an updated SOV.

Before submitting each payment request, the Contractor must meet with GSA to review the advance copy of the construction progress report and associated updated SOV. The Contractor must ensure that GSA agrees with the progress of the construction work and the value of the work completed/accepted.

Based upon the agreed construction progress report, schedule, and associated updated SOV, the Contractor may then submit their formal monthly payment request to GSA.

3.1.5 Construction Stage Commissioning

During the Construction Delivery Phase, the Contractor must coordinate its testing, inspection, and quality assurance activities with GSA’s independent testing, inspection, and verification. Elements of the Contractor’s Quality Control (CQC) Plan for all systems, assemblies, and equipment may overlap elements of the commissioning requirements which will be independently verified by, but not performed by, GSA. The Contractor must perform Commissioning activities as briefly described below and as per the contract requirements.

3.1.5.1 Construction Stage Commissioning Plan Updates

The Contractor must review and comment on Construction Stage Commissioning Plan updates.

3.1.5.2 Commissioning Schedule

The Contractor must review and comment on the commissioning schedule, and must coordinate all commissioning work activities with the Project Delivery Team to ensure that commissioning activities are being incorporated and properly sequenced. The Contractor must integrate all commissioning activities into the construction schedule.

3.1.5.3 Construction Stage Commissioning Coordination

The Contractor must participate in regular commissioning coordination meetings with the Project Delivery Team.

3.1.5.4 Systems Coordination Plans

The Contractor must prepare and submit systems coordination plans as described and required in the Contract Documents.

3.1.5.5 Commissioning Testing and Inspection Procedures

The Contractor must provide GSA the information required to perform commissioning tasks, including O&M materials and Contractor start-up and checkout procedures. Before systems start-up, the Contractor must coordinate with subcontractors, GSA, and all other relevant parties to obtain information and clarity on control sequences and interlocks as necessary to develop detailed testing procedures and an enhanced systems start-up and initial systems checkout plan.

The Contractor must review and comment on the step-by-step commissioning test procedures for commissioned systems, including pre-functional test (PFT) procedures, functional performance test (FPT) procedures, and documentation forms and construction checklists for all commissioned equipment and assemblies.

The Contractor must assist GSA in preparing an enhanced start-up and initial systems checkout plan with contractors for commissioned equipment.

3.1.5.6 Construction Checklists

The Contractor must complete the construction checklists as the work is accomplished.

3.1.5.7 Commissioning Testing and Inspection

The Contractor must coordinate with GSA and other involved parties when performing all required Commissioning Testing and Inspection per the Commissioning Plan.

The Contractor must coordinate with GSA and all other involved parties as necessary to perform any re-testing and/or re-inspection required if initial testing and inspection indicates performance deficiencies.

The Contractor must assist GSA in coordinating the scheduling of additional off-site testing and must review and comment on GSA special testing reports, as appropriate, for tests of critical components and systems.

The Contractor must assist GSA in verifying proper installation of commissioned components and systems.

The Contractor must provide GSA with all subcontractor functional testing records for commissioned systems and assemblies.

3.1.5.8 Commissioning Documentation

The Contractor must perform these duties related to documentation:

· Review and comment on GSA commissioning inspection reports

· Assemble and review all commissioning test certifications described in the testing and inspection plan

· Resolve all failures reported in the commissioning issues log

3.1.5.9 Commissioning Test Certifications

The Contractor must assist GSA in assembling and reviewing all commissioning test certifications described in the Commissioning Plan.

3.1.5.10 Commissioning Issues Log

The Contractor must resolve all failures reported in the Commissioning Issues Log prior to acceptance of any installed system.

3.1.6 Turnover Process

3.1.6.1 Substantial Completion

Prior to substantial completion, the Contractor must assist GSA in conducting a pre-final walk-through.

GSA’s current expectation is that there will be several substantial completion dates/milestones for the overall project/contract – one for HUD space, one for DOL space, and one for ABAAS upgrades – as each of these “separate” project aspects is completed. However, for simplicity and to facilitate overall contract administration, there will be one (1) Period of Performance (PoP) associated with the overall contract.

3.1.6.2 Punch-List

After GSA certification that the work or each designated portion thereof is substantially complete, the Contractor must assist GSA in conducting a final inspection and preparing a punch-list documenting remaining work for that project aspect.

The Contractor must participate with GSA in conducting follow-up inspections to administer resolution of punch-list items.

3.1.6.3 Operation and Maintenance (O&M) Manuals Submittals

The Contractor must prepare and submit complete and properly organized O&M manuals as required in accordance with the Final CD specifications. The O&M manuals must be presented in both 3-ring binder (hardcopy) and digital (normally PDF) file formats.

3.1.6.4 Warranties, Guarantees and Certificates

The Contractor must prepare and submit warranties, guarantees, and certificates, ensuring that GSA’s rights and responsibilities are clearly defined.

3.1.6.5 Final As-Built Drawings and Specifications

The Contractor must prepare and submit final as-built CAD & BIM drawings, and electronic as-built specifications, for review and approval at the completion of the construction.

3.1.6.6 Material Samples, Attic Stock and Spare Parts

As a condition for GSA certification of substantial completion, the Contractor must provide an inventory list of all attic stock items to be turned over to GSA at close-out.

3.1.6.7 Preparation for Occupancy

The Contractor must coordinate the planning and scheduling of Property Management Office (PMO) training with GSA PMO staff, allowing sufficient lead time for GSA to prepare for the training and to ensure that the appropriate personnel will be available.

The Contractor must conduct training of operating staff in optimal operation and maintenance of the delivered equipment as required in accordance with Final CD specifications. The training must be conducted on-site in the completed and fully operational facility using the actual equipment in place.

The Contractor must include any available and suitable video material from manufacturers and suppliers in the training sessions.

The Contractor must prepare list(s) of equipment inventory and room numbering to match the data structure of GSA’s National Computerized Maintenance Management System (NCMMS), i.e. in COBie format.

3.1.7 Construction Closeout

3.1.7.1 Project Awards/Certifications

The Contractor must assist GSA in compiling all required documentation and submitting any applications for awards and/or certifications.

3.1.7.2 Final Record Documents

The Contractor must update the CAD construction drawings (as-built drawings) and electronic specifications (as-built specifications) to document all changes that occur, or unforeseen conditions impacting delivered work during construction. The Contractor must produce final record documents, based on as-built drawings and specifications, to reflect all contract modifications and noted field conditions. The Contractor must finalize any necessary BIM model updates to reflect as-built conditions.

3.1.7.3 GSA CAD & BIM Library Coordination

The Contractor must coordinate with GSA’s Regional CAD and Spatial Data Management coordinators to upload record documents to GSA’s document library.

3.1.7.4 Final Project Photographs

The Contractor must provide digital images (JPEG format, minimum resolution of 1024x768 pixels) as necessary to fully depict the completed project. All images must be tagged with the project name and the specific view/description of the image. Captions and photo credits must also be keyed to each image.

All digital images must be accompanied by a statement signed by the photographer (or his or her authorized representative) allowing GSA to reproduce the images in print and electronic media without additional compensation.

3.1.7.5 Closeout Stage Commissioning Activities

The Contractor must provide close-out stage commissioning services per the Commissioning Plan and contract.

3.1.7.6 Contract Closeout

As part of the contract close-out process, the Contractor must, before submitting final invoices:

· Resolve all outstanding punch list items

· Assist GSA with establishing a final accounting of the total contract amount, broken down into the key modernization cost elements.

· Submit a Release of Claims

· Return all Government-issued security credentials

4 ADMINISTRATION

4.1 Travel

The Contractor is responsible for all travel costs to support the requirements contained in this Statement of Work, including, but not limited to, all progress meetings, workshops, reviews, site visits, and factory equipment test witnessing. The Contractor must not assume all travel will be within the vicinity of the project site except as specifically indicated otherwise in the Scope of Services section.

4.2 Reproduction and Delivery

Printing, reproduction and delivery costs necessary for execution of this contract are included in the contract price.

SOW v1 12April2021 image1.jpg image2.jpg