Exh 5 to Sample Contract_Specs.docx

DOCX document 89 KB Posted

Attached to
US101: Trask River Bridge Proj.
Solicitation number
S-73000-00016851
Issued by
Tillamook County, Oregon

About this file

This document is a Specification Exhibit for the Trask River Bridge Project (US 101) in Oregon, prepared by the Oregon Department of Transportation (ODOT). The project involves scour repair work at a bridge crossing the Trask River and includes associated roadway and environmental protection measures. Key work components include mobilization, traffic control accommodations, temporary access roads, temporary river traffic control, temporary water management facilities, erosion and sediment control, environmental protection measures, contaminated soil management, clearing and grubbing, earthwork, riprap protection, commercial grade concrete, seeding, planting, fencing, and waterway enhancements. The specifications reference the 2024 Oregon Standard Specifications for Construction and include numerous special provisions that modify or supplement those standard specifications. The project involves regulated work areas at or below 17 feet elevation between stations "L" 288+60 and "L" 290+30, with in-water work restricted to July 1 through September 15. Estimated material quantities include 168 cubic yards of embankment, 227 square yards of subgrade geotextile, 19 cubic yards of excavation, and 145 tons of aggregate base for temporary access roads. Approximately 742 cubic yards of contaminated soil from known pesticide and herbicide locations must be excavated, with 269 cubic yards reused on-site and 710 tons disposed at a landfill.

The specifications establish comprehensive environmental and safety requirements including NPDES 1200-CA permit compliance, fish and fish habitat protection measures, turbidity monitoring protocols, migratory bird protection, and cultural resource protection through an Inadvertent Discovery Plan. Contractors must prepare site-specific Health and Safety Plans meeting HAZWOPER training and medical surveillance requirements for contaminated soil work. Traffic control requirements restrict lane closures on US 101 to weekdays 9:00 a.m. to 4:00 p.m. and Fridays 9:00 a.m. to 12:00 p.m., with load restrictions on bridges limited to 65,000 pounds per 1,000 square feet or 200,000 pounds total per span. Pre-construction conference attendance is mandatory, and multiple submittals are required including Traffic Control Plans, Temporary Water Management Plans, Erosion and Sediment Control Plans, OSMB Work Plans, and archaeological monitoring coordination. Payment terms include lump sum amounts for mobilization, temporary water management, temporary river traffic control, turbidity monitoring, and Health and Safety Plans, with unit pricing for contaminated soil disposal, reinforcement materials, and landscape work items. No separate payment is provided for temporary facility removal, restoration activities, or incidental materials unless specifically identified in the contract schedule.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT 5

SPECIFICATIONS

US101: Trask River Bridge Proj.

OREGON STANDARD SPECIFICATIONS FOR CONSTRUCTION. The 2024 Oregon Standard Specifications for Construction (“Standard Specifications”) include detailed specifications in Part 00200 and beyond (“technical specifications”) that apply to this Project. Some sections of the technical specifications may be identified and modified in the Contract Documents. Sections of the technical specifications not identified in the Contract Documents remain applicable to the Contract according to their original terms.

Sections 00120-00199 in Part 00100 of the Standard Specifications are not applicable to the Contract unless they are specifically identified in the Contract Documents as being applicable. However, if a section in Part 00100, Section 00120—00199, that has been identified as being applicable references another section in Part 00100, or if a technical specification references a section from Part 00100, that section from Part 00100 applies to the Contract for purposes of supporting and giving full effect to the specification that referenced it. Abbreviations, definitions, and conventions in Part 00100, Section 00110, apply to the ITB and any resulting Contract as required for context within the Contract Document. The Standard Specifications can be accessed online at:

http://www.oregon.gov/ODOT/Business/Pages/Standard_Specifications.aspx

SPECIAL PROVISIONS

The special provisions below identify and modify certain sections of the Standard Specifications.

All number references in the special provisions shall be understood to refer to the sections and subsections of the Standard Specifications bearing like numbers.

TABLE OF CONTENTS FOR SPECIAL PROVISIONS

SECTION 00210 - MOBILIZATION3
SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC3
SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC CONTROL4
SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS5
SECTION 00223 - WORK ZONE TRAFFIC CONTROL LABOR AND VEHICLES6
SECTION 00224 - TEMPORARY TRAFFIC CHANNELIZING DEVICES6
SECTION 00231 - TEMPORARY ACCESS ROAD7
SECTION 00232 - TEMPORARY RIVER TRAFFIC CONTROL9
SECTION 00245 - TEMPORARY WATER MANAGEMENT11
SECTION 00270 - TEMPORARY FENCES15
SECTION 00280 - EROSION AND SEDIMENT CONTROL15
SECTION 00290 - ENVIRONMENTAL PROTECTION19
SECTION 00294 - CONTAMINATED MEDIA28
SECTION 00305 - CONSTRUCTION SURVEY WORK32
SECTION 00310 - REMOVAL OF STRUCTURES AND OBSTRUCTIONS32
SECTION 00320 - CLEARING AND GRUBBING32
SECTION 00330 - EARTHWORK32
SECTION 00350 - GEOSYNTHETIC INSTALLATION32
SECTION 00390 - RIPRAP PROTECTION33
SECTION 00440 - COMMERCIAL GRADE CONCRETE34
SECTION 01030 - SEEDING35
SECTION 01040 - PLANTING37
SECTION 01050 - FENCES40
SECTION 01091 - WATERWAY ENHANCEMENTS40
SECTION 02510 - REINFORCEMENT43

SPECIAL PROVISIONS

SECTION 00210 - MOBILIZATION

Comply with Section 00210 of the Standard Specifications.

SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC

Comply with Section 00220 of the Standard Specifications modified as follows:

00220.01(b) Abbreviations - Delete this subsection.

00220.02(b) Temporary Pedestrian Accessible Route Plan - Add the following bullet(s) to the end of the bullet list:

Maintain access to bus stops and Pedestrian Accessible Routes.

00220.03(b) Closures - Add the following bullets to the end of the bullet list:

Floatable Natural Waterway - A minimum of 35 Calendar Days before restricting or closing the public access site(s), listed below:

Public Access Location – Steiner Boat Launch and Carnahan City Park .

00220.40(e)(1) Closed Lanes - Replace this subsection, except for the subsection number and title, with the following:

Traffic Lanes may be closed on the Oregon Coast Highway US 101 when allowed, shown, or directed during the following periods of time except as specified in 00220.40(e)(2):

Single Lane Closures - One Traffic Lane on the Oregon Coast US 101 may be closed during the following times:

Daily, Monday through Thursday, between 9:00 a.m. and 4:00 p.m.

Daily, Friday, between 9:00 a.m. and 12:00 p.m.

Add the following subsection:

00220.45 Load Restrictions on Bridges - For Structure(s) No.(s) 07147, limit the combined weight of construction vehicles, Equipment, and daily Material usage to 65,000 pounds for every 1,000 square feet of surface area plus the weight of long term storage of Materials to 25,000 pounds for every 100 square feet of surface area of the Bridge or a total of 200,000 pounds for each span of the Bridge, whichever is less.

The Contractor may request alternate loadings by submitting, 30 Calendar Days before proposed loadings, stamped loading calculations and data according to 00150.35.

SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC CONTROL

Comply with Section 00221 of the Standard Specifications modified as follows:

00221.06 Traffic Control Plan ‑ Replace this subsection with the following subsection:

00221.06 Traffic Control Plan and Tourist-Oriented Directional and Business Logo Signs –

(a) Traffic Control Plan - Submit one of the following, 5 Calendar Days before the preconstruction conference:

(1) Agency Traffic Control Plan ‑ If the Contractor intends to use the Agency TCP without modification, a written notification indicating that the Agency TCP will be used without modification.

(2) Contractor-Modified Traffic Control Plan ‑ The Contractor may request to use a Contractor-modified Agency TCP, or a TCP developed by the Contractor. Do not use a modified TCP, or a TCP developed by the Contractor, unless approved by the Engineer. Use the Agency TCP unless a modified TCP, or a TCP developed by the Contractor is accepted.

The Engineer is not obligated to consider any modified Agency TCP or a TCP developed by the Contractor. The Agency will not be liable to the Contractor for failure to accept or act upon any request for a modified Agency TCP or a TCP developed by the Contractor.

To conserve time and funds, the Contractor may first submit a written request for a preliminary review by the Engineer. The request should contain a description of the proposal together with a rough estimate of anticipated dollar and time impacts. The Engineer will, within a reasonable time, respond to the Contractor in writing whether or not the request would be considered by the Agency.

If requesting a Contractor-modified Agency TCP, or a TCP developed by the Contractor, at a minimum the request shall meet all requirements of the Contract documents and comply with the Project transportation management plan (TMP). Provide the following information:

Stamped Working Drawings according to 00150.35 that include the proposed TCP showing all TCM and quantities of TCD.

A TPAR plan that includes:

Details and features used to provide pedestrian accessibility.

Pedestrian staging Plans at a scale no smaller than 1 inch = 50 feet.

Temporary alternate facilities or detour routes for pedestrian traffic.

Staging sequences and details for Work affecting vehicular, pedestrian, and bicycle traffic.

Proposed order and duration of the TCM.

A detailed temporary striping plan.

If the Contractor’s request to use a Contractor-modified Agency TCP, or a TCP developed by the Contractor is approved in whole or in part, acceptance will be made by a Change Order.

The Engineer will establish prices that represent a fair measure of the value of Work to be added, changed, or deleted as a result of any accepted modifications to the Agency TCP or an accepted TCP developed by the Contractor.

Once a TCP has been accepted by the Engineer, any additional modifications must be submitted by the Contractor for Agency review following the procedure described above. The Engineer is not obligated to consider additional modifications to a previously approved TCP.

(b) Tourist-Oriented Directional and Business Logo Signs ‑ Submit one of the following for approval, at least 5 Calendar Days before the preconstruction conference:

(1) No Signs ‑ If there are no tourist-oriented directional (TOD) or business logo signs on the Project, a written notification that no TOD or business logo signs exist within the Project limits or

(2) Signs ‑ Submit one copy of a sketch map of the Project showing all existing TOD and business logo signs and a written narrative describing how these signs will be kept in service and protected throughout all the construction stages. If modifications are necessary, submit updated information to the Engineer for approval at least 21 Calendar Days before the change is needed.

00221.60 Temporary Traffic Control Devices – Replace the paragraph that begins “TCD delivered to the Project Site found…” with the following paragraph:

Repair or replace TCD delivered to the Project Site found to be in “marginal” or “unacceptable” condition, at no additional cost to the Agency.

00221.90(b) Temporary Protection and Direction of Traffic – Replace the bullet that begins “Providing, Surfacing, maintain…” with the following bullet:

Providing, surfacing, maintaining, removing, and restoring the TPAR.

SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS

Comply with Section 00222 of the Standard Specifications modified as follows:

00222.40(e) Temporary Sign Placement ‑ Add the following to the end of the bullet list:

Place a “WAIT FOR FLAGGER” (CR4-23) sign approximately 50 feet in advance of each flagger station, facing incoming pedestrian traffic when a flagger is required to coordinate pedestrian movements. Install the sign on a conical marker or other temporary sign support, as shown or as directed. Do not allow the sign installation height or location to block the visibility of the flagger for incoming Public Traffic.

At least ten Calendar Days prior to the start of work, when the TPAR is open through the work area, place a “SIDEWALK OPEN” (CW11-3) sign in advance of each end of the Work Area as shown in the TCP or as directed. Locate the sign so it is legible from the nearest alternate pedestrian pathway facing incoming pedestrian traffic. The sign may be mounted between the panels of a Type II barricade, or on a single-post TSS. Do not place the sign or support such that it narrows the pedestrian pathway to a width less than 4 feet. Maintain “SIDEWALK OPEN” (CW11-3) signs while work is affecting the pedestrian pathway.

Place a “PEDESTRIANS ON ROADWAY” (CW11-2) sign, when the TPAR is located on a Roadway or paved Shoulder, at the beginning of each end of the Work Area, facing incoming traffic as shown, or as directed.

Install "ROAD WORK AHEAD" (W20‑1‑48) signs with a 36 by 24-inch "FINES DOUBLE" (R2‑6aP) rider on the Oregon Coast Highway, according to the "TCD Spacing Table" shown on the Standard Drawings or as modified by the Plans except do not install the "FINES DOUBLE" rider on concrete barrier mounted signs.

Install beyond each end of the Project, facing outgoing traffic, an "END ROAD WORK" (CG20‑2A‑24) sign a distance of (A ÷ 2) according to the "TCD Spacing Table" shown on the Standard Drawings or as modified by the Plans.

SECTION 00223 - WORK ZONE TRAFFIC CONTROL LABOR AND VEHICLES

Comply with Section 00223 of the Standard Specifications modified as follows:

00223.80 Measurement - Replace the bullet that begins ”The replacement of TCD and TCM…” with the following bullet:

The replacement of flagger station lighting damaged by Public Traffic and replaced by the Contractor.

Add the following paragraph to the end of the bullet list:

No additional measurement will be made for automated flagger assistance devices damaged by Public Traffic and replaced or repaired by the Contractor.

SECTION 00224 - TEMPORARY TRAFFIC CHANNELIZING DEVICES

Comply with Section 00224 of the Standard Specifications.

SECTION 00231 - TEMPORARY ACCESS ROAD

Section 00231, which is not a Standard Specification, is included in this Project by Special Provision.

Description

00231.00 Scope - This Work consists of constructing, maintaining, and removing temporary, unpaved access roads for the use of Contractor and Agency Equipment and personnel as needed, shown, or directed.

Materials

00231.11 Geotextile - Furnish subgrade geotextile. Geotextile shall meet the requirements of Section 02320, with documentation according to 02320.10(c).

00231.12 Geogrid - Subgrade reinforcement geogrid, if used, shall meet the requirements of Section 02320.

00231.13 Road Material - Furnish crushed Aggregate Base, stone embankment, or other suitable Granular Material capable of supporting the weight of Equipment intended to use the temporary access road.

Construction

00231.41 Clearing - Clearing brush and vegetation for temporary access roads is allowed in the areas shown or where directed. Preserve and protect trees as shown or directed.

00231.42 Temporary Access Road - Construct temporary access roads to the width, grade, profile, and depth of base sufficient to support the weight of Equipment using the road. Install geotextile or geogrid prior to placement of road material.

00231.43 Not for Public Traffic - Do not direct or allow Public Traffic to use temporary access roads constructed according to this Section.

00231.45 Verification of Original Ground - Test the density of the original ground according to TM 158, in the presence of the Engineer, before beginning construction of the temporary access road and after removing it. If post-removal density testing indicates that the original ground has been weakened by construction activities, or the presence or use of the temporary access road, correct the deficient condition in an approved manner and at no additional expense to the Agency.

Maintenance

00231.60 Surface Maintenance - Maintain temporary access roads so that the road surfaces remain firm, smooth, free of ruts or standing water, and are graded to prevent concentrations of runoff water. Promptly remove accumulations of mud or debris.

Finishing and Cleaning Up

00231.70 General - When a temporary access road is no longer needed, do the following:

Remove all Materials.

Restore areas occupied by the temporary access road to the original ground contours or as directed.

Apply permanent seeding to the area occupied by the temporary access road according to Section 01030.

Dispose of excess materials according to 00330.41(a)(5).

Rebuild existing embankments according to 0330.42(c)

Measurement

00231.80 Measurement - Except for permanent seeding, no measurement of quantities will be made for Work performed under this Section. The estimated quantities of Materials are:

Construct and Remove Temporary Access Road:

Item Quantity

Embankment168 Cu. Yd.
Subgrade Geotextile227 Sq. Yd.
Excavation19 Cu. Yd.
Aggregate Base145 Ton

The quantities above do not include excavation required for removal of the temporary access roads.

Permanent seeding will be measured according to 01030.80.

Payment

00231.90 Payment - The accepted quantities of Work performed under this Section, except for permanent seeding work, will be paid for at the Contract Lump Sum amount for the item "Construct and Remove Temporary Access Road".

Payment will be payment in full for furnishing and placing all Materials, and for furnishing all Equipment, labor, and Incidentals necessary to complete the Work as specified.

No separate or additional payment will be made for removing and disposing of temporary access road materials or for restoring the areas to original ground contours.

Permanent seeding Work will be paid for according to 01030.90.

SECTION 00232 - TEMPORARY RIVER TRAFFIC CONTROL

Section 00232, which is not a Standard Specification, is included in this Project by Special Provision.

Description

00232.00 Scope ‑ This Work consists of setup, maintenance, and removal of temporary river zone traffic control to comply with Oregon State Marine Board (OSMB) regulations. Preliminary approval of the temporary clearances and river traffic control has been provided by OSMB but is subject to final approval based on the OSMB Work Plan submittal.

00232.01 Submittals

(a) Notification – Submit to the Engineer in writing for approval any limitation to river usage or traffic patterns for either recreational or commercial craft that would prevent the through passage of any currently permitted craft. Such changes include but are not limited to partial river closures such as a closure under a bridge span not in the navigable channel, installation of debris booms, warning signs and buoys. Notify the Engineer a minimum of 30 Calendar Days before making any changes that affect such river usage.

(b) OSMB Work Plan Submittal – At least 30 Calendar Days prior to beginning activities and operations affecting any part of the waterway in the vicinity of the scour repair work, submit the following:

Plan view and elevation view sketches of work zone and associated waterway with proposed obstructions that reduce permanent horizontal and vertical clearances and recreational navigation channel(s) (work bridge, cofferdams, vessels, barges, containment, etc.).

Prime Contractor contact for the Project, with associated email and phone number.

Scheduled on-site start work date and finish work date.

Days and times of operation over the normal work week.

Dates and times of stages of work, as applicable for operations involving sequential or staged activities.

Location of the Work by latitude and longitude, river mile, and geographic point of land, with latitude and longitude expressed in degrees, minutes, seconds, and thousandths of seconds.

Point of contact phone number available for 24-hour-seven-days-a-week contact from local mariners through the duration of the Project.

Detailed identification of work operation hazards to mariners, if any, created by operations (cables, buoys, machinery, tools, tows, containment and platform structures, cofferdams, falling debris such as during waterline removal or installation, etc.), including details such as size, diameter, color as applicable.

Precautions regarding the in-water vessels, Equipment, and work operation hazards, if any, affecting local mariners such as operating speed and wake, clearance distance, etc.

Systems and Equipment causing a reduction in the existing available vertical clearance beneath the bridge, if any, such as containment and platform systems and supports and the Equipment necessary to install, maintain, and remove such systems, and the identification of any falling debris hazard to waterway traffic.

Description of advisory signage and lighting to be implemented by the Contractor to advise local mariners of the operations, reduced clearances, and presence of work operation hazards, as applicable. Include description of the advisory message, and placement and orientation of the signage and flashing amber lighting (4-seconds/15 per minute).

Submit the OSMB Work Plan to the Engineer.

Approval from the Engineer is required prior to submitting a Boating Obstruction Report advising of the operations and allowing the operations to commence.

Throughout the Project, submit Addendums to the Plan as necessary to stay consistent with Contractor’s planned operations. Submit any Addendums a minimum of 30 Calendar Days prior to the anticipated start date of the Work and include the same information listed above.

(c) Boating Obstruction Report – At least 30 Calendar Days prior to beginning activities and operations affecting any part of the waterway in the vicinity of the bridge work, submit a Boating Obstruction Report to the OSMB. Contact information is located at: https://oregon-boating-obstructions-geo.hub.arcgis.com/

Throughout the Project submit Boating Obstruction reports as necessary to stay consistent with Contractor’s planned operations. Submit information at least four weeks before an event or operation is scheduled to commence.

Materials

00232.10 Materials - Included is all temporary Materials and labor needed to meet the Work as shown and as detailed below. Also included are any modifications to these Materials made as a result of the Contractor's traffic control methods.

(a) Buoy Lines – Furnish round orange buoys with a minimum diameter of 16 inches that have a 3-inch reflective band near the top of each buoy. Space buoys 10 feet on center, with connecting ropes and anchors, for placement in the Trask River. Buoy lines may consist of separate buoys with individual anchors, or strings of buoys anchored at the ends. Submit Materials for approval prior to installing buoy lines.

(b) Temporary River Navigation Signs – Use Materials and signs according to Section 00222.

Construction

00232.40 General - Do not occupy or impede navigation in the river at any time, unless otherwise approved in writing.

(a) Buoy Lines - Install buoy lines at approved locations. Anchor securely, using as many anchors as required to keep buoy lines in indicated locations. Adjust anchor lines as needed due to changing river level or as required.

(b) Temporary River Navigation Signs – Install signs at locations shown or directed.

Maintenance

00232.60 Buoy lines and Temporary River Navigation Signs - Evaluate and maintain or immediately replace all unacceptable buoy lines and signs.

Measurement

00232.80 Measurement ‑ No measurement of quantities will be made for Work performed under this Section.

Payment

00232.90 Payment ‑ The accepted quantities of Work performed under this Section will be paid for at the Contract unit price, per unit of measurement, for the following item:

Pay Item Unit of Measurement

(a) Temporary River Traffic Control................................................ Lump Sum

Payment will be payment in full for furnishing, installing, maintaining in good Working order, replacing, and removing all Materials, and for furnishing all Equipment, labor, and Incidentals necessary to complete the Work as specified.

SECTION 00245 - TEMPORARY WATER MANAGEMENT

Section 00245, which is not a Standard Specification, is included in this Project by Special Provision.

Description

00245.00 Scope - This Work consists of furnishing, installing, operating, maintaining, and removing temporary water management facilities in regulated Work areas.

00245.01 Abbreviations:

TWM-Temporary Water Management
TWMF-Temporary Water Management Facility
TWMP-Temporary Water Management Plan

00245.02 Definitions:

Temporary Water Management Facility - A TWMF that conveys water around or through Work areas, removes water from Work areas, and treats and discharges water at locations outside Work areas.

00245.03 Temporary Water Management Plan - The Agency TWMP is a concept plan. 28 Calendar Days before beginning Work in regulated Work areas, submit stamped Working Drawings of a Contractor-developed TWMP, according to 00150.35, based on either the Agency’s concept plan or an independent plan that meets water quality and environmental guideline requirements and does not negatively affect neighboring properties or water rights.

Include the following minimum information in the TWMP:

The sequence and schedule for dewatering and re-watering. This sequence and schedule must include when to contact the Engineer prior to dewatering and re-watering.

How the Work area is isolated from the active stream flow upstream, through, and downstream.

How the stream flow is routed and conveyed around or through the isolated Work area.

How fish passage is provided around the Work area, if required.

How the isolated Work area is de-watered.

How the pumped water is treated, if necessary, before it is discharged downstream.

Description of all construction stages, including appropriate contact points for each stage.

A list of on‑site backup Materials and Equipment.

Provide the name of the TWM Subcontractor (if applicable) and Contractor’s superintendent, and their 24‑hour contact phone number 10 Days before the pre-Work meeting. If changes in the appointment of the TWM Subcontractor or Contractor’s superintendent occur during the term of the Contract, provide written notice to the Engineer within 5 Calendar Days of the change.

Calculations of water withdraw pump’s capacity.

Details of the proposed water intake screen used to isolate in-water Work area and how it meets the requirements of 00290.34(c)(3).

Any change to the TWMP during construction requires approval prior to implementation.

Obtain the Engineer's written approval before beginning Work in in‑water Work areas.

00245.04 Pre-Work Meeting ‑ Before beginning any TWM Work, attend a pre-work meeting at the Project Site with the Engineer no more than 8 Calendar Days prior to implementation of TWM. Required meeting attendees include:

Engineer Contractor TWM Subcontractor (if applicable) Agency Environmental Coordinator or their appointed representative

The pre-Work meeting agenda typically includes the method of TWM, the TWMP, fish salvage plan and strategy, describe environmental risks, turbidity monitoring, energy dissipation, dewatering and re-watering plan and strategy, site clean-up expectations, and the circumstances under which contacting the Engineer is required.

Materials

00245.10 Materials - Furnish Materials meeting the following requirements:

Riprap00390.11
Cofferdams00520.10

Furnish pumps that are:

Self‑priming.

Equipped with a variable speed governor.

Equipped with a power source.

Able to pump water that contains soft and hard solid.

Construction

00245.40 Fish Removal - Qualified Agency, ODFW, or ODOT consultant biologists will remove fish and other aquatic organisms from the isolation Work areas. Coordinate fish removal with the Engineer at least 28 Calendar Days before beginning Work in regulated Work areas. Allow access into the isolation Work areas before, during and after installation of the TWMF to perform the specified tasks as follows:

Before Installation of TWMF - Before any in-water Work, including installing TWMF, qualified personnel will remove fish and other native aquatic organisms from within the proposed isolated Work area.

After Installation of TWMF - After installing TWMF and the reduction of the water level through the isolated Work area has begun, qualified personnel will remove all fish and aquatic organisms as the water level is reduced. Do not completely de‑water the isolation area until all fish and aquatic organisms have been removed.

00245.41 Installation - During installation of the temporary water management facility, maintain a downstream water flow rate of at least 50 percent of the upstream water flow rate.

00245.42 Operation - Operate temporary water management as follows:

Protect fish and fish habitat according to 00290.34.

Maintain and control water flow downstream of the isolated Work area for the duration of the diversion to prevent downstream de-watering.

Clean, maintain and repair water intake screening to ensure adequate flows and protection of aquatic organisms.

In the event of containment failure immediately notify the Engineer so arrangements can be made to remove fish and aquatic organisms from the isolation Work areas prior to the continuation of Work within the ordinary high water limits.

Maintenance

00245.60 Maintenance - Monitor water turbidity according to 00290.30(a)(8).

Finishing and Cleaning Up

00245.70 Removal - Prior to removal of the TWMF, obtain approval from the Engineer after completion of all Work within ordinary high water limits. Remove the TWMF and re‑water and restore the stream flow. Maintain downstream water flow during removal of the facility. Staged or metered re-watering may be required and will be determined by the Engineer.

Measurement

00245.80 Measurement - No measurement of quantities will be made for temporary water management facilities.

The estimated quantities of Materials required for the temporary water management facility are:

Temporary Water Management Facility at Station "L" 288+40 :

Sediment Control Facility1 Each
Riprap3 Cubic Yard
Cofferdams224 Square Yard

Turbidity monitoring will be measured according to 00290.80.

Payment

00245.90 Payment - The accepted quantities of temporary water management facilities will be paid for at the Contract lump sum amount for the item "Temporary Water Management Facility at Station _______ ".

The location of the facility will be inserted in the blank.

Payment will be payment in full for furnishing and placing all Materials, and for furnishing all Equipment, labor, and Incidentals necessary to complete the Work as specified.

Turbidity monitoring will be paid for according to 00290.90.

No separate or additional payment will be made for TWMP, maintaining, operating, monitoring, moving, or removing the facility.

SECTION 00270 - TEMPORARY FENCES

Comply with Section 00270 of the Standard Specifications as modified:

00270.10 Material – Replace the sentence that begins “Provide new Material…” with the following paragraph:

Provide new Material meeting the requirements of 01050.10. Used Materials in like new condition may be provided if approved. See 00270.70.

SECTION 00280 - EROSION AND SEDIMENT CONTROL

Comply with Section 00280 of the Standard Specifications modified as follows:

00280.00 Scope - Replace the paragraph that begins "This Work also consists of providing temporary …" with the following paragraphs and bullets:

This Work also consists of providing temporary erosion and sediment control (ESC) measures and furnishing, installing, moving, operating, maintaining, inspecting, and removing ESC throughout the Project area according to the Standard Drawings, the erosion and sediment control plan (ESCP), the Specifications, or as directed, until the site is permanently stabilized. Included also is the monitoring of weather, of stormwater and receiving waters, the reporting of monitoring observations, the reporting of corrective actions (when necessary) and the updates and revisions of the ESCP, including ESCP cover sheet, necessary to keep it representative of current site conditions and compliant with the NPDES 1200-CA, 1200-CN, OR 1200-C permit if applicable.

Conditions requiring NPDES 1200 permits are as follows:

Projects with one acre of ground disturbance or more on Agency owned land are regulated under the Agency’s 1200-CA permit.

When Project Work on Agency owned land disturbs less than one acre, but ground disturbances on non-Agency owned lands combined with Project ground disturbances on Agency owned land total one acre or more the Agency Project Work will be regulated by the Agency’s 1200-CA permit. The Contractor is responsible for acquiring the 1200-C permit for all areas of disturbance on non-Agency owned land.

When the combined areas of disturbance of all Project related activities is less than one acre, no NPDES 1200 permit coverage is required.

The area of ground disturbance on Agency owned land is 0.13 acres.

Delete the paragraph that begins “When contaminants, pollutants or hazardous materials…”.

Add the following paragraph to the end of this subsection:

The Agency's NPDES 1200‑CA permit is applicable to the Project.

Add the following subsection:

00280.01 Submittals – Submit documentation that the compost material meets the requirements of Section 03020 for its intended use and is available for use according to the Project schedule in 00180.41 according to 00150.37, within 30 Calendar Days of Award of the Contract,.

00280.02 Definitions ‑ Delete the definition Wet Season Work

00280.04 Erosion and Sediment Control Plan on Agency Controlled Lands ‑ Replace the bullet that begins “Information required under 1200-CA…” with the following bullet:

Information required under 1200-CA permit, if applicable.

Add the following paragraphs to the end of this subsection:

Fill in required information listed on the ESCP cover sheet prior to beginning of construction and submit revised cover sheet to Engineer 10 Days before the preconstruction meeting. Monitor weather, stormwater runoff, and receiving waters, and document monitoring observations. Immediately upon discovery, notify Engineer if a 1200-CA permit non-compliance occurs. Provide updates and revisions of the ESCP, including ESCP cover sheet, necessary to keep it representative of current site conditions and compliant with the 1200-CA permit.

When contaminants, pollutants or hazardous materials are discovered in the Project location in soils or groundwater comply with 00290.20(f) and, provide an environmental management plan (EMP) as required by the 1200-CA permit if applicable.

00280.15(f)(1) Filter Sock Material - Add the following sentence to the end of this subsection:

Furnish filter sock Material with a diameter of 12 inches.

00280.16(a) Construction Entrances - Replace the bullet that begins “Geotextile…” with the following bullet:

Geotextile - Riprap geotextile meeting the requirements of 02320.20 Table 02320-2. Provide documentation according to 02320.10(c).

0280.16(d) Inlet Protection - Replace the bullet that begins “Geotextile…” with the following bullet:

Geotextile - Type 1 geotextile meeting the requirements of 02320.20 Table 02320-1 Provide documentation according to 02320.10(c).

00280.16(k) Active Treatment System – Add the following sentence to the end of this subsection:

Obtain approval of the active treatment system from DEQ prior to use.

00280.30 Erosion and Sediment Control Manager – Add the following bullet to the beginning of the bullet list under “The ESCM duties include:”

Be present at the Project Site during all ground disturbing activities.

Replace the bullet that begins “Monitor rainfall, snow melt and runoff …” with the following bullet:

Visually monitor rainfall, snow melt and runoff at the Project Site.

Replace the bullet that begins “Monitor water quality in receiving streams in …” with the following bullet:

Visually monitor water quality in receiving streams in the vicinity of the Project Site.

Replace the bullet that begins “Monitor water in sediment traps receiving …” with the following bullet:

Monitor the pH of the water in sediment traps receiving runoff from soils amended with cementitious material for acidity or alkalinity.

Add the following bullet to the end of the bullet list:

Monitor locations identified in Section 00294 for compliance.

00280.41(c) Wet Season Work and Temporary Work Suspension ‑ Replace this subsection with the following subsection:

00280.41(c) Temporary Work Interruption ‑ Update the ESCP and schedule for Work proposed between October 1 and May 31 to ensure that all appropriate controls, including ESC during Work interruption, are implemented and maintained. Submit the updated ESCP and schedule to the Agency and receive approval before beginning any Work between October 1 and May 31.

Between October 1 and May 31, limit excavation and bare ground activities to only those required for immediate operations. Stabilize stockpiles at the end of each workday by diverting flows, placing covers, or installing Sediment barriers.

00280.41(f) Hauling Material – Replace this subsection, except for the subsection number and title, with the following:

Cover loads carrying soil or sediment which may generate dust. Haul saturated loads in water tight beds or drain saturated loads prior to leaving the Project Site.

00280.41(g) Underground Injection Controls (UIC) – Replace this subsection, except for the subsection number and title, with the following:

Do not allow storm water from work area to enter Underground Injection Control (UIC) inlets, UIC catch basins or UIC wells.

00280.48 Emergency Materials - Add the following paragraphs after the paragraph that begins "Provide, stockpile, and protect...":

Provide and stockpile the following emergency Materials on the Project Site:

Item Quantity

Sediment Barrier, Type 3………………………………100 FT
Inlet Protection, Type 78 EA
Straw Bale………………………………………………….6 EA

When emergency materials are used, restock emergency materials within 48 hours of use.

00280.62 Inspecting and Monitoring – Delete the paragraph that begins “Inspect the Project Site…”.

00280.62(a) Inspection ‑ Replace the paragraph that begins "Perform site inspection, complete…" with the following paragraph:

Inspect the Project Site and all ESC devices for Effective Function and potential erosion or sediment movement and complete all applicable parts of the ODOT Erosion Control Monitoring Form, and submit the form to the Agency as follows:

00280.62(b) Rainfall – Add the following to the end of this subsection:

The closest on-line rain gauge is located at:

forecast.weather.gov/MapClick.php?lat=45.42951&lon=-123.82428&unit=0&lg=english&FcstType=graphical

00280.64(a) Corrective Action Timelines – Delete the bullet that begins “If completion of corrective action is not feasible…”

Delete the bullet that begins “Provide a schedule for clean-up and corrective actions…”

Delete the bullet that begins “Provide all corrective action documentation and photographs…”

00280.64(b) Corrective Action Documentation – Add the following bullets to the beginning of the bullet list:

If completion of corrective action is not feasible within 24 hours, document the reasons why the time line cannot be met.

Provide a schedule for clean-up and corrective actions that restores Effective Functioning as soon as feasible. If schedule cannot be met document the reasons for the delay.

Provide all corrective action documentation and photographs to Agency within 24 hours of completion of corrective actions.

00280.70 Removal – Add the following to the end of this subsection:

Leave Sediment Barrier, Type 8 in place, it will remain the property of the Agency unless directed otherwise.

00280.91 Payment – Replace the paragraph that begins “Emergency Materials that are incorporated…” with the following paragraph:

Materials listed in 00280.48 that are incorporated into the Project will be paid for under the appropriate items listed in the Contract Schedule of Items.

SECTION 00290 - ENVIRONMENTAL PROTECTION

Comply with Section 00290 of the Standard Specifications modified as follows:

00290.20(c)(2) Clean Fill - Add the following paragraph to the end of this subsection:

Manage all excavated soil that does not meet the definition of clean fill according to Section 00294.

00290.30 Pollution Control – Replace the paragraph that begins "Prevent, control, and abate…" with the following paragraph:

Prevent, control, and abate pollution of the environment.

00290.30(a)(1) General - Replace this subsection, except for the subsection number and title, with the following:

Do not allow any foreign substances or objects to enter waters of the State and U.S. that exceed regulated or permit limits.

Do not cause turbidity in waters of the State and U.S. that exceeds regulated or permit limits.

Add the following subsection:

00290.30(a)(7) Water Quality:

Do not discharge water contaminated by pollutants including sediment, drilling fluids and waste, concrete, grout, or water contained within a work area isolation, into any waters of the State or U.S. or conveyances draining thereto until it has been treated using Materials such as those listed in 00280.15 or 00280.16 or by pumping to a vegetated upland location. Do not allow Project discharges to increase the concentration of any pollutant in the receiving water to a level that exceeds the limits prescribed by OAR 340‑041.

Do not use permanent stormwater quality treatment facilities to treat construction runoff unless prescribed by an ESCP approved under Section 00280.

If construction discharge water is released using an outfall or diffuser port, do not exceed velocities more than 4 feet per second, and do not exceed an aperture size of 1 inch.

Implement containment measures adequate to prevent pollutants from entering waters of the State or U.S. Such pollutants include but are not limited to construction and demolition materials, waste spoils, fuel or petroleum products, detergents, silt, welding slag and grindings, concrete sawcutting by-products and sandblasting abrasives.

Do not allow curing concrete or grout to be submerged within waters of the State or U.S. less than 24 hours after placement, except within work area isolation. Do not end-dump riprap into the waters of the State or U.S. Place riprap from above the ordinary high water line.

Monitor weather and streamflow forecasts and conditions to anticipate high flows that may unintentionally inundate any portion of the Project Site.

If high flow conditions occur or are anticipated to occur that may unintentionally inundate any portion of the Project Site, remove all potentially affected Equipment, Materials, and debris from the potential inundation area. Cease Work in the area until water recedes and the risk of further high water events passes. The Engineer retains the authority to temporarily halt or modify the Work in case of excessive turbidity or damage to natural resources.

If Work in or around waters of the State or U.S. violate permit conditions or any requirement of this subsection, stop such Work and notify the Engineer.

Add the following subsection:

00290.30(a)(8) Meter Turbidity Monitoring - In addition to the requirements of 00280.62(c) to monitor the receiving stream to identify water quality issues, during Work in waters of the State or U.S., implement best management practices (BMPs) to minimize turbidity, and monitor turbidity using a turbidity meter that has been maintained and calibrated according to the manufacturer’s specifications and according to the following:

Measure upcurrent and downcurrent turbidity at two-hour intervals and perform work based on turbidity measurements according to the following:

Take upcurrent samples at a location representative of background turbidity approximately 100 feet from the work area.

Take downcurrent samples at a location approximately 100 feet from the work area at approximately mid-depth of the water body and within any visible turbidity plume.

If the downcurrent reading is less than 5 nephelometric turbidity units (NTU) higher than the upcurrent reading, continue to Work and take readings every two hours.

If the downcurrent reading is greater than or equal to 5 and less than 30 NTU higher than the upcurrent reading, modify work procedures and repair or upgrade BMPs, continue Work, and continue to take readings every two hours. If after four hours the downcurrent reading is still greater than or equal to 5 NTU higher than the upcurrent reading, stop all work in water and repair or upgrade BMPs. Resume work in water only after the downcurrent reading is less than 5 NTU above the upcurrent reading.

If the downcurrent reading is greater than or equal to 30 and less than 50 NTU higher than the upcurrent reading, modify work procedures, repair or upgrade BMPs and continue Work. If, at the subsequent two-hour reading, the downcurrent reading is still more than 30 NTU higher than the upcurrent reading, stop all work in water and repair or upgrade BMPs. Resume work in water only after the downcurrent reading is less than 5 NTU above the upcurrent NTU reading.

If the downcurrent reading is 50 NTU or more higher than the upcurrent reading, stop all work in water, repair or upgrade BMPs, and inform the Engineer. Resume work in water only after the downcurrent reading is less than 5 NTU above the upcurrent NTU, as determined by continued readings made no more than two hours apart.

Document all turbidity monitoring observations on form 734-2755, “Turbidity Monitoring Report”, or another form approved by the Engineer. Submit reports to the Engineer weekly during work in water and keep copies of the reports at the Project Site.

Meter turbidity monitoring may be temporarily suspended if all of the following conditions are met:

Temporary water management and work area isolation measures have been installed and are functioning as designed.

The Engineer, after consultation with DEQ, has authorized the suspension of turbidity monitoring. The Engineer will provide information to be documented on the turbidity monitoring form, including the date of the DEQ authorization and the name of the DEQ employee providing the authorization.

Resume the turbidity monitoring protocol if Work during a temporary suspension of meter turbidity monitoring causes a release of a visible turbidity plume.

00290.34 Protection of Fish and Fish Habitat - Add the following paragraph:

Meet with the Agency Biologist, Resource Representative, Engineer, and inspector on site, before moving equipment on-site or beginning any work, to ensure that all parties understand the locations of sensitive biological sites and the measures that are required to be taken to protect them.

00290.34(a) Regulated Work Areas - Add the following to the end of this subsection:

The regulated work area is the area at or below 17 feet elevation and between stations “L” 288+60 and “L” 290+30.

Perform work within the regulated work area only during the in-water work period. The in‑water work period is from July 1st to September 15th.

The total volume of material filled or discharged into waters of the State and waters of the U.S. shall not exceed 1,494 cubic yards.

The total volume of material excavated from the waters of the State and waters of the U.S. shall not exceed 1,163 cubic yards.

Submit a schedule to complete all work within the regulated work area within the in-water work period at least 10 Days prior to the preconstruction conference.

00290.34(b) Prohibited Operations - Add the following to the end of this subsection:

Allow entry within the regulated work area.

Add the following subsection:

00290.34(c) Aquatic Species Protection Measures Required by Environmental Permits:

(1) General Requirements:

Do not install fish ladders (for example: pool and weirs, vertical slots, fishways) or fish trapping systems.

Do not apply surface fertilizer within 50 feet of any stream channel.

Use heavy equipment as follows:

Choice of equipment must have the least adverse effects on the environment (for example: minimally sized, low ground pressure).

Secure absorbent material around all stationary power equipment (for example: generators, cranes, drilling equipment) operated within 150 feet of wetlands, waters of the State, waters of the U. S., drainage ditches, or water quality facilities to prevent leaks, unless suitable containment is provided to prevent spills from entering waters of the State or waters of the U.S.

Do not cross directly through a stream for construction access, unless shown or approved. If shown or approved, cross perpendicular to the stream and do not block stream flow. When a crossing is no longer needed, completely remove the crossing and restore the soils and vegetation to the original condition.

Store fuel and maintain all equipment in staging areas that are at least 150 feet away from any waters of the State, waters of the U.S., or storm inlet or on an impervious surface that is isolated from any waters of the State, waters of the U.S., or storm inlet.

If temporary access roads are needed within 150 feet of any body of water, use existing routes unless new routes are shown or approved.

Before beginning work on temporary access routes that are not shown, submit a proposal to the Engineer for approval.

(2) Work Area Isolation - Provide work isolation according to Section 00245. Provide safe passage around or through the isolated work area for adult and juvenile migratory fish unless passage did not previously exist.

(3) Water Intake Screening - Install, operate, and maintain fish screens on each water intake used for project construction, including pumps used to isolate an in-water work area. When drawing or pumping water from any stream, protect fish by equipping intakes with screens having a minimum 27 percent open area and meeting the following requirements:

Perforated plate openings shall be 3/32 inch or smaller.

Mesh or woven wire screen openings shall be 3/32 inch or smaller in the narrowest direction.

Profile bar screen or wedge wire openings shall be 1/16 inch or smaller in the narrow direction.

Choose size and position of screens to meet the following criteria in Table 00290‑1:

Table 00290-1

Type
Approach Velocity 1

(Ft./Sec.)

Sweeping Velocity 2 (Ft./Sec.)

Wetted Area of Screen (Sq. Ft.)

Comments

Ditch Screen
≤ 0.4
Shall exceed approach velocity
Divide max. water flow rate (cfs) by

0.4 fps If screen is longer than 4 feet, angle 45° or less to stream flow

Screen with proven self-cleaning system
≤ 0.4
–
Divide max. water flow rate (cfs) by

0.4 fps

Screen with no cleaning system other than manual
≤ 0.2
–
Divide max. water flow rate (cfs) by

0.2 fps Pump rate 1 cfs or less

1 Velocity perpendicular to screen face at a distance of approximately 3 inches 2 Velocity parallel to screen

Provide ditch screens with a bypass system to transport fish safely and rapidly back to the stream.

(4) Special Aquatic Habitats - The following exploration or construction activities are not allowed in special aquatic habitats:

Use of pesticides and herbicides, unless allowed according to Section 01030.

Use of short pieces of plastic ribbon to determine flow patterns.

Temporary roads or drilling pads built on steep slopes, where grade, soil type, or other features suggest a likelihood of excessive erosion or slope failure.

Exploratory drilling in estuaries that cannot be conducted from a work barge, or an existing bridge, dock, or wharf.

Installation of a fish screen on any permanent water diversion or intake that is not already screened.

Drilling or sampling in an EPA-designated Superfund Site, a state-designated clean-up area, or the likely impact zone of a significant contaminant source, as identified by historical information, U. S. Army Corps of Engineers representative, or the Agency.

(5) Site Restoration - Restore damaged streambanks to a natural slope, pattern, and profile suitable for establishment of permanent woody vegetation unless precluded by pre‑project conditions (for example: natural rock substrate):

Replant all damaged streambanks before the first April 15 following construction.

If use of large wood, native topsoil, or native channel material is required for the site restoration according to the roadside development plans, stockpile all large wood, native vegetation, weed-free topsoil, and native channel material displaced by construction. Cut trees or large wood and trees into pieces of no less than 20 feet in length, or as shown on the roadside development plans or as directed. Stockpiled native wood and vegetation remain the property of the Agency.

Stabilize all disturbed soils, including obliteration of temporary access roads, following any break in work unless construction will resume in 4 Calendar…