This Estimated Project Quantities document outlines the work scope for the Iowa Department of Transportation's Davenport Tile Boring Replacement project (RFB #645-RFB-1746-2025). The project encompasses subdrain pipe replacement, steel encasement installation, topsoil management, erosion control, seeding, and traffic control measures. Key deliverables include 544 linear feet of 4-inch non-perforated dual-wall HDPE subdrain pipe, 325 cubic yards of topsoil stripping and spreading, 50 linear feet of 8-inch minimum steel encasement for trenchless boring across Ramp D, 0.20 acres of mulching with certified noxious weed-free straw, 0.20 acres of stabilizing crop seeding and fertilizing, 700 linear feet of silt fence installation, 700 linear feet of perimeter and slope sediment control devices, and comprehensive traffic control for work near I-80 and I-280. All work shall comply with Iowa DOT Standard Specifications Series 2023 and applicable supplemental specifications. The bid opening is scheduled for May 7, 2025 at 5:25 PM CDT, with bid closure on May 29, 2025 at 1:00 PM CDT, and estimated project completion by November 15, 2025.
Payment shall be on a unit price basis per linear foot, cubic yard, or acre as applicable for each line item, with the contractor's lump sum mobilization costs included as a separate item. Steel encasement payment is based on the linear footage of encasement actually installed, measured to the nearest foot. Contractors are required to register with the Iowa Department of Workforce Development and must comply with traffic control restrictions prohibiting lane closures on I-80, I-280, or interchange ramps; work within 15 feet of the traveled way requires Standard Road Plan TC-402 installation. Performance and payment bonds may be required if the contracted amount exceeds $25,000. All subdrain work includes removal and disposal of existing tile and accessories, with all necessary fittings and materials included in the unit price. Mulching materials must be certified noxious weed seed-free per Iowa Crop Improvement Association standards, and reseeding shall be performed at the contractor's expense if damage occurs due to contractor negligence during the contract period.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Item
No.
Item Code Item Unit Quantity Estimate Reference Notes
1 2502-8212104 SUBDRAIN, PLASTIC PIPE, 4 IN. LF 544.00
These items shall be non-perforated, dual wall, HDPE pipe and comply with Section 4146. Removal and disposal of existing subdrain tile and other accessories shall be incidental to these items. All fittings required to make connections or angles shall be included. Contractor shall note that not all subdrain items may be used but are included in case any one of these diameters are encountered. It is anticipated that work will include a 3"and 4" size subdrain pipe but sizes will need to be verified in the field. Payment will be per linear foot and will include pipe, fittings, collars, and all other materials necessary to complete the connections.
2 2105-8425015
TOPSOIL, STRIP, SALVAGE AND
SPREAD
CY 325.00 Quantity based on stripping 12" and spreading evenly across excavated area.
3 2599-9999009
STEEL ENCASEMENT FOR
SUBDRAIN TILE, TRENCHLESS, 8"
DIA.
LF 50.00
Item is for boring a trenchless 8"-minumum steel encasement across Ramp D (I-80 eastbound on Ramp). Steel encasement shall be a minimum 1/4" wall thickness. Installation will be in accordance with Standard Road Plan DR-302. Item shall include all costs to install steel encasement including encasement pipe, jacking pit, boring, labor and any other materials required to provide encasement. Method of Measurement: Iowa DOT will measure the length of encasement installed to the nearest foot. Basis of Payment: Payment to contractor shall be based on the contract unit price per linear foot of encasement installed.
4 2601-2634100 MULCHING ACRE 0.20
Perform mulching According to Article 2601.03, E, 2, of the Standard Specifications. Anchor mulch into the soil using mulch anchoring equipment with a minimum of two passes. Item is included for areas requiring reshaping and seedbed preparation. Use mulch that is Certified Noxious Weed Seed Free
Mulch as certified by the Iowa Crop Improvement Association or adjacent states Crop Improvement Associations. Mulch Rate: 1 1/2 tons of dry cereal straw of native grass straw per acre. Mulching: Mulching shall be applied as described in standard specification section 2601. After seeding, mulch all areas disturbed by grading.
5 2601-2642100
STABILIZING CROP - SEEDING AND
FERTILIZING
ACRE 0.20
Item is included for disturbed areas. Seed and fertilize all disturbed areas according to Article 2601.03, C, 1 of the Standard Specifications. If permanent seeding cannot be placed due to the restrictive planting dates, stabilizing crop will need to be placed on all disturbed areas as temporary erosion control. Preparation and seeding shall be performed in accordance with Section 2601. Stabilizing crop will not be used when the application dates in
Section 2601 allows permanent seeding. If stabilizing crop must be used, place immediately following completions of finished grading. Reseeding of these areas will be required at contractor's expense if damage occurs due to contractor's negligence during the contract period.
6 2602-0000020 SILT FENCE LF 700.00 Item is to be installed as needed during the course of the project to prevent any silt from entering the stream or leaving the project.
7 2602-0000071
REMOVAL OF SILT FENCE FOR SILT
FENCE FOR DITCH CHECKS
LF 700.00
Item is included for silt fence removal required for staging reasons, removal to allow for replacement (Replacement to be paid separately), or for areas that have achieved 70% permanent growth. Remove silt fence and posts after multching or vegetation is established and approved by the Engineer.
8 2602-0000312
PERIMETER AND SLOPE SEDIMENT
CONTROL DEVICE, 12 IN. DIA.
LF 700.00 Item is to be installed as needed during the course of the project to prevent any silt from entering the stream or leaving the project.
9 2602-0000351
REMOVAL OF PERIMETER AND
SLOPE OR DITCH CHECK SEDIMENT
CONTROL DEVICE
LF 700.00
Contractor Responsibilities: Ensuring that sediment control devices, including perimeter and slope sediment control devices, are removed following appropriate erosion control measures.
Site Conditions Considerations: The contractor must verify device placement and removal conditions in coordination with the project engineer.
Spacing Recommendations: Guidelines for sediment control device installation based on slope percentage and site-specific erosion control needs.
10 2601-2636041
SEEDING AND FERTILIZING
(RURAL)
ACRE 0.20
Seed and fertilize all areas disturbed in the right-of-way according to Article 2601.03, C, 3, of the Standard Specifications. Use ground driven equipment. Reseeding of these areas will be required at the contractor's expense if damage occurs due to contractor's negligence during the contract period.
11 2528-8445110 TRAFFIC CONTROL LS 1.00
Item is payment for all traffic control necessary to perform the work. Contractor will not be allowed to work from the shoulder or close any lanes of I-
80, I-280, or any ramps within the interchange. If work is within 15 feet of traveled way, contractor shall install Standard Road Plan TC-402. Otherwise install Standard Road Plan TC-1.
12 2533-4980005 Mobilization LS 1.00 Section 2533 shall apply.
ESTIMATED PROJECT QUANTITIES - REFERENCE NOTES
aafifeh Text Box
*** STANDARD SPECIFICATIONS -- SERIES 2023 ***
The Iowa Department of Transportation STANDARD SPECIFICATIONS FOR HIGHWAY AND BRIDGE CONSTRUCTION, SERIES 2023, plus applicable General Supplemental Specifications, Developmental Specifications, Supplemental Specifications AND Special Provisions shall apply to construction work on this contract.
GS-23003: GENERAL SUPPLEMENTAL SPECIFICATIONS FOR HIGHWAY AND BRIDGE CONSTRUCTION Electronic Reference Library - Iowa Department of Transportation - October 17, 2023 https://iowadot.gov/erl/current/GS/Navigation/nav.htm
File details come from the government source that posted it. Updated .