EC-204 Perimeter, Slope and Ditch Check Sediment Control Devices

This document is a Standard Road Plan specification sheet issued by the Iowa Department of Transportation (Iowa DOT) Design Methods Engineer, detailing installation requirements for sediment control devices used in perimeter protection, slope protection, and ditch protection applications. The specification addresses three primary sediment control device types: Perimeter and Slope Sediment Control Devices for general perimeter and slope applications, and Ditch Check Sediment Control Devices for installation in ditches. The devices utilize 3/4" x 3/4" minimum actual size wood stakes installed at varying angles and spacing depending on application type—downslope stakes at 4-foot maximum spacing for perimeter and slope applications and 2-foot maximum spacing for ditch applications, with upslope stakes spaced at device ends and middle locations. Installation specifications require staple fastening every 2 feet on the upslope side for perimeter and slope applications and every 1 foot for ditch applications. All installations require a minimum 12-inch ground contact length and overlap joints per Detail 'A', with provisions for fill and compaction of rills and gullies prior to device placement. The specification notes that devices are not intended for use in perennial or intermittent streams and may require additional run-ups or erosion reduction measures when placed on slopes to ensure proper runoff conveyance.

The document includes detailed installation diagrams across three sheets with sections addressing perimeter control along curbs and inlets, slope protection perpendicular to slope contours, and ditch protection installed perpendicular to ditch configurations. Installation length measurements are taken along the device itself, with run-ups included in total length calculations. Extra material required for overlap installation is not included in the installation length. The specification was revised on 10-19-21 with labeling changes on Sheet 3. Reference materials include links to the Iowa DOT Design Manual (01e-06.pdf), providing additional context and design guidance for sediment control applications on Iowa road projects.

View the file

Other files

File Type Posted
1311041-event.pdf PDF
dr302-Subdrains.pdf PDF
ec201-Silt Fence.pdf PDF
Amendment 1.pdf PDF
AIA Sample Form.pdf PDF
tc001-Traffic Control.pdf PDF
Google Earth with Map.pdf PDF
Seeding in Rural Areas.pdf PDF
Estimated Project Quantities.pdf PDF
I-80 PCC pave I-280 to US Hwy 61 9.pdf PDF
tc402-Traffic Control.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERIMETER CONTROL

Contour Lines

LEGEND

Flow

INLET PERIMETER PROTECTION

PERIMETER CONTROL ALONG CURB

Wood Stake

(Overlap Joint)

DETAIL 'A'

Perimeter and Slope Sediment Control Device

INLET

45 typ.

Right of Way or Protected Area

Perimeter and Slope Sediment Control Device

See Detail 'A' (Typ.)

See Detail 'A' (Typ.)

See Detail 'A' (Typ.)

12" min.

2' min.

(measured along device)

Installation Length

DETAIL 'B'

See Detail 'A' (Typ.)

Control Device

Slope Sediment

Perimeter and incidental to Perimeter and Slope Sediment Control Device.

and compacting rills and gullies, and minor ground shaping, is

Control Device. Minor ground shaping may be required. Filling continuous contact with Perimeter and Slope Sediment

Ensure ground surface is smooth in order to provide placing Perimeter and Slope Sediment Control Device.

Fill and compact rills and gullies (see Detail 'B') prior to

Not intended for use in perennial or intermittent streams.

Sediment Control Device

Perimeter and Slope

Perimeter and Slope Sediment Control Device.

Fill and compact rills and gullies prior to placing

12" min.

8 Install staples every 2 feet on upslope side.

ground.

All stakes to be placed at approximatly 45 degree angle to minimum actual stake size 3/4" x 3/4" wood stakes.

Upslope stakes spaced at ends and middle of device. Use

Install downslope stakes at 4 foot maximum spacing.

included in the installation length.

Extra material required to install overlaps will not be installation length.

along the device. Run-ups will be included in the run-ups and/or means may be required to reduce erosion such that runoff is conveyed along the device, additional each run up the slope to help contain runoff. When placed

Overlap joints per Detail 'A'. Turn the lower 10 feet of

100-19

Possible Tabulation:

Ditch Check Sediment Control Device

Perimeter and Slope Sediment Control Device

Possible Contract Item:

EC-204

REVISION

10-19-21

SHEET 1 of 3

REVISIONS: Changed labeling on Sheet 3.

APPROVED BY DESIGN METHODS ENGINEER

STANDARD ROAD PLAN

SEDIMENT CONTROL DEVICES

PERIMETER, SLOPE AND DITCH CHECK

DESIGNER INFORMATION

https://www.iowadot.gov/design/dmanual/01e-06.pdf http://www.iowadot.gov/design/dmanual/01e-06.pdf

SLOPE PROTECTION

30 typ.

A

A

(measured along device)

Installation Length

Top of Slope or Undisturbed Area

Sediment Control Device

Perimeter and Slope

Sediment Control Device

Perimeter and Slope Filler Material

SECTION A-A

Installation

(Typ.)

See Detail 'A'

(Typ.)

See Detail 'A'

(Typ.)

See Detail 'A'

12" min.

Contour Lines

LEGEND

Flow

Wood Stake

12" min.

Install staples every 2 feet on upslope side.

length.

runaround. Run-ups will be included in the installation feet of each device up the slope to prevent flow contours). Overlap joints per Detail 'A'. Run the last 10

Install Slope Protection perpendicular to slope (parallel to staples every 2 feet on upslope side.

minimum actual stake size 3/4" x 3/4" wood stakes. Install

Upslope stakes spaced at ends and middle of device. Use

Install downslope stakes at 4 foot maximum spacing.

EC-204

REVISION

10-19-21

SHEET 2 of 3

REVISIONS: Changed labeling on Sheet 3.

APPROVED BY DESIGN METHODS ENGINEER

STANDARD ROAD PLAN

SEDIMENT CONTROL DEVICES

PERIMETER, SLOPE AND DITCH CHECK

DITCH PROTECTION

Foreslope

Ditch

Backslope

Control Device Ditch Check Sediment

Control Device Ditch Check Sediment

12" min.

INSTALLATION IN DITCH

(measured along device)

Installation Length

Contour Lines

LEGEND

Flow

Wood Stake

12" min.

Install staples every 1 foot on upslope side.

joints per Detail 'A'.

Install Ditch Protection perpendicular to ditch. Overlap minimum actual stake size 3/4" x 3/4" wood stakes.

Upslope stakes spaced at ends and middle of device. Use

Install downslope stakes at 2 foot maximum spacing.

EC-204

REVISION

10-19-21

SHEET 3 of 3

REVISIONS: Changed labeling on Sheet 3.

APPROVED BY DESIGN METHODS ENGINEER

STANDARD ROAD PLAN

SEDIMENT CONTROL DEVICES

PERIMETER, SLOPE AND DITCH CHECK

ec204