This document is a Prebid Meeting Question and Answer summary for the Construction of Large Potable Water Valve Replacement Project (EO-3598, WD-52-22) issued by the Long Beach Utilities Department. The project involves the replacement of large potable water valves on Willow Street. Key clarifications from the prebid meeting address contractor responsibilities, including the installation of line-stops only (no insertion valves), removal of existing 20-inch valve bypass piping in its entirety, and hydrotesting and chlorination of any depressurized water system sections. The contractor must complete the Caltrans Encroachment Permit process for work on Willow Street, following instructions outlined in the permit and special provisions detailed in the contract documents' Part 10 specifications.

The Long Beach Utilities Department will furnish butterfly valves and actuators as owner-supplied materials. Test caps for hydrotesting are not being provided by the water department and must be secured by the contractor. The project is not subject to a Prevailing Wage Agreement (PLA). While a Caltrans Rider Permit is not explicitly required to be pulled by the contractor, the contractor must complete the encroachment permit process that has already been initiated by Long Beach Utilities Department with Caltrans District 7, adhering to all permit requirements and special provisions as outlined in the contract documents.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

H:\ACTIVE PROJECTS\EO-3598 Large Valve Replacement - Willow St\1.3 Construction Contractor\Prebid Meeting\EO-3598_Pre- Bid Meeting Q&A.docx

CONSTRUCTION OF LARGE POTABLE WATER VALVE REPLACEMENT PROJECT

(EO-3598)

WD-52-22

Question and Answers

1. Question: Is the water Dept. providing Test Caps to hydrotest new sections of valves and piping?

Answer: No

2. Question: Does the City have the Cal/Trans Permit for the work on Willow St.?

Answer: Long Beach Utilities Department have obtained an Encroachment Permit from Caltrans District 7. The Contractor will be required to complete the process by following the instructions outlined on the permit and the Encroachment Permit Special Provisions. See Specifications, Part 10 – Caltrans Encroachment Permit in the Contract Documents.

3. Question: On Spec. section 33 12 10 - Part 3.2 (A) Furnish and install line-stops and insertion valves at locations shown on the plans and submittals. Line stops and Insertion valves are 2 different applications, and a big difference in cost. What is the contractor to quote, line stops or Insertion valves?

Answer: This project is line-stops only. There are no insertion valves.

4. Question: Can you post list of all Materials LBUD is proving for this project, Valves, test caps, etc.

Answer: Owner furnished materials include butterfly valves and actuators.

5. Question: On the Existing 20” Valves the bypass piping is it to be removed Completely or just cut and cap inside bellhole?

Answer: Per the contract documents, everything is to be removed in its entirely.

6. Question: For Hydrotest and Chlorination, are only sections of installed valves and fittings to be hydrotested and chlorinated or the entire section from line stop to line stop?

Answer: Any portion of the water system that is depressurized shall be hydrotested and chlorinated.

7. Question: Is this a PLA Project?

Answer: This project is not subject to a PLA.

8. Question: Is the contractor required to pull a Cal/Trans Rider Permit?

Answer: See answer to Question #2