Emergency Generator specs 1 3.14.2023.pdf

PDF 3 MB Posted

Attached to
Service of Emergency generator, automatic transfer switches, and relay panels FY24-26
Solicitation number
BD-23-1022-DMH06-8460A-85682
Issued by
Suffolk County, Massachusetts

About this file

This document appears to be a submittal from a vendor for an emergency generator related to a state or local government contract opportunity. The submittal highlights several deviations from the specified requirements, including larger generator dimensions that do not meet the required clearances, the need for a 400-amp breaker, and the absence of a critical grade exhaust silencer. The vendor also indicates that the submitted system is not from one of the three basis-of-design manufacturers specified in the project. The document emphasizes the need for confirmation that the submitted system complies with all aspects of the project specifications.

The document does not provide details on pricing terms, set-asides, incumbents, funding requirements, or sources. It appears to focus solely on the technical details and compliance of the emergency generator submittal with the project specifications.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

X

46250 Amish08/30/17

See notes on page 2 of this submittal.

1. Dimensions exceed that of specified generator

- required clearances for existing panels / gear are not met due to larger size.

2. Include remote e-stops are shown on the plans.

3. Each generator is to have a 400amp breaker to match the rated output.

4. The speed regulation of the governor shall be +/- 0.25% maximum.

5. The on-board generator controller shall have an integral e-stop switch.

6. The remote annunciator shall have manual start/stop capabilities.

7. Critical grade exhaust silencer not submitted.

8. The manufacturer is not one of the three basis-of-design manufacturers.

9. Confirmation shall be provided that the submitted system is in compliance with the project specifications as all aspects of the specified components is not addressed in the submittal.