East of 3 Way_Staking Sheet.pdf
PDF 3 MB Posted
- Solicitation number
- MPE2025DHSEM
- Issued by
- Gilpin County, Colorado
About this file
This document is a 71-page staking sheet for Mountain Parks Electric, Inc. (MPEI) for an electrical infrastructure project located in Jackson County, Colorado, specifically detailing an electrical line extension from an East 3-way junction to the Wyoming state line. The project involves constructing a three-phase #4 ACSR (Aluminum Conductor Steel Reinforced) power line, with specific technical specifications for pole placement, wire configurations, and electrical equipment across multiple station locations. The work includes replacing existing overhead lines, installing new poles, and reconfiguring electrical infrastructure with various wire sizes and configurations.
The project appears to be part of a broader wildfire mitigation construction initiative, funded potentially through the Colorado Department of Public Safety's Division of Homeland Security and Emergency Management (DHSEM) Hazard Mitigation Grant Program. The staking sheet provides extensive technical details for each pole location, including station numbers, pole types, span lengths, wire sizes, primary and secondary voltage configurations, and specific equipment specifications. The documentation suggests a comprehensive engineering approach to modernizing and potentially undergrounding electrical distribution infrastructure in a rural mountainous region, with a focus on improving electrical grid resilience and reducing wildfire risks.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet No. 1 of 71
Name:
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N Range: 79W Section: 4
Pri Voltage: Sec Voltage: Loan No.: S8
Ruling Span: Primary Wire Size: RUS Code: 359
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 34539 P35-5 1952 VC1U-M M2-11 E1-2 F1-2
R VA5-M
C P40-4 VC8-FN-M M2-11 (2) E1-3F78 (3) F1-3S
C VA5-2-M E1-2F78 (3) E-CG
R 34541 P35-7 1952 373 (4) ACSR 4 VC1U-M 0
R 34542 P35-7 1952 379 (4) ACSR 4 VC1U-M 0
C 127 P40-4 2022 276 (4) ACSR 1/0 VC1F-M 0 M2-11
C 128 P40-4 2022 276 (4) ACSR 1/0 VC1F-M 1 M2-11
C 129 P40-4 2022 276 (4) ACSR 1/0 VC1F-M 0 M2-11
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 2 of 71
72 0 72
SCALE IN FEET
Sheet No. 3 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 34543 P35-5 1950 354 (4) ACSR 4 VC2-M 0 M2-11 E1-2 F1-2
C P40-4 2022 278 (4) ACSR 1/0 VC8-2F-M M2-11 (2) E1-3F78 (2) F1-6S
R 34544 P35-7 1952 345 (4) ACSR 4 VC1U-M -5
R 34545 P35-7 1952 349 (4) ACSR 4 VC1U-M -1
R 34546 P35-5 1950 174 (4) ACSR 4 VC2-M 1 M2-11 E1-2F78 F1-2
C 130 P40-4 2022 255 (4) ACSR 1/0 VC1F-M -8 M2-11
C 131
ROCK POLE
HOLE 2022
255 (4) ACSR 1/0 VC1F-M 1 M2-11
C P40-4 2022
C 132
ROCK POLE
HOLE 2022
255 (4) ACSR 1/0 VC1F-M 0 M2-11
C P40-4 2022
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 4 of 71
Sheet No. 5 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 34547 P35-5 1952 339 (4) ACSR 4 VC8-2-M -5 M2-11 (2) E1-2F78
R 34548 P35-5 1950 278 (4) ACSR 4 VC1U-M 0
C 133 P40-4 2022 255 (4) ACSR 1/0 VC1F-M 0 M2-11
C 134
ROCK POLE
HOLE 2022
255 (4) ACSR 1/0 VC1F-M 0 M2-11
C P40-4 2022
C 135
ROCK POLE
HOLE 2022
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 6 of 71
59 0 59
Sheet No. 7 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 34549 P35-5 1950 389 (4) ACSR 4 VC2-M 0 M2-11 E1-2 F1-2
R 34550 P35-7 1952 267 (4) ACSR 4 VC1U-M 4
R 34551 P35-7 1952 304 (4) ACSR 4 VC1U-M 0
C 136
ROCK POLE
HOLE 2022
255 (4) ACSR 1/0 VC1F-M 0 M2-11
C P40-4 2022
C 137
ROCK POLE
HOLE 2022
255 (4) ACSR 1/0 VC1F-M 0 M2-11
C P40-4 2022
C 138
ROCK POLE
HOLE 2022
255 (4) ACSR 1/0 VC1F-M 0 M2-11
C P40-4 2022
C 139
ROCK POLE
HOLE 2022
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 8 of 71
Sheet No. 9 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 34552 P35-7 1952 275 (4) ACSR 4 VC1U-M -1
R 34553 P35-7 1952 216 (4) ACSR 4 VC1U-M 1
R 34554 P35-7 1952 375 (4) ACSR 4 VC8-2-M 0 M2-11
C P40-4 2022 250 (4) ACSR 1/0 VC8-1-M M2-11
C 140
ROCK POLE
HOLE 2022
255 (4) ACSR 1/0 VC1F-M 0 M2-11
C P40-4 2022
C 141
ROCK POLE
HOLE 2022
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 10 of 71
64 0 64
Sheet No. 11 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 34555 P35-7 1952 224 (4) ACSR 4 VC1U-M 0
R 34556 P35-7 1952 210 (4) ACSR 4 VC1-2-M 0
R 34557 P35-7 1952 137 (4) ACSR 4 VC1-2-M -1
E 34558 1 10 KVA 10
R P35-7 1952 298 (4) ACSR 4 VC8-2-M VG105 M2-11 (3) E1-2 (3) F1-2
C P40-4 2022 238 (4) ACSR 1/0 VC8-F-M VG105 M2-11 (3) E1-3F78 (3) F1-3S
E 20 51 3 (3) TPLEX 1/0
Unknown gs_service_point
C 266 P40-4 2022 240 (4) ACSR 1/0 VC1F-M 1 M2-11
C 267 P40-4 2022 240 (4) ACSR 1/0 VC1F-M 0 M2-11
C 268 P40-4 2022 240 (4) ACSR 1/0 VC1F-M 0 M2-11
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 12 of 71
68 0 68
Sheet No. 13 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 34559 P40-5 1997 317 (4) ACSR 4 VC1U-M 1 M2-11
R 34560 P35-5 1970 235 (4) ACSR 4 VA5-2-M -1 M2-11 (2) E1-2F78
R VC2-M
C P40-4 2022 278 (4) ACSR 1/0 VC2F-M VM5-9CLF M2-11 E1-3F78 F1-3S
C
VA5-2-M
OH-FUSE 40
CL
E 34561 P45-5 1973 VA5-1-M 106 VG105 M2-11 E1-2F78 F1-2
E VA5-M 5 KVA 5
R 283 (2) ACSR 4
C 283 (2) ACSR 1/0
C 142 P40-4 2022 274 (4) ACSR 1/0 VC1F-M 0 M2-11
C
ROCK POLE
HOLE
E 13219 P40-5 2009 62 (2) ACSR 1/0 VA6-1-M -111 M2-11 E1-2F78 F1-3S
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 14 of 71
Sheet No. 15 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 34562 P35-5 1954 335 (4) ACSR 4 VC1U-M -22 M2-11
R 34563 P35-5 1950 336 (4) ACSR 4 VC1U-M 0 M2-11
C 143 P40-4 2022 262 (4) ACSR 1/0 VC1F-M -21 M2-11
C 144 P40-4 2022 262 (4) ACSR 1/0 VC1F-M -2 M2-11
C 145 P40-4 2022 262 (4) ACSR 1/0 VC1F-M 2 M2-11
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 16 of 71
78 0 78
Sheet No. 17 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 34564 P35-5 1954 341 (4) ACSR 4 VC1U-M 0 M2-11
R 34565 P40-5 1954 301 (4) ACSR 4 VB8 VM5-9 0 M2-11 E1-2 F1-2
R VC1U-M
C P40-4 2022 265 (4) ACSR 1/0 VA5-2-M VM5-9CLF M2-11 E1-2F78 F1-3S
VC1F-M
E 34566 P45-5 2007 VC1-M 88 M2-11
R 288 (2) ACSR 4
C 288 (2) ACSR 1/0
C 146 P40-4 2022 262 (4) ACSR 1/0 VC1F-M -1 M2-11
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 18 of 71
54 0 54
Sheet No. 19 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 34567 P35-5 1950 181 (2) ACSR 4 VB9 -1 M2-11 E1-2 F1-2
C P40-5 2022 181 (2) ACSR 1/0 VA9F-M M2-11 E1-2F78 F1-3S
R 33926 P35-5 1950 146 (2) ACSR 4 VB9 2 M2-11 E1-2 F1-2
C P40-5 2022 146 (2) ACSR 1/0 VA9F-M M2-11 E1-2F78 F1-3S
E 14934 P40-4 2014 VA5-1-M 0 M2-11 (2) E1-2F78 (2) F1-3S
E VA3-M
R 206 (2) ACSR 4
C 206 (2) ACSR 1/0
E 33928 P35-5 1990
VA5-M -51 25 KVA 25 M2-11 E1-2 F1-2
AMI
COLLECTOR
E VG105
R 214 (2) ACSR 4
C 214 (2) ACSR 1/0
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 20 of 71
62 0 62
Sheet No. 21 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 33924 P35-5 1970 340 (4) ACSR 4 VC3-M 0 M2-11 (2) E1-2 F1-2
C P45-4 2022 172 (4) ACSR 1/0 VC3-M M2-11 (2) E1-3F78 (2) F1-3S
C (2) E-CG
R 33925 P30-5 1954 262 (4) ACSR 4 VC1U-M -47 M2-11
R 33934 P40-5 1950 301 (4) ACSR 4 VC9-1 -1 M2-11
C 154 P40-4 2022 168 (4) ACSR 1/0 VC1F-M 4 M2-11
C 155 P40-4 2022 281 (4) ACSR 1/0 VC1F-M -44 M2-11
C 156 P40-4 2022 277 (4) ACSR 1/0 VC1F-M 1 M2-11
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 22 of 71
132 0 132
Sheet No. 23 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
E 33935 P40-5 0 1 M2-11 (2) E1-2F78 F1-4S
E E-RP
E F1-3S
R 367 (4) ACSR 4 VC1U-M
R VA5-2-M
C VA8-F-M
R 33936 P35-5 1970 360 (4) ACSR 4 VC1U-M 0 M2-11
R 33937 P35-5 1954 342 (4) ACSR 4 VC1U-M 0 M2-11
C 157 P40-4 2022 271 (4) ACSR 1/0 VC1F-M 0 M2-11
C 159 P40-4 2022 298 (4) ACSR 1/0 VC1F-M 3 M2-11
C 160 P40-4 2022 278 (4) ACSR 1/0 VC1F-M -1 M2-11
C 257 P40-4 2022 118 (2) ACSR 1/0 VC1F-M 0 M2-11 E1-2F78 F1-3S
C VA5-2-M E-CG
C 158 P40-4 2022 197 (4) ACSR 1/0 VC1F-M 0 M2-11
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 24 of 71
160 0 160
Sheet No. 25 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 33938 P35-5 1950 356 (4) ACSR 4 VC1U-M 0 M2-11
R 33939 P35-5 1950 341 (4) ACSR 4 VC1U-M 0 M2-11
R 33940 P35-5 1950 341 (4) ACSR 4 VC8-2-M 0 M2-11
C 161 P40-4 2022 278 (4) ACSR 1/0 VC1F-M 0 M2-11
C 162 P40-4 2022 276 (4) ACSR 1/0 VC1F-M 0 M2-11
C 163 P40-4 2022 278 (4) ACSR 1/0 VC1F-M 0 M2-11
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 26 of 71
149 0 149
Sheet No. 27 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 33941 P35-5 1954 319 (4) ACSR 4 VC1U-M 0 M2-11
R 33942 P35-5 1954 341 (4) ACSR 4 VC1U-M 0 M2-11
E 33943 P40-5 1997 1 M2-11 E1-2 E-RP
E F1-2
R 225 (4) ACSR 4 VA5-1-M
R VC1U-M
C 256 (2) ACSR 1/0 VA8-F-M
R 33951 P40-5 1970 261 (4) ACSR 4 VC1U-M -2 M2-11
C 164 P40-4 2022 279 (4) ACSR 1/0 VC1F-M 0 M2-11
C 165 P40-4 2022 278 (4) ACSR 1/0 VC1F-M 0 M2-11
C 166 P45-4 2022 288 (4) ACSR 1/0 VC3-M 0 M2-11 E1-3F78 F1-6S
C 245 P40-4 207 (4) ACSR 1/0 VC1-M -27 M2-11
C 252 P35-4 88 E2-3F12
C 246 P40-4 155 (4) ACSR 1/0 VC2-M 0 M2-11 E1-3F78 E-CG
C F1-4S
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 28 of 71
170 0 170
Sheet No. 29 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 33952 P40-5 1970 318 (4) ACSR 4 VC8-2-M 1 M2-11
R 33953 P40-5 1970 329 (4) ACSR 4 VC1-2-M 0 M2-11
R 33954 P40-5 1970 240 (4) ACSR 4 VC1U-M 0 M2-11
C 168 P40-4 2022 260 (4) ACSR 1/0 VC1F-M -4 M2-11
C 169 P40-4 2022 280 (4) ACSR 1/0 VC1F-M 0 M2-11
C 170 P40-4 2022 209 (4) ACSR 1/0 VC3-M 0 M2-11 E1-2F156 (2) E-CG
C E1-2F78 F1-3S
C 171 P40-4 2022 211 (4) ACSR 1/0 VC1F-M 29 M2-11
C 167 P40-4 299 (4) ACSR 1/0 VC2-M 8 M2-11 E1-2F78 F1-3S
C E-CG
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 30 of 71
142 0 142
Sheet No. 31 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
E 33955 P40-5 1997 VA5-2-M 0 M2-11 E-RP
R 354 (4) ACSR 4 VC1U-M E1-2 F1-2
C 251 (4) ACSR 1/0 VC2F-M VM5-9CLF E1-3F78 F1-3S
R 33960 P40-5 1954 204 (4) ACSR 4 VC1-2-M 0 M2-11
R 33961 P40-5 1950 355 (4) ACSR 4 VC1U-M 0 M2-11
C 172 P40-4 2022 286 (4) ACSR 1/0 VC1F-M 17 M2-11
C 173 P40-4 2022 275 (4) ACSR 1/0 VC1F-M -5 M2-11
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 32 of 71
149 0 149
Sheet No. 33 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 33962 P40-5 1950 356 (4) ACSR 4 VC1U-M 1 M2-11
R 33963 P40-5 1950 290 (4) ACSR 4 VC1U-M -2 M2-11
R 33964 P35-5 1994 VC1U-M 2 M2-11
C 174 P40-4 2022 269 (4) ACSR 1/0 VC1F-M 0 M2-11
C 175 P40-4 2022 280 (4) ACSR 1/0 VC1F-M 0 M2-11
C 176 P40-4 2022 275 (4) ACSR 1/0 VC2F-M 0 M2-11 E1-3F78 F1-3S
C E-CG
C 178 P40-4 2022 461 (4) ACSR 1/0 VC1F-M 18 M2-11
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 34 of 71
133 0 133
Sheet No. 35 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 33965 P35-5 1970 VC2-M -1 M2-11 E1-2 F1-2
R 33966 P35-5 1970 339 (4) ACSR 4 VA5-1-M VM5-9 21 M2-11 E1-2 F1-2
R VC1U-M
R 33967 P35-5 1970 423 (2) ACSR 4 VB8 102 M2-11
E 33968 -1 5 KVA 5
R P35-5 1970 152 (2) ACSR 4 VB8 VG105 M2-11 E1-2 F1-2
C P40-5 2022 191 (2) ACSR 1/0 VA1-M VG105 M2-11
E 33970 3 25 KVA 25
R P30-5 1990 161 (2) ACSR 4 VA5-M VG105 M2-11
C P40-5 2022 161 (2) ACSR 1/0 VA5-M VG105 M2-11 E1-3F12
C E1-2F78
C 180 P40-4 2022 203 (4) ACSR 1/0 VC2F-M 0 M2-11 E1-3F78 E-CG
C F1-3S
C 260 P40-4 2022
254 (4) ACSR 1/0 VC1F-M
OH-FUSE 40
CL
0 M2-11 E1-2F78 E-CG
C VA5-2-M VM5-9CLF F1-3S
C 179 P40-4 2022 551 (4) ACSR 1/0 VC1F-M 0 M2-11
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 36 of 71
119 0 119
Sheet No. 37 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 33972 P35-5 1970 342 (4) ACSR 4 VC1U-M -1 M2-11
R 33973 P35-5 1970 298 (4) ACSR 4 VC1U-M 1 M2-11
R 33974 P35-5 1970 384 (4) ACSR 4 VC1U-M 0 M2-11
R 33975 P35-5 1970 315 (4) ACSR 4 VC1U-M 0 M2-11
C 181 P40-4 2022 266 (4) ACSR 1/0 VC1F-M -15 M2-11
C 182 P40-4 2022 286 (4) ACSR 1/0 VC1F-M 0 M2-11
C 183 P40-4 2022 288 (4) ACSR 1/0 VC1F-M 0 M2-11
C 184 P40-4 2022 275 (4) ACSR 1/0 VC1F-M 0 M2-11
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 38 of 71
183 0 183
Sheet No. 39 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 33976 P35-5 1970 278 (4) ACSR 4 VC1U-M 0 M2-11
R 33977 P35-5 1970 327 (4) ACSR 4 VA5-1-M VM5-9 -1 M2-11 E1-2 F1-2
R VC1U-M
R 33978 P35-5 1970 373 (2) ACSR 4 VA1-2-M 108 M2-11 E1-2 F1-2
R 33979 P35-5 1970 337 (2) ACSR 4 VA1-2-M 0 M2-11
C 185 P40-4 2022 191 (4) ACSR 1/0 VC1F-M -5 M2-11
C 248 P40-5 2022 271 (2) ACSR 1/0 VA1-M 1 M2-11
C 262 P40-4 2022
214 (4) ACSR 1/0 VA5-2-M
OH-FUSE 40
CL
0 M2-11 E1-2F78 F1-3S
C VC1F-M VM5-9CLF E-CG
C 247 P40-5 2022 542 (2) ACSR 1/0 VA1-M 117 M2-11
C 186 P40-4 2022 363 (4) ACSR 1/0 VC1F-M 0 M2-11
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 40 of 71
95 0 95
Sheet No. 41 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 33980 P35-7 1954 373 (2) ACSR 4 VA1U-M 1 M2-11
R 33981 P40-5 1997 352 (2) ACSR 4 VA1U-M -1 M2-11
R 33982 P35-7 1970 150 (2) ACSR 4 VA1U-M 0 M2-11
R 33983 P35-5 1970 348 (2) ACSR 4 VA4-M 0 M2-11 (2) E1-2F78
C P40-5 2022 274 (2) ACSR 1/0 VA4-M M2-11 (2) E1-2F78 (2) F1-3S
E 33984 P40-5 2007 VA5-M 67 15 KVA 15 M2-11 E1-2F78 F1-4S MC-200
E VG105
R 256 (2) ACSR 4
C 256 (2) ACSR 1/0
C 249 P40-5 2022 271 (2) ACSR 1/0 VA1-M 0 M2-11
C 250 P40-5 2022 271 (2) ACSR 1/0 VA1-M 0 M2-11
C 251 P40-5 2022 271 (2) ACSR 1/0 VA1-M 0 M2-11
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 42 of 71
150 0 150
Sheet No. 43 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 33986 P35-5 1970 328 (4) ACSR 4 VC1U-M 1 M2-11
R 33987 P30-5 1970 238 (4) ACSR 4 VC2-M 0 M2-11 E1-2 F1-2
R 33988 P35-5 1954 304 (4) ACSR 4 VC1U-M -23 M2-11
R 33989 P40-5 1997 324 (4) ACSR 4 VC1U-M 0 M2-11
C 187 P40-4 2022 220 (4) ACSR 1/0 VC1F-M 0 M2-11
C 189 P40-4 2022 270 (4) ACSR 1/0 VC1F-M -14 M2-11
C 190 P40-4 2022 270 (4) ACSR 1/0 VC1F-M 0 (2) M2-11
C 270 (4) ACSR 1/0
C 188 P40-4 2022 250 (4) ACSR 1/0 VC2F-M 0 M2-11 E1-3F78 E-CG
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 44 of 71
Sheet No. 45 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 33990 P45-5 1954 245 (4) ACSR 4 VC9 -1 M2-11 E1-2 F1-2
R 33991 P45-5 1954 278 (4) ACSR 4 VC9 1 M2-11 E1-2 F1-2
R 33992 P35-5 1954 355 (4) ACSR 4 VC1U-M 0 M2-11
C 191 P40-4 2022 270 (4) ACSR 1/0 VC1F-M 0 M2-11
C 192 P40-4 2022 270 (4) ACSR 1/0 VC1F-M 0 M2-11
C 193 P40-4 2022 271 (4) ACSR 1/0 VC1F-M 0 M2-11
C 194 P40-4 2022 270 (4) ACSR 1/0 VC1F-M 0 M2-11
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 46 of 71
132 0 132
Sheet No. 47 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 33993 P35-5 1954 301 (4) ACSR 4 VC1U-M 0 M2-11
R 33994 P40-4 2017 288 (4) ACSR 4 VA5-2-M VM5-9L 0 M2-11 E1-2F78 F1-3S
R
VC1-M
OH-FUSE-40
K
R 41902 P40-5 2017 260 (2) ACSR 1/0 VA1-M 94 M2-11
R 41901 P40-5 2017 217 (2) ACSR 1/0 VA1-M 0 M2-11
E 41900 P40-5 2017 VA5-M 0 VG105 M2-11 E1-2F78 F1-3S
E 15 KVA 15
R 280 (2) ACSR 1/0
C 247 (2) ACSR 1/0
E 254 3 15 (15) TPLEX 2 F2S
C 256 P40-5 2022 246 (2) ACSR 1/0 VA1-M 1 M2-11
C 263 P40-4 2022 297 (4) ACSR 1/0 VC1F-M 0 M2-11
C 264 P40-4 2022
296 (4) ACSR 1/0 VC1F-M
OH-FUSE 40
CL
0 M2-11 E1-2F78 F1-3S
C VM5-9CLF E-CG
C 195 P40-4 2022 283 (4) ACSR 1/0 VC1F-M 0 M2-11
C 255 P40-5 2022 246 (2) ACSR 1/0 VA1-M 96 M2-11
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 48 of 71
123 0 123
Sheet No. 49 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 33995 P40-5 1997 365 (4) ACSR 4 VC1U-M 0 M2-11
R 33996 P35-6 1954 326 (4) ACSR 4 VC1U-M 0 M2-11
R 33997 P40-5 1997 351 (4) ACSR 4 VC1U-M 0 M2-11
C 196 P40-4 2022 253 (4) ACSR 1/0 VC1F-M 0 M2-11
C 197 P40-4 2022 253 (4) ACSR 1/0 VC1F-M 0 M2-11
C 198 P40-4 2022 253 (4) ACSR 1/0 VC1F-M 0 M2-11
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 50 of 71
153 0 153
Sheet No. 51 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 33998 P40-5 1997 298 (4) ACSR 4 VC1U-M 0 M2-11
R 33999 P40-5 1997 357 (4) ACSR 4 VC1U-M 0 M2-11 E1-2 F1-2
R VA5-1-M E-RP
R 34254 P35-5 1954 319 (4) ACSR 4 VC1U-M -1 M2-11
C 199 P40-4 2022 253 (4) ACSR 1/0 VC1F-M 0 M2-11
C 200 P40-4 2022 253 (4) ACSR 1/0 VC1F-M 0 M2-11
C 265 P40-4 2022 283 (4) ACSR 1/0 VA5-2-M VM5-9CLF 0 M2-11 E1-2F78 F1-3S
VC1F-M
E-CG
C 201 P40-4 2022 328 (4) ACSR 1/0 VC1F-M 0 M2-11
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 52 of 71
140 0 140
Sheet No. 53 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 14954 P40-4 2015 295 (4) ACSR 4 VC1-M 1 M2-11
R 34256 P40-5 2007 300 (4) ACSR 4 VC1-M -1 M2-11
R 34257 P45-5 1950 284 (4) ACSR 4 VC9 2 M2-11 E1-2 F1-2
C 202 P40-4 2022 259 (4) ACSR 1/0 VC1F-M 0 M2-11
C 203 P40-4 2022 257 (4) ACSR 1/0 VC1F-M 0 M2-11
C 204 P40-4 2022 297 (4) ACSR 1/0 VC1F-M 0 M2-11
C 205 P40-4 2022 252 (4) ACSR 1/0 VC1F-M 0 M2-11
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 54 of 71
143 0 143
Sheet No. 55 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 34258 P35-5 1950 381 (4) ACSR 4 VC1U-M -1 M2-11
R 34259 P35-5 1954 352 (4) ACSR 4 VC1U-M 0 M2-11
R 34260 P35-5 1954 353 (4) ACSR 4 VC1U-M 0 M2-11
C 206 P40-4 2022 253 (4) ACSR 1/0 VC1F-M 0 M2-11
C 207 P40-4 2022 252 (4) ACSR 1/0 VC1F-M 0 M2-11
C 208 P40-4 2022 252 (4) ACSR 1/0 VC1F-M 0 M2-11
C 209 P40-4 2022 252 (4) ACSR 1/0 VC1F-M 0 M2-11
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 56 of 71
Sheet No. 57 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 34261 P40-5 1997 349 (4) ACSR 4 VC1U-M -1 M2-11
R 34262 P35-5 1950 283 (4) ACSR 4 VC2-M 1 M2-11 E1-2 F1-2
C P40-4 2022 282 ACSR 1/0 VC2F-M M2-11 (2) E1-3F78 (2) F1-3S
C E-CG
E 34263 P40-5 1997 23 M2-11 E-RP
E F1-2
R 329 (4) ACSR 4 VC1U-M E1-2
R VA5-1-M
C 165 (4) ACSR 1/0 VC1F-M VM5-9CLF E1-2F78
VA5-2-M
C 210 P40-4 2022 220 (4) ACSR 1/0 VC1F-M 0 M2-11
C 211 P40-4 2022 165 (4) ACSR 1/0 VC1F-M 20 M2-11
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 58 of 71
135 0 135
Sheet No. 59 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 34268 P35-5 1950 346 (4) ACSR 4 VC1U-M -1 M2-11
R 34269 P35-6 1954 354 (4) ACSR 4 VC1U-M 0 M2-11
R 34270 P35-6 1950 308 (4) ACSR 4 VC1U-M 0 M2-11
R 34271 P35-6 1954 289 (4) ACSR 4 VC1U-M 1 M2-11
C 212 P40-4 2022 280 (4) ACSR 1/0 VC1F-M -3 M2-11
C 213 P40-4 2022 276 (4) ACSR 1/0 VC1F-M 3 M2-11
C 214 P40-4 2022 274 (4) ACSR 1/0 VC1F-M 0 M2-11
C 269 P40-4 196 (4) ACSR 1/0 VC1F-M 0 M2-11
C 215 P40-4 2022 126 (4) ACSR 1/0 VC1F-M -1 M2-11
C 216 P40-4 2022 231 (4) ACSR 1/0 VC1F-M 1 M2-11
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Sheet No. 60 of 71
193 0 193
Sheet No. 61 of 71
Map Location:
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation: NP1 - North Park 1Feeder: North Phase:
SO Number: Work Order #: 20220122
Staked By: Date:
Eng Review By: Date:
Released By: Date:
Const Comp By: Date:
Inspected By: Inspected By Date:
Comments:
East of 3-way to WY state line 3ph #4 ACSR to 1/0 ACSR
Directions:
Operations Notes
As-Built
Revised Employee #s Start Date Completed Date
Action Conductor Wire Feet No. of Wires
Pole Line
R ACSR 1/0 1418 2 757
R ACSR 4 114492 4 28593
R ACSR 4 8386 2 4243
E ACSR 1/0 124 2 62
E ACSR 4 1844 4 461
E TPLEX 1/0 3 1 3
E TPLEX 2 15 1 15
C ACSR 1/0 120504 4 29894
C ACSR 1/0 9879 2 4939
C ACSR 1/0 282 1 282
PRIMARY GUY & ANCHOR SECONDARY SERVICE
* STATION NUMBER POLE SPAN
FEET
WIRE SIZE PRIMARY UNIT MISC UNIT LINE
ANGLE
XFMR KVA GRND UNIT GUY LEAD ANCHOR UNIT SPAN
FEET
UNIT "J OR U" WIRE SIZE SPAN
FEET
UNIT "K
OR U"
WIRE SIZE METER OR LOOP
R 34272 P35-6 1954 307 (4) ACSR 4 VC1U-M 0 M2-11
R 34273 P35-5 1954 325 (4) ACSR 4 VC2-M -1 M2-11 E1-2 F1-2
R E-RP
R 34274 P35-6 1954 337 (4) ACSR 4 VC1U-M 8 M2-11
R 34275 P35-6 1950 339 (4) ACSR 4 VC1U-M -1 M2-11
C 217 P40-4 2022 274 (4) ACSR 1/0 VC1F-M 0 M2-11
C 218 P40-4 2022 276 (4) ACSR 1/0 VC2F-M 0 M2-11 E1-3F78 F1-3S
C 219 P40-4 2022 288 (4) ACSR 1/0 VC1F-M 7 M2-11
C 220 P40-4 2022 286 (4) ACSR 1/0 VC1F-M 0 M2-11
Description: East 3-way to WY state line 3ph #4 ACSR
County: JACKSON Township: 11N
Substation:…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .