By:
Date:
PMO RIO Management Working Group
(RMWG)
Federal Aviation Administration
Program Management Organization (PMO)
Risk, Issue, and Opportunity (RIO) Management Process Executive Summary
May 30th, 2013
PMO RIO Management Process Exec Summary
Federal Aviation Administration
Objectives
This executive summary provides an overview of:
– Overview of RIO Management concepts
– PMO RIO Management process
• Process
• Definitions
• Status Options
• Scorecards
– PMO RIO Management Board (RMB) structure
– RIO Software Tools
Federal Aviation Administration
PMO RIO Management Process
Federal Aviation Administration
PMO RIO Management Process
Risk: A future event or situation with a realistic probability of occurring that may have a negative impact to the successful accomplishment of one or more program/portfolio objectives.
Issue: An event or situation that has occurred or is certain to occur and has a negative impact to the successful accomplishment of one or more program/portfolio objectives.
Opportunity: A future event or situation with a realistic probability of occurring that may have a positive impact to the successful accomplishment of one or more program/portfolio objectives.
Federal Aviation Administration
RIO Status Options
RIO Status Option Definition Watch Item A RIO that includes only the minimum set of information and describes a topic of consideration.
Draft A RIO that includes the minimum set of information through full maturity, prior to Manager’s endorsement.
Proposed A draft RIO that is ready for Manager’s endorsement.
Pending A proposed RIO that is awaiting RMB approval.
Approved A pending RIO that has been approved by the RMB.
Not Approved A pending RIO that has not been approved by the RMB.
Disposition Ready An approved RIO that is awaiting RMB decision for disposition.
Closed An approved RIO that has been found to be overcome by events, transferred outside the organization, or found to be duplicate.
Retired An approved RIO that has been successfully managed and is no longer required.
Realized An approved RIO that has not been successfully managed (i.e., has achieved its negative or positive impact).
Federal Aviation Administration
Risk and Issue Assessment Scorecard
Federal Aviation Administration
Opportunity Assessment Scorecard
Federal Aviation Administration
PMO RIO Management Organizational Structure
Federal Aviation Administration
PMO RMB Structure Overview Tier 1:
PMO
Tier 2:
Directors
Tier 3:
Programs
External Orgs.
Note:
• Board meetings are supported by
RIO Review Meetings.
RIO
Status
Meetings
2nd Level Mgr.
Board?
No
Yes
Tier 4:
Programs
Transfer
E sc al at io n
Every other month (2nd Week of Month)
Monthly (1st Week of Month)
Monthly (3rd or 4th Week of Month)
Monthly (3rd or 4th Week of Month)
Monthly (Prior to Tier 2 RMB)
Federal Aviation Administration
Generic RMB Participation Chair: Manager of associated organization Board:
• Deputy Manager of associated organization
• Technical Advisors of associated organization
• Business Management Group of associated organization
• Manager(s) of the next lower level on the organizational chart
External Organization Participants (Required for Tier 2 RMBs, other Tiers as needed):
• ANG-D (NAS Lifecycle Integration)
• AJW-2 (ATC Facilities)
As needed:
• Tier 1 RIO Manager (Tier 1 RMB)
• Tier 2 Manager(s) and/or RIO Manager(s)
• Tier 3/Tier 4 Manager(s) and/or RIO Manager(s)
• Subject Matter Experts (SMEs)
• Risk Management Working Group (RMWG)
Federal Aviation Administration
RIO Software Tools Active Risk Manager (ARM)
• ARM has been selected as the new tool to support PMO RIO Management tasks
– ARM will be used by the PMO, NextGen, and AJW-24
– Allows for easier coordination of RIOs between organizations
• ARM is located behind the FAA firewall
– Access limited to ARM Tool Administrators and RIO Managers
• Reports generated by ARM will be made available to team members by the RIO Managers
• Training was provided to RIO Managers/Admins
PMO Knowledge Sharing Network (KSN)
• RIO Data will be shared with Team Members through the use of Program and
Directorate-level KSN sites
• RIO Data will also be presented through Program Management Reviews (PMRs) and other Management briefings
| Slide Number 1 |
| Objectives |
| PMO RIO Management Process |
| Slide Number 4 |
| RIO Status Options |
| Risk and Issue Assessment Scorecard |
| Opportunity Assessment Scorecard |
| PMO RIO Management Organizational Structure |
| Slide Number 9 |
| Generic RMB Participation |
| RIO Software Tools |