Project No.: AK TTP CHICK 2013(1) Project: Dene Tene Pedestrian Bridge

# General Technical Question Answer Date 1 X Q1: Government contracts sometimes require the testing laboratory be AASHTO accredited. Is that a requirement for this project?

Q2: Sheet J.3 the foundation plan says to provide temporary shoring and bracing. Is this something that needs to be designed by an engineer?

Q3. Do we need to have a engineered stream diversion plan?

A1: No. Test according to Sections 106, 153 and 154.

A2: Yes. See Subsection 574.04.

A.3. No. Design the stream diversion according to Subsection 157.09. Structures requiring the seal and signature of a professional engineer are described in Subsection 104.03.

4/4/17

2 X Looking for a detail on the poured concrete abutment and reinforcing steel for the abutment.

The abutment plan sheets are J.4 and J.5.

The contractor is required to produce their own bar list (See FP 554.03). A blank copy is included on sheet J.10 for reference.

4/4/17

3 X It appears that the requirements for this project is 50% of the labor needs to be performed by a HUBZone contractor.

Reading FAR Clause 52.219‐3 #4 it references Construction by Special Trade Contractors which says that 25% of the cost of contract performance to be incurred for HUBZone personnel. This project appears to require multiple specialty trade contractor, so does this contract fall under the 50% or 25%?

The work identified in this solicitation is primarily for general construction.

Therefore, “52.219‐3(d)(3) of 52.219‐3 Notice of HUBZone Set‐Aside or Sole Source Award” would apply. (4/4/17) In addition to our previous response, we offer the following additional information: for General Construction, 50% is required.

(4/5/17)

4/5/17

4 X Upon award of contract, will notice to proceed be issued before May 1st 2017?

Due to the Migratory Bird Act?

The notice to proceed will not be issued before May 1, 2017 see FAR Clause 52.211‐

10. Regarding the Migratory Bird Treaty Act please see SCR Subsection 107.10(c)(2) and

201.03 for direction regarding clearing and grubbing and other compliance requirements.

4/5/17

Check General or Technical