T A B U L A T I O N O F B I D S Schedule A Total of Bid Items: 17,619,687.87$ -8.1% 16,199,000.00$ 5.3% 18,560,953.00$ 25.7% 22,141,688.00$ Project No: Hawaii HI STP SR11(1) AND HI STP SR11(2)
Project Name: NINOLE STREAM BRIDGE AND HILEA STREAM BRIDGE
CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount
15101-0000
Line A0020 ALL LPSM 2,300,000.00$ 2,300,000.00$ 1,450,000.00$ 1,012,000.00$ 2,069,553.00$
15201-0000
Line A0040 ALL LPSM 60,000.00$ 60,000.00$ 82,000.00$ 90,000.00$ 250,000.00$
15301-0000
Line A0060 ALL LPSM 375,000.00$ 375,000.00$ 360,000.00$ 175,000.00$ 700,000.00$
15401-0000
Line A0080 ALL LPSM 250,000.00$ 250,000.00$ 280,000.00$ 80,000.00$ 500,000.00$
15501-0000
Line A0100 ALL LPSM 86,842.87$ 86,842.87$ 60,000.00$ 5,000.00$ 40,000.00$
15705-0100
Line A0120 550 LNFT 45.00$ 24,750.00$ 22,000.00$ 38,500.00$ 16,500.00$
15706-0200
Line A0140 22 EACH 400.00$ 8,800.00$ 18,700.00$ 10,450.00$ 11,000.00$
15706-1600
Line A0160 2 EACH 8,000.00$ 16,000.00$ 25,200.00$ 30,000.00$ 20,000.00$
15802-0000
Line A0180 ALL LPSM 270,000.00$ 270,000.00$ 524,000.00$ 120,000.00$ 300,000.00$
20304-1000
Line A0200 ALL LPSM 240,000.00$ 240,000.00$ 210,000.00$ 400,000.00$ 950,000.00$
20401-0000
Line A0220 6,700 CUYD 110.00$ 737,000.00$ 435,500.00$ 1,005,000.00$ 938,000.00$
20435-2000
Line A0240 1,680 CUYD 300.00$ 504,000.00$ 352,800.00$ 739,200.00$ 168,000.00$
20720-0300
Line A0260 7,300 SQYD 20.00$ 146,000.00$ 62,050.00$ 73.00$ 14,600.00$
20801-0000
Line A0280 3,550 CUYD (CQ) 225.00$ 798,750.00$ 603,500.00$ 621,250.00$ 710,000.00$
20803-0000
Line A0300 10 CUYD 1,400.00$ 14,000.00$ 69,000.00$ 8,150.00$ 70,000.00$
20803-0000
Line A0320 185 CUYD (CQ) 1,500.00$ 277,500.00$ 555,000.00$ 175,750.00$ 129,500.00$
25101-2100
Line A0340 12 CUYD 350.00$ 4,200.00$ 14,400.00$ 8,700.00$ 3,600.00$
25101-2200
CONTRACTOR TESTING
280,000.00$ 80,000.00$ 500,000.00$
MOBILIZATION
CONSTRUCTION SURVEY AND STAKING
CONTRACTOR QUALITY CONTROL
STRUCTURAL BACKFILL(CLASS A CONCRETE)
PLACED RIPRAP, METHOD B, CLASS 1
PLACED RIPRAP, METHOD B, CLASS 2
SOIL EROSION CONTROL, CHECK DAM
SOIL EROSION CONTROL, STABILIZED CONSTRUCTION EXIT
WATERING FOR DUST CONTROL
REMOVAL OF STRUCTURES AND OBSTRUCTIONS
ROADWAY EXCAVATION
BACKFILL, GRANULAR
CONSTRUCTION SCHEDULE
SOIL EROSION CONTROL, SILT FENCE
REINFORCEMENT GEOSYNTHETIC, TYPE 3
STRUCTURE EXCAVATION
STRUCTURAL BACKFILL(SLOPE PAVING, CLASS A CONCRETE)
1,012,000.00$ 2,069,553.00$
Hawaiian Dredging CC, Inc. Kiewit Infrastructure West Co. Road & Highway Builders, LLC
82,000.00$
1,450,000.00$
60,000.00$ 5,000.00$ 40,000.00$
90,000.00$ 250,000.00$
360,000.00$ 175,000.00$ 700,000.00$
12,600.00$ 15,000.00$ 10,000.00$
850.00$ 475.00$ 500.00$
40.00$ 70.00$ 30.00$
210,000.00$ 400,000.00$ 950,000.00$
524,000.00$ 120,000.00$ 300,000.00$
210.00$ 440.00$ 100.00$
65.00$ 150.00$ 140.00$
170.00$ 175.00$ 200.00$
8.50$ 0.01$ 2.00$
3,000.00$ 950.00$ 700.00$
6,900.00$ 815.00$ 7,000.00$
1,200.00$ 725.00$ 300.00$
Engineer's Estimate
2/22/2018 Page 1 of 3
Schedule A Total of Bid Items: 17,619,687.87$ -8.1% 16,199,000.00$ 5.3% 18,560,953.00$ 25.7% 22,141,688.00$ Project No: Hawaii HI STP SR11(1) AND HI STP SR11(2)
Project Name: NINOLE STREAM BRIDGE AND HILEA STREAM BRIDGE
CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount
Hawaiian Dredging CC, Inc. Kiewit Infrastructure West Co. Road & Highway Builders, LLCEngineer's Estimate
Line A0360 65 CUYD 375.00$ 24,375.00$ 35,750.00$ 47,125.00$ 26,000.00$
25120-2100
Line A0380 530 LNFT 200.00$ 106,000.00$ 238,500.00$ 174,900.00$ 42,400.00$
26101-0000
Line A0400 1,580 SQFT 80.00$ 126,400.00$ 632,000.00$ 592,500.00$ 31,600.00$
30202-2000
Line A0420 1,400 TON 110.00$ 154,000.00$ 140,000.00$ 140,000.00$ 140,000.00$
40301-0000
Line A0440 800 TON 325.00$ 260,000.00$ 240,000.00$ 272,000.00$ 400,000.00$
55201-1500
Line A0460 800 CUYD (CQ) 2,550.00$ 2,040,000.00$ 1,520,000.00$ 2,000,000.00$ 4,400,000.00$
55201-1500
Line A0480 450 CUYD (CQ) 2,900.00$ 1,305,000.00$ 1,305,000.00$ 1,710,000.00$ 3,150,000.00$
55302-3200
Line A0500 728 LNFT (CQ) 1,000.00$ 728,000.00$ 1,223,040.00$ 1,237,600.00$ 1,456,000.00$
55302-3500
Line A0520 635 LNFT (CQ) 1,100.00$ 698,500.00$ 1,238,250.00$ 889,000.00$ 1,270,000.00$
55401-1000
Line A0540 409,615 LB (CQ) 4.00$ 1,638,460.00$ 675,864.75$ 819,230.00$ 1,228,845.00$
55401-2000
Line A0560 1,000 LB (CQ) 5.00$ 5,000.00$ 2,600.00$ 3,000.00$ 4,000.00$
55601-0600
Line A0580 507 LNFT (CQ) 970.00$ 491,790.00$ 456,300.00$ 608,400.00$ 152,100.00$
58401-0000
Line A0600 215 LB (CQ) 18.00$ 3,870.00$ 1,666.25$ 1,935.00$ 10,750.00$
61701-1500
Line A0620 650 LNFT 175.00$ 113,750.00$ 37,700.00$ 48,100.00$ 52,000.00$
61702-0800
Line A0640 8 EACH 5,000.00$ 40,000.00$ 50,800.00$ 58,400.00$ 40,000.00$
61707-0000
Line A0660 200 LNFT (CQ) 275.00$ 55,000.00$ 51,000.00$ 59,000.00$ 50,000.00$
62201-0200
Line A0680 100 HOUR 180.00$ 18,000.00$ 17,000.00$ 20,000.00$ 16,000.00$
62201-0900
Line A0700 100 HOUR 210.00$ 21,000.00$ 19,600.00$ 20,000.00$ 18,000.00$
GLASS FIBER REINFORCED POLYMER (GFRP) REINFORCING BARS
GUARDRAIL SYSTEM G4, TYPE 3, CLASS A STEEL POSTS
TERMINAL SECTION TYPE TANGENT
STRUCTURE TRANSITION RAILING
DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACITY
WHEEL LOADER, 2 CUBIC YARD MINIMUM RATED CAPACITY
PRECAST, PRESTRESSED CONCRETE GIRDER(WASHINGTON WF36G)
PRECAST, PRESTRESSED CONCRETE SLAB(48" (19" SOLID))
REINFORCING STEEL
REINFORCING STEEL, EPOXY COATED
BRIDGE RAILING, CONCRETE, BEAM RAIL(WITH PEDESTRIAN HANDRAIL)
RIPRAP DITCH, METHOD B, CLASS 1
REINFORCED SOIL SLOPE(ROCK FACED)
ROADWAY AGGREGATE, METHOD 2
ASPHALT CONCRETE PAVEMENT
STRUCTURAL CONCRETE, CLASS STATEDOT(CLASS D)
STRUCTURAL CONCRETE, CLASS STATEDOT(CLASS E)
550.00$ 725.00$ 400.00$
400.00$ 375.00$ 20.00$
450.00$ 330.00$ 80.00$
300.00$ 340.00$ 500.00$
100.00$ 100.00$ 100.00$
2,900.00$ 3,800.00$ 7,000.00$
1,900.00$ 2,500.00$ 5,500.00$
1,950.00$ 1,400.00$ 2,000.00$
1,680.00$ 1,700.00$ 2,000.00$
2.60$ 3.00$ 4.00$
1.65$ 2.00$ 3.00$
7.75$ 9.00$ 50.00$
900.00$ 1,200.00$ 300.00$
6,350.00$ 7,300.00$ 5,000.00$
58.00$ 74.00$ 80.00$
170.00$ 200.00$ 160.00$
255.00$ 295.00$ 250.00$
196.00$ 200.00$ 180.00$
2/22/2018 Page 2 of 3
Schedule A Total of Bid Items: 17,619,687.87$ -8.1% 16,199,000.00$ 5.3% 18,560,953.00$ 25.7% 22,141,688.00$ Project No: Hawaii HI STP SR11(1) AND HI STP SR11(2)
Project Name: NINOLE STREAM BRIDGE AND HILEA STREAM BRIDGE
CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount
Hawaiian Dredging CC, Inc. Kiewit Infrastructure West Co. Road & Highway Builders, LLCEngineer's Estimate
62201-2850
Line A0720 100 HOUR 230.00$ 23,000.00$ 24,000.00$ 30,000.00$ 19,000.00$
62201-3000
Line A0740 100 HOUR 285.00$ 28,500.00$ 40,500.00$ 20,000.00$ 20,000.00$
62301-0000
Line A0760 180 HOUR 120.00$ 21,600.00$ 19,800.00$ 27,000.00$ 14,400.00$
62302-1000
Line A0780 140 HOUR 250.00$ 35,000.00$ 21,000.00$ 28,000.00$ 22,400.00$
62302-1100
Line A0800 100 HOUR 250.00$ 25,000.00$ 22,700.00$ 20,000.00$ 20,000.00$
62510-1000
Line A0820 1.4 ACRE 20,000.00$ 28,000.00$ 15,260.00$ 37,800.00$ 2,800.00$
62515-1000
Line A0840 1.4 ACRE 12,000.00$ 16,800.00$ 15,260.00$ 37,800.00$ 2,800.00$
62902-1100
Line A0860 1.4 ACRE 40,000.00$ 56,000.00$ 39,620.00$ 49,000.00$ 2,800.00$
63301-0000
Line A0880 26 EACH 900.00$ 23,400.00$ 8,060.00$ 14,040.00$ 8,840.00$
63401-1500
Line A0900 2,900 LNFT 6.00$ 17,400.00$ 24,650.00$ 11,600.00$ 8,700.00$
63406-0000
Line A0920 150 EACH 20.00$ 3,000.00$ 3,000.00$ 3,450.00$ 1,500.00$
63501-0000
Line A0940 ALL LPSM 325,000.00$ 325,000.00$ 400,000.00$ 40,000.00$ 1,600,000.00$
63701-0000
Line A0960 1 EACH 300,000.00$ 300,000.00$ 75,000.00$ 40,000.00$ 40,000.00$
65001-1000
Line A0980 ALL LPSM 2,775,000.00$ 2,775,000.00$ 2,480,929.00$ 4,982,000.00$ 1,000,000.00$
HYDRAULIC EXCAVATOR
GENERAL LABOR
SPECIAL LABOR, HIRED TECHNICAL SERVICES
SPECIAL LABOR, HIRED SURVEY SERVICES
SEEDING, DRY METHOD
MULCHING, DRY METHOD
MOTOR GRADER, 12 FOOT MINIMUM BLADE
CONSTRUCT AND MAINTAIN DIVERSION(ROADWAY BYPASS)
ROLLED EROSION CONTROL PRODUCT, TYPE 4
SIGN SYSTEM
PAVEMENT MARKINGS, TYPE H, SOLID
RAISED PAVEMENT MARKER
TEMPORARY TRAFFIC CONTROL
FIELD OFFICE
240.00$ 300.00$ 190.00$
110.00$ 150.00$ 80.00$
405.00$ 200.00$ 200.00$
227.00$ 200.00$ 200.00$
150.00$ 200.00$ 160.00$
10,900.00$ 27,000.00$ 2,000.00$
10,900.00$ 27,000.00$ 2,000.00$
310.00$ 540.00$ 340.00$
28,300.00$ 35,000.00$ 2,000.00$
20.00$ 23.00$ 10.00$
8.50$ 4.00$ 3.00$
75,000.00$ 40,000.00$ 40,000.00$
400,000.00$ 40,000.00$ 1,600,000.00$
2,480,929.00$ 4,982,000.00$ 1,000,000.00$
2/22/2018 Page 3 of 3