Bid_Tabs_X.pdf
PDF 19 KB Posted
- Attached to
- TX FTNP PAIS 10(1) MAIN PARK ROAD Federal contract opportunity
- Solicitation number
- DTFH6816B00015
About this file
Option X
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid_Tabs_A.pdf | ||
| Bid_Opening_Summary.pdf | ||
| A002.pdf | ||
| 08_24_2016.pdf | ||
| 08_24_2016.pdf | ||
| 08_19_2016.pdf | ||
| 08_09_2016.pdf | ||
| A001.pdf | ||
| Plans.pdf | ||
| Appendix_A.pdf | ||
| Appendix_C.pdf | ||
| Appendix_D.pdf | ||
| Appendix_B.pdf | ||
| Pavements_Report_.pdf | ||
| DTFH6816B00015.pdf | ||
| Pavements_Report_Addendum.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
T A B U L A T I O N O F B I D S Option X
Project No : TX FTNP PAIS 10(1)
Project Name : Main Park Road Solcitation No:
State : TX County : Kleberg Federal Location : Padre Island National Seashore
Opened at:
Opened by:
Date:
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed:
Title:
Date:
Contract Awarded to: Award Date:
Contract Number: Data is Public
Contractor Comment Bid Amount Responsive
Engineer's Estimate 777,910.00$
Bay, Ltd. 683,933.15$
Haas-Anderson Constr 656,213.00$
Bay, Ltd.
$ 656,213.00
DTFH6817C00001
$ 683,933.15
9/16/2016 FHWA Confidential Page 1 of 1
ADDITIONAL LINES NEEDED AT BOTTOM T A B U L A T I O N O F B I
'Bid Tabs'!$F$9:$K$127012 'Bid Tabs'!$H$7:$K$7 'Bid Tabs'!$H$3:$K$3 2 1
Option X Total of Bid Items: 777,910.00$ -12.1% 683,933.15$ -15.6% 656,213.00$ Project No: TX FTNP PAIS 10(1)
Project Name: Main Park Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount Unit Price Amount Unit Price Amount
1 15101-0000
1 Line X0020 ALL LPSM 57,194.00$ 57,194.00$ 62,500.00$ 20,000.00$
2 15210-3000
2 Line X0040 78.080 STA 75.00$ 5,856.00$ 1,561.60$ 15,616.00$
3 15215-3000
3 Line X0060 2 EACH 1,500.00$ 3,000.00$ 300.00$ 4,000.00$
4 15301-0000
4 Line X0080 ALL LPSM 8,750.00$ 8,750.00$ 15,200.00$ 10,000.00$
5 15401-0000
5 Line X0100 ALL LPSM 26,250.00$ 26,250.00$ 30,400.00$ 20,000.00$
6 15501-0000
6 Line X0120 ALL LPSM 5,000.00$ 5,000.00$ 1,000.00$ 3,000.00$
7 15705-1400
7 Line X0140 330 LNFT 16.00$ 5,280.00$ 4,620.00$ 4,620.00$
8 15802-0000
8 Line X0160 ALL LPSM 10,000.00$ 10,000.00$ 8,300.00$ 8,000.00$
9 20101-0000
9 Line X0180 0.2 ACRE 3,500.00$ 700.00$ 2,205.53$ 2,000.00$
10 20304-1000
10 Line X0200 ALL LPSM 1,000.00$ 1,000.00$ 3,600.00$ 858.00$
11 20401-0000
11 Line X0220 70 CUYD 20.00$ 1,400.00$ 1,120.00$ 5,810.00$
12 30306-2500
12 Line X0240 18,000 SQYD 4.00$ 72,000.00$ 68,400.00$ 86,400.00$
13 30802-2000
13 Line X0260 560 TON 45.00$ 25,200.00$ 31,360.00$ 33,600.00$
14 40101-5600
14 Line X0280 3,000 TON 140.00$ 420,000.00$ 330,000.00$ 318,000.00$
15 40920-1000
15 Line X0300 8 TON 800.00$ 6,400.00$ 4,400.00$ 3,112.00$
16 41103-0000
16 Line X0320 18,000 SQYD 1.50$ 27,000.00$ 10,800.00$ 29,700.00$
17 41105-0000
17 Line X0340 30 TON 40.00$ 1,200.00$ 4,800.00$ 5,730.00$
18 41201-1000
18 Line X0360 8 TON 800.00$ 6,400.00$ 6,720.00$ 4,584.00$
19 60201-0800
19 Line X0380 40 LNFT 140.00$ 5,600.00$ 6,800.00$ 4,880.00$
20 60210-0800
20 Line X0400 2 EACH 500.00$ 1,000.00$ 4,400.00$ 3,640.00$
21 60413-0000
21 Line X0420 45 LNFT 225.00$ 10,125.00$ 25,650.00$ 17,955.00$
22 62201-0450
22 Line X0440 10 HOUR 100.00$ 1,000.00$ 460.00$ 580.00$
23 62201-0900
23 Line X0460 10 HOUR 115.00$ 1,150.00$ 710.00$ 760.00$
24 62201-2750
24 Line X0480 10 HOUR 150.00$ 1,500.00$ 1,200.00$ 1,160.00$
25 62301-0000
Engineer's Estimate
120.00$ 116.00$
71.00$ 76.00$
46.00$ 58.00$
570.00$ 399.00$
2,200.00$ 1,820.00$
170.00$ 122.00$
840.00$ 573.00$
160.00$ 191.00$
0.60$ 1.65$
550.00$ 389.00$
110.00$ 106.00$
56.00$ 60.00$
3.80$ 4.80$
16.00$ 83.00$
3,600.00$ 858.00$
11,027.65$ 10,000.00$
8,300.00$ 8,000.00$
14.00$ 14.00$
1,000.00$ 3,000.00$
30,400.00$ 20,000.00$
200.00$
150.00$ 2,000.00$
Bay, Ltd. Haas-Anderson Construction, Ltd.
20.00$
62,500.00$ 20,000.00$
MOBILIZATION
CENTERLINE, VERIFICATION AND STAKING
SURVEY AND STAKING, DRAINAGE STRUCTURE
PRIME COAT
BLOTTER
TACK COAT GRADE CSS-1, CSS-1H, SS-1, OR SS-1H
SOIL EROSION CONTROL, SEDIMENT LOG
WATERING FOR DUST CONTROL
CLEARING AND GRUBBING
REMOVAL OF STRUCTURES AND OBSTRUCTIONS
ROADWAY EXCAVATION
PULVERIZING, 5-INCH DEPTH
GENERAL LABOR
24-INCH PIPE CULVERT
END SECTION FOR 24-INCH PIPE CULVERT
TRENCH DRAIN
BACKHOE LOADER, 4 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 18-INCH WIDTH
WHEEL LOADER, 2 CUBIC YARD MINIMUM RATED CAPACITY
MOTOR GRADER
CONTRACTOR TESTING
CONSTRUCTION SCHEDULE
ROADWAY AGGREGATE, METHOD 2
SUPERPAVE PAVEMENT, 1/2-INCH OR 3/4-INCH NOMINAL MAXIMUM SIZE AGGREGATE, 0.3 TO <3 MILLION ESAL
FOG SEAL, EMULSIFIED ASPHALT GRADE CSS-1 OR CSS-1H, SS-1 OR SS-1H
CONTRACTOR QUALITY CONTROL
15,200.00$ 10,000.00$
9/16/2016 Page 1 of 2
Option X Total of Bid Items: 777,910.00$ -12.1% 683,933.15$ -15.6% 656,213.00$ Project No: TX FTNP PAIS 10(1)
Project Name: Main Park Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount Unit Price Amount Unit Price Amount
Engineer's Estimate Bay, Ltd. Haas-Anderson Construction, Ltd.
25 Line X0500 20 HOUR 35.00$ 700.00$ 980.00$ 680.00$
26 62302-1000
26 Line X0520 5 HOUR 140.00$ 700.00$ 1,400.00$ 1,190.00$
27 62302-1100
27 Line X0540 5 HOUR 140.00$ 700.00$ 850.00$ 1,490.00$
28 62510-2000
28 Line X0560 0.1 ACRE 2,400.00$ 240.00$ 3,164.51$ 1,600.00$
29 62515-2000
29 Line X0580 0.1 ACRE 3,000.00$ 300.00$ 3,164.51$ 1,600.00$
30 63301-0000
30 Line X0600 10 EACH 400.00$ 4,000.00$ 3,300.00$ 3,280.00$
31 63308-2000
31 Line X0620 6 EACH 90.00$ 540.00$ 438.00$ 426.00$
32 63404-0200
32 Line X0640 155 GAL 55.00$ 8,525.00$ 8,990.00$ 8,835.00$
33 63405-0050
33 Line X0660 1 EACH 100.00$ 100.00$ 790.00$ 774.00$
34 63502-0700
34 Line X0680 50 EACH 35.00$ 1,750.00$ 265.00$ 250.00$
35 63502-1300
35 Line X0700 100 EACH 100.00$ 10,000.00$ 790.00$ 775.00$
36 63502-1600
36 Line X0720 4 EACH 75.00$ 300.00$ 44.00$ 48.00$
37 63505-1000
37 Line X0740 1.5 MILE 2,500.00$ 3,750.00$ 15,750.00$ 10,500.00$
38 63506-0500
38 Line X0760 320 HOUR 35.00$ 11,200.00$ 8,000.00$ 10,880.00$
39 63506-0600
39 Line X0780 160 HOUR 90.00$ 14,400.00$ 5,600.00$ 6,080.00$
40 63602-6000
40 Line X0800 1 EACH 17,700.00$ 17,700.00$ 3,900.00$ 3,800.00$ 3,900.00$ 3,800.00$
35.00$ 38.00$
25.00$ 34.00$
10,500.00$ 7,000.00$
11.00$ 12.00$
7.90$ 7.75$
5.30$ 5.00$
790.00$ 774.00$
58.00$ 57.00$
73.00$ 71.00$
330.00$ 328.00$
31,645.10$ 16,000.00$
31,645.10$ 16,000.00$
170.00$ 298.00$
280.00$ 238.00$
49.00$ 34.00$
SPECIAL LABOR, HIRED TECHNICAL SERVICES
SPECIAL LABOR, HIRED SURVEY SERVICES
SEEDING, HYDRAULIC METHOD
MULCHING, HYDRAULIC METHOD
SIGN SYSTEM
TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS
TEMPORARY TRAFFIC CONTROL, FLAGGER
TEMPORARY TRAFFIC CONTROL, PILOT CAR
SYSTEM INSTALLATION, TRAFFIC DETECTOR SYSTEM
OBJECT MARKER, TYPE 2
PAVEMENT MARKINGS, TYPE B
PAVEMENT MARKINGS, SYMBOLS
TEMPORARY TRAFFIC CONTROL, CONE
TEMPORARY TRAFFIC CONTROL, DRUM
TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B