Q-A_11_4_15.pdf
PDF 112 KB Posted
- Attached to
- NV FTNP LAKE 114(1), Katherine Lake
- Solicitation number
- DTFH6815B00021
About this file
Q A for the project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid_Tabs_NV_FTNP_Lake_114(1)_Sch_A.pdf | ||
| Bid_Tabs_NV_FTNP_Lake_114(1)_Opt_X.pdf | ||
| NV_FTNP_LAKE_114(1)_Bid_Summary_11_19_15.xlsx | XLSX spreadsheet | |
| A001.pdf | ||
| NV_FTNP_PRA-LAKE_114(1)_Final_Geotech_Report_(100__Final).pdf | ||
| Hydraulics_Memo_LAKE114_1__Overall.pdf | ||
| IFB_DTFH6815B00021.pdf | ||
| Plans.pdf | ||
| Cross_Section.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DTFH68‐15‐B‐00021
Katherine Access Road
11/4/15
QUESTION #1
The project has a Nevada project number and is listed in the State of Nevada on the 2nd page of the solicitation but accounts for an Arizona wage decision and makes Arizona DEQ references. From the plan cover, it is clearly shown on the Arizona side of the borders. That being said, is the 402 reference to
HVEEM appropriate as it is not a locally approved product? We recommend this be changed to a
Marshall mix.
Response:
The HVEEM is appropriate as shown in the plans and SCRs.
QUESTION #2
Since this invitation to bid has an interim completion incentive/disincentive, has CFL established an award date for this project?
Response:
It is anticipated that award will be made by December 11, 2015. The Notice to Proceed (NTP) is dependent on the contractors bonds and therefore no anticipated NTP can be given.