Bid Tabs Option X
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid_Tabs_NV_FTNP_Lake_114(1)_Sch_A.pdf | ||
| NV_FTNP_LAKE_114(1)_Bid_Summary_11_19_15.xlsx | XLSX spreadsheet | |
| A001.pdf | ||
| NV_FTNP_PRA-LAKE_114(1)_Final_Geotech_Report_(100__Final).pdf | ||
| Hydraulics_Memo_LAKE114_1__Overall.pdf | ||
| Q-A_11_4_15.pdf | ||
| IFB_DTFH6815B00021.pdf | ||
| Plans.pdf | ||
| Cross_Section.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
T A B U L A T I O N O F B I D S Option X Total of Bid Items: 1,115,633.00$ -2.9% 1,082,907.00$
Project No: NV FTNP LAKE 114(1)
Project Name: Katherine Access Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount Unit Price Amount
15101-0000 Line X0020 ALL LPSM 130,000.00$ 130,000.00$ 75,000.00$
15206-0000 Line X0040 43.000 STA 110.00$ 4,730.00$ 3,225.00$
15210-3000 Line X0060 43.000 STA 120.00$ 5,160.00$ 215,000.00$
15215-3000 Line X0080 4 EACH 980.00$ 3,920.00$ 1,600.00$
15216-2000 Line X0100 43.000 STA 120.00$ 5,160.00$ 2,795.00$
15301-0000 Line X0120 ALL LPSM 53,000.00$ 53,000.00$ 11,000.00$
15401-0000 Line X0140 ALL LPSM 53,000.00$ 53,000.00$ 22,000.00$
15501-0000 Line X0160 ALL LPSM 27,000.00$ 27,000.00$ 3,000.00$
15705-0100 Line X0180 3,000 LNFT 5.00$ 15,000.00$ 12,000.00$
15705-1400 Line X0200 2,700 LNFT 11.00$ 29,700.00$ 10,800.00$
15706-0400 Line X0220 5 EACH 3,000.00$ 15,000.00$ 6,000.00$
15706-1600 Line X0240 2 EACH 2,200.00$ 4,400.00$ 7,000.00$
15802-0000 Line X0260 ALL LPSM 10,000.00$ 10,000.00$ 8,000.00$
SURVEY AND STAKING, DRAINAGE STRUCTURE
400.00$
MOBILIZATION
SLOPE, REFERENCE, AND CLEARING AND GRUBBING STAKE
CENTERLINE, VERIFICATION AND STAKING
CONTRACTOR TESTING
CONSTRUCTION SCHEDULE
SOIL EROSION CONTROL, SILT FENCE
SOIL EROSION CONTROL, SEDIMENT LOG
SOIL EROSION CONTROL, SEDIMENT TRAP
SOIL EROSION CONTROL, STABILIZED CONSTRUCTION ENTRANCE
SURVEY AND STAKING, GRADE FINISHING STAKES
CONTRACTOR QUALITY CONTROL
WATERING FOR DUST CONTROL
SWP
75.00$
75,000.00$
65.00$
5,000.00$
3,000.00$
22,000.00$
11,000.00$
4.00$
4.00$
3,500.00$
1,200.00$
8,000.00$
Engineer's Estimate
12/2/2015 Page 1 of 20
Project No: NV FTNP LAKE 114(1)
Project Name: Katherine Access Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount Unit Price Amount
SWPEngineer's Estimate
20103-0000 Line X0280 17,000 SQYD 2.00$ 34,000.00$ 11,900.00$
20301-0700 Line X0300 16 EACH 38.00$ 608.00$ 1,360.00$
20301-2400 Line X0320 6 EACH 200.00$ 1,200.00$ 1,170.00$
20420-0000 Line X0340 7,300 CUYD -$ -$ 51,100.00$
25101-3000 Line X0360 220 CUYD 90.00$ 19,800.00$ 28,600.00$
30306-3000 Line X0380 16,500 SQYD 2.75$ 45,375.00$ 49,500.00$
30801-2000 Line X0400 1,050 CUYD 15.00$ 15,750.00$ 42,000.00$
40201-4700 Line X0420 2,700 TON 90.00$ 243,000.00$ 216,000.00$
40205-3000 Line X0440 28 TON 141.00$ 3,948.00$ 4,900.00$
40501-0000 Line X0460 490 TON 104.00$ 50,960.00$ 51,450.00$
40505-3000 Line X0480 6 TON 185.00$ 1,110.00$ 1,050.00$
40961-0000 Line X0500 2,800 SQYD 1.00$ 2,800.00$ 1,680.00$
41103-0000 Line X0520 14,500 SQYD 0.75$ 10,875.00$ 15,950.00$
REMOVAL OF SIGN
EMBANKMENT CONSTRUCTION
PLACED RIPRAP, CLASS 3
BLOTTER
PRIME COAT
PULVERIZING, 6-INCH DEPTH
ROADWAY AGGREGATE, METHOD 2
HOT ASPHALT CONCRETE PAVEMENT, HVEEM TEST, CLASS B, GRADING C OR E
ANTISTRIP ADDITIVE, TYPE 3
OPEN-GRADED ASPHALT FRICTION COURSE
ANTISTRIP ADDITIVE, TYPE 3
CLEARING AND GRUBBING
REMOVAL OF DELINEATOR
0.70$
195.00$
85.00$
130.00$
7.00$
40.00$
3.00$
175.00$
80.00$
175.00$
105.00$
1.10$
0.60$
12/2/2015 Page 2 of 20
Project No: NV FTNP LAKE 114(1)
Project Name: Katherine Access Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount Unit Price Amount
SWPEngineer's Estimate
41201-1000 Line X0540 7 TON 610.00$ 4,270.00$ 3,745.00$
60201-1000 Line X0560 50 LNFT 164.00$ 8,200.00$ 5,000.00$
60210-1000 Line X0580 5 EACH 450.00$ 2,250.00$ 4,800.00$
60704-0000 Line X0600 2 EACH (CQ) 1,400.00$ 2,800.00$ 1,600.00$
60902-1000 Line X0620 680 LNFT 20.00$ 13,600.00$ 15,980.00$
61701-1800 Line X0640 1,690 LNFT 30.00$ 50,700.00$ 30,420.00$
61702-0800 Line X0660 14 EACH 2,700.00$ 37,800.00$ 37,100.00$
62201-0200 Line X0680 20 HOUR 110.00$ 2,200.00$ 1,920.00$
62201-0550 Line X0700 20 HOUR 120.00$ 2,400.00$ 1,400.00$
62201-0900 Line X0720 20 HOUR 130.00$ 2,600.00$ 2,000.00$
62201-1150 Line X0740 20 HOUR 120.00$ 2,400.00$ 3,500.00$
62201-1300 Line X0760 20 HOUR 160.00$ 3,200.00$ 3,800.00$
62201-2750 Line X0780 20 HOUR 175.00$ 3,500.00$ 2,560.00$
CLEANING CULVERT IN PLACE
BULLDOZER, 70HP MINIMUM FLYWHEEL POWER
BULLDOZER, 160HP MINIMUM FLYWHEEL POWER
MOTOR GRADER
CURB AND GUTTER, CONCRETE, 12-INCH DEPTH
GUARDRAIL SYSTEM G4, TYPE 4, CLASS A STEEL POSTS
TERMINAL SECTION TYPE TANGENT
DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACITY
BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 24-INCH WIDTH
WHEEL LOADER, 2 CUBIC YARD MINIMUM RATED CAPACITY
TACK COAT GRADE CSS-1, CSS-1H, SS-1, OR SS-1H
36-INCH PIPE CULVERT
END SECTION FOR 36-INCH PIPE CULVERT
100.00$
535.00$
800.00$
960.00$
18.00$
23.50$
96.00$
2,650.00$
100.00$
70.00$
190.00$
175.00$
128.00$
12/2/2015 Page 3 of 20
Project No: NV FTNP LAKE 114(1)
Project Name: Katherine Access Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount Unit Price Amount
SWPEngineer's Estimate
62201-3350 Line X0800 20 HOUR 190.00$ 3,800.00$ 2,560.00$
62202-1000 Line X0820 ALL LPSM 25,000.00$ 25,000.00$ 5,500.00$
62301-0000 Line X0840 40 HOUR 50.00$ 2,000.00$ 740.00$
62302-1000 Line X0860 40 HOUR 135.00$ 5,400.00$ 3,800.00$
62302-1100 Line X0880 40 HOUR 165.00$ 6,600.00$ 6,000.00$
63301-0000 Line X0900 6 EACH 500.00$ 3,000.00$ 2,190.00$
63308-3000 Line X0920 10 EACH 175.00$ 1,750.00$ 1,600.00$
63309-0100 Line X0940 46 EACH 27.00$ 1,242.00$ 1,978.00$
63313-0000 Line X0960 4,300 LNFT 1.00$ 4,300.00$ 688.00$
63316-1000 Line X0980 2 EACH 300.00$ 600.00$ 380.00$
63403-0400 Line X1000 100 SQFT 5.00$ 500.00$ 450.00$
63404-0400 Line X1020 140 GAL 84.00$ 11,760.00$ 8,960.00$
63405-0050 Line X1040 6 EACH 130.00$ 780.00$ 576.00$
HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY
MATERIALS TRANSFER VEHICLE
GENERAL LABOR
REMOVE AND RESET SIGN
PAVEMENT MARKINGS, TYPE D
PAVEMENT MARKINGS, TYPE D
PAVEMENT MARKINGS, SYMBOLS
SPECIAL LABOR, HIRED TECHNICAL SERVICES
SPECIAL LABOR, HIRED SURVEY SERVICES
SIGN SYSTEM
OBJECT MARKER, TYPE 3
DELINEATOR, TYPE 1
RUMBLE STRIP
128.00$
18.50$
5,500.00$
150.00$
95.00$
160.00$
365.00$
0.16$
43.00$
4.50$
190.00$
96.00$
64.00$
12/2/2015 Page 4 of 20
Project No: NV FTNP LAKE 114(1)
Project Name: Katherine Access Road CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount Unit Price Amount
SWPEngineer's Estimate
63501-1000 Line X1060 ALL LPSM 15,000.00$ 15,000.00$ 26,000.00$
63502-0700 Line X1080 140 EACH 27.00$ 3,780.00$ 1,120.00$
63502-1300 Line X1100 170 EACH 118.00$ 20,060.00$ 2,380.00$
63502-1700 Line X1120 10 EACH 68.00$ 680.00$ 270.00$
63503-0300 Line X1140 20 LNFT 64.00$ 1,280.00$ 540.00$
63504-1000 Line X1160 385 SQFT 25.00$ 9,625.00$ 2,310.00$
63505-1000 Line X1180 1.6 MILE 1,600.00$ 2,560.00$ 1,960.00$
63506-0500 Line X1200 1,000 HOUR 52.00$ 52,000.00$ 30,000.00$
63506-0600 Line X1220 300 HOUR 75.00$ 22,500.00$ 15,000.00$
TEMPORARY TRAFFIC CONTROL, TRAFFIC AND SAFETY SUPERVISOR
TEMPORARY TRAFFIC CONTROL, CONE
TEMPORARY TRAFFIC CONTROL, PILOT CAR
TEMPORARY TRAFFIC CONTROL, DRUM
TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE C
TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS
TEMPORARY TRAFFIC CONTROL, FLAGGER
8.00$
26,000.00$
27.00$
14.00$
6.00$
27.00$
50.00$
30.00$
1,225.00$
12/2/2015 Page 5 of 20
Option X Total of Bid Items:
Project No: NV FTNP LAKE 114(1)
Project Name: Katherine Access Road CQ = "Contract Quantity"
Item No. Quantity Unit
15101-0000 Line X0020 ALL LPSM
15206-0000 Line X0040 43.000 STA
15210-3000 Line X0060 43.000 STA
15215-3000 Line X0080 4 EACH
15216-2000 Line X0100 43.000 STA
15301-0000 Line X0120 ALL LPSM
15401-0000 Line X0140 ALL LPSM
15501-0000 Line X0160 ALL LPSM
15705-0100 Line X0180 3,000 LNFT
15705-1400 Line X0200 2,700 LNFT
15706-0400 Line X0220 5 EACH
15706-1600 Line X0240 2 EACH
15802-0000 Line X0260 ALL LPSM
SURVEY AND STAKING, DRAINAGE STRUCTURE
MOBILIZATION
SLOPE, REFERENCE, AND CLEARING AND GRUBB
CENTERLINE, VERIFICATION AND STAKING
CONTRACTOR TESTING
CONSTRUCTION SCHEDULE
SOIL EROSION CONTROL, SILT FENCE
SOIL EROSION CONTROL, SEDIMENT LOG
SOIL EROSION CONTROL, SEDIMENT TRAP
SOIL EROSION CONTROL, STABILIZED CONSTR
SURVEY AND STAKING, GRADE FINISHING STAK
CONTRACTOR QUALITY CONTROL
WATERING FOR DUST CONTROL
-11.3% 989,666.00$ 14.8% 1,280,810.92$
Unit Price Amount Unit Price Amount
60,000.00$ 48,946.53$
3,010.00$ 14,063.58$
1,892.00$ 4,687.86$
1,500.00$ 1,090.20$
2,795.00$ 7,031.79$
35,000.00$ 29,419.05$
11,000.00$ 21,804.00$
1,500.00$ 2,180.40$
11,400.00$ 13,080.00$
9,126.00$ 8,829.00$
29,000.00$ 2,725.50$
7,000.00$ 6,541.20$
4,500.00$ 10,902.00$
375.00$ 272.55$
60,000.00$ 48,946.53$
Fann Contracting, Inc. Interstate Rock Products
65.00$ 163.53$
70.00$ 327.06$
44.00$ 109.02$
1,500.00$ 2,180.40$
11,000.00$ 21,804.00$
35,000.00$ 29,419.05$
3.38$ 3.27$
3.80$ 4.36$
3,500.00$ 3,270.60$
5,800.00$ 545.10$
4,500.00$ 10,902.00$
12/2/2015 Page 6 of 20
Project No: NV FTNP LAKE 114(1)
Project Name: Katherine Access Road CQ = "Contract Quantity"
Item No. Quantity Unit
20103-0000 Line X0280 17,000 SQYD
20301-0700 Line X0300 16 EACH
20301-2400 Line X0320 6 EACH
20420-0000 Line X0340 7,300 CUYD
25101-3000 Line X0360 220 CUYD
30306-3000 Line X0380 16,500 SQYD
30801-2000 Line X0400 1,050 CUYD
40201-4700 Line X0420 2,700 TON
40205-3000 Line X0440 28 TON
40501-0000 Line X0460 490 TON
40505-3000 Line X0480 6 TON
40961-0000 Line X0500 2,800 SQYD
41103-0000 Line X0520 14,500 SQYD
REMOVAL OF SIGN
EMBANKMENT CONSTRUCTION
PLACED RIPRAP, CLASS 3
BLOTTER
PRIME COAT
PULVERIZING, 6-INCH DEPTH
ROADWAY AGGREGATE, METHOD 2
HOT ASPHALT CONCRETE PAVEMENT, HVEEM TE
ANTISTRIP ADDITIVE, TYPE 3
OPEN-GRADED ASPHALT FRICTION COURSE
ANTISTRIP ADDITIVE, TYPE 3
CLEARING AND GRUBBING
REMOVAL OF DELINEATOR
-11.3% 989,666.00$ 14.8% 1,280,810.92$
Unit Price Amount Unit Price Amount
Fann Contracting, Inc. Interstate Rock Products
3,400.00$ 3,740.00$
288.00$ 436.16$
360.00$ 163.56$
109,500.00$ 151,548.00$
20,900.00$ 21,106.80$
82,500.00$ 18,315.00$
44,100.00$ 27,468.00$
221,400.00$ 235,494.00$
5,040.00$ 4,426.24$
51,450.00$ 58,359.00$
1,080.00$ 948.48$
980.00$ 336.00$
13,050.00$ 5,220.00$
0.20$ 0.22$
60.00$ 27.26$
18.00$ 27.26$
95.00$ 95.94$
15.00$ 20.76$
42.00$ 26.16$
5.00$ 1.11$
180.00$ 158.08$
82.00$ 87.22$
180.00$ 158.08$
105.00$ 119.10$
0.90$ 0.36$
0.35$ 0.12$
12/2/2015 Page 7 of 20
Project No: NV FTNP LAKE 114(1)
Project Name: Katherine Access Road CQ = "Contract Quantity"
Item No. Quantity Unit
41201-1000 Line X0540 7 TON
60201-1000 Line X0560 50 LNFT
60210-1000 Line X0580 5 EACH
60704-0000 Line X0600 2 EACH (CQ)
60902-1000 Line X0620 680 LNFT
61701-1800 Line X0640 1,690 LNFT
61702-0800 Line X0660 14 EACH
62201-0200 Line X0680 20 HOUR
62201-0550 Line X0700 20 HOUR
62201-0900 Line X0720 20 HOUR
62201-1150 Line X0740 20 HOUR
62201-1300 Line X0760 20 HOUR
62201-2750 Line X0780 20 HOUR
CLEANING CULVERT IN PLACE
BULLDOZER, 70HP MINIMUM FLYWHEEL POWER
BULLDOZER, 160HP MINIMUM FLYWHEEL POWE
MOTOR GRADER
CURB AND GUTTER, CONCRETE, 12-INCH DEPTH
GUARDRAIL SYSTEM G4, TYPE 4, CLASS A STEE
TERMINAL SECTION TYPE TANGENT
DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACIT
BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RA
WHEEL LOADER, 2 CUBIC YARD MINIMUM RATE
TACK COAT GRADE CSS-1, CSS-1H, SS-1, OR S
36-INCH PIPE CULVERT
END SECTION FOR 36-INCH PIPE CULVERT
-11.3% 989,666.00$ 14.8% 1,280,810.92$
Unit Price Amount Unit Price Amount
Fann Contracting, Inc. Interstate Rock Products
6,860.00$ 4,197.27$
6,200.00$ 6,432.00$
3,940.00$ 8,176.50$
1,230.00$ 763.14$
17,000.00$ 13,341.60$
37,180.00$ 69,374.50$
46,200.00$ 73,032.54$
1,900.00$ 2,834.60$
1,700.00$ 2,398.40$
1,900.00$ 5,015.00$
1,600.00$ 5,287.40$
2,300.00$ 7,140.80$
2,400.00$ 6,541.20$
124.00$ 128.64$
980.00$ 599.61$
615.00$ 381.57$
788.00$ 1,635.30$
22.00$ 41.05$
25.00$ 19.62$
95.00$ 141.73$
3,300.00$ 5,216.61$
95.00$ 250.75$
85.00$ 119.92$
115.00$ 357.04$
80.00$ 264.37$
120.00$ 327.06$
12/2/2015 Page 8 of 20
Project No: NV FTNP LAKE 114(1)
Project Name: Katherine Access Road CQ = "Contract Quantity"
Item No. Quantity Unit
62201-3350 Line X0800 20 HOUR
62202-1000 Line X0820 ALL LPSM
62301-0000 Line X0840 40 HOUR
62302-1000 Line X0860 40 HOUR
62302-1100 Line X0880 40 HOUR
63301-0000 Line X0900 6 EACH
63308-3000 Line X0920 10 EACH
63309-0100 Line X0940 46 EACH
63313-0000 Line X0960 4,300 LNFT
63316-1000 Line X0980 2 EACH
63403-0400 Line X1000 100 SQFT
63404-0400 Line X1020 140 GAL
63405-0050 Line X1040 6 EACH
HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMU
MATERIALS TRANSFER VEHICLE
GENERAL LABOR
REMOVE AND RESET SIGN
PAVEMENT MARKINGS, TYPE D
PAVEMENT MARKINGS, TYPE D
PAVEMENT MARKINGS, SYMBOLS
SPECIAL LABOR, HIRED TECHNICAL SERVICES
SPECIAL LABOR, HIRED SURVEY SERVICES
SIGN SYSTEM
OBJECT MARKER, TYPE 3
DELINEATOR, TYPE 1
RUMBLE STRIP
-11.3% 989,666.00$ 14.8% 1,280,810.92$
Unit Price Amount Unit Price Amount
Fann Contracting, Inc. Interstate Rock Products
2,500.00$ 6,323.20$
4,000.00$ 21,804.00$
1,280.00$ 3,706.80$
2,600.00$ 5,232.80$
5,600.00$ 7,849.60$
4,500.00$ 35,976.60$
1,500.00$ 2,125.90$
1,932.00$ 6,519.58$
1,075.00$ 1,505.00$
1,200.00$ 2,725.50$
400.00$ 2,644.00$
8,400.00$ 11,447.80$
588.00$ 1,962.36$
125.00$ 316.16$
32.00$ 92.67$
4,000.00$ 21,804.00$
140.00$ 196.24$
65.00$ 130.82$
150.00$ 212.59$
750.00$ 5,996.10$
0.25$ 0.35$
42.00$ 141.73$
4.00$ 26.44$
600.00$ 1,362.75$
98.00$ 327.06$
60.00$ 81.77$
12/2/2015 Page 9 of 20
Project No: NV FTNP LAKE 114(1)
Project Name: Katherine Access Road CQ = "Contract Quantity"
Item No. Quantity Unit
63501-1000 Line X1060 ALL LPSM
63502-0700 Line X1080 140 EACH
63502-1300 Line X1100 170 EACH
63502-1700 Line X1120 10 EACH
63503-0300 Line X1140 20 LNFT
63504-1000 Line X1160 385 SQFT
63505-1000 Line X1180 1.6 MILE
63506-0500 Line X1200 1,000 HOUR
63506-0600 Line X1220 300 HOUR
TEMPORARY TRAFFIC CONTROL, TRAFFIC AND S
TEMPORARY TRAFFIC CONTROL, CONE
TEMPORARY TRAFFIC CONTROL, PILOT CAR
TEMPORARY TRAFFIC CONTROL, DRUM
TEMPORARY TRAFFIC CONTROL, WARNING LIGH
TEMPORARY TRAFFIC CONTROL, BARRICADE TY
TEMPORARY TRAFFIC CONTROL, CONSTRUCTIO
TEMPORARY TRAFFIC CONTROL, PAVEMENT MAR
TEMPORARY TRAFFIC CONTROL, FLAGGER
-11.3% 989,666.00$ 14.8% 1,280,810.92$
Unit Price Amount Unit Price Amount
Fann Contracting, Inc. Interstate Rock Products
6,000.00$ 67,976.15$
3,220.00$ 7,936.60$
17,000.00$ 38,734.50$
570.00$ 7,631.40$
16,500.00$ 12,690.00$
7,700.00$ 12,593.35$
1,920.00$ 2,616.48$
27,000.00$ 75,220.00$
12,000.00$ 42,192.00$
23.00$ 56.69$
6,000.00$ 67,976.15$
57.00$ 763.14$
100.00$ 227.85$
20.00$ 32.71$
825.00$ 634.50$
40.00$ 140.64$
27.00$ 75.22$
1,200.00$ 1,635.30$
12/2/2015 Page 10 of 20
Project No: NV FTNP LAKE 114(1)
Project Name: Katherine Access Road CQ = "Contract Quantity"
Item No. Quantity Unit
15101-0000 Line X0020 ALL LPSM
15206-0000 Line X0040 43.000 STA
15210-3000 Line X0060 43.000 STA
15215-3000 Line X0080 4 EACH
15216-2000 Line X0100 43.000 STA
15301-0000 Line X0120 ALL LPSM
15401-0000 Line X0140 ALL LPSM
15501-0000 Line X0160 ALL LPSM
15705-0100 Line X0180 3,000 LNFT
15705-1400 Line X0200 2,700 LNFT
15706-0400 Line X0220 5 EACH
15706-1600 Line X0240 2 EACH
15802-0000 Line X0260 ALL LPSM
SURVEY AND STAKING, DRAINAGE STRUCTURE
MOBILIZATION
SLOPE, REFERENCE, AND CLEARING AND GRUBB
CENTERLINE, VERIFICATION AND STAKING
CONTRACTOR TESTING
CONSTRUCTION SCHEDULE
SOIL EROSION CONTROL, SILT FENCE
SOIL EROSION CONTROL, SEDIMENT LOG
SOIL EROSION CONTROL, SEDIMENT TRAP
SOIL EROSION CONTROL, STABILIZED CONSTR
SURVEY AND STAKING, GRADE FINISHING STAK
CONTRACTOR QUALITY CONTROL
WATERING FOR DUST CONTROL
14.8% 1,280,810.92$ -17.7% 917,870.00$
Unit Price Amount Unit Price Amount
48,946.53$ 10,000.00$
14,063.58$ 10,750.00$
4,687.86$ 1,720.00$
1,090.20$ 4,000.00$
7,031.79$ 8,600.00$
29,419.05$ 8,000.00$
21,804.00$ 8,000.00$
2,180.40$ 1,000.00$
13,080.00$ 12,000.00$
8,829.00$ 10,800.00$
2,725.50$ 7,500.00$
6,541.20$ 4,000.00$
10,902.00$ 5,000.00$
272.55$ 1,000.00$
48,946.53$
Pace Contracting RBK Contracting, Inc.
163.53$ 200.00$
10,000.00$
327.06$ 250.00$
109.02$ 40.00$
2,180.40$ 1,000.00$
21,804.00$ 8,000.00$
29,419.05$ 8,000.00$
3.27$ 4.00$
4.36$ 4.00$
3,270.60$ 2,000.00$
545.10$ 1,500.00$
10,902.00$ 5,000.00$
12/2/2015 Page 11 of 20
Project No: NV FTNP LAKE 114(1)
Project Name: Katherine Access Road CQ = "Contract Quantity"
Item No. Quantity Unit
20103-0000 Line X0280 17,000 SQYD
20301-0700 Line X0300 16 EACH
20301-2400 Line X0320 6 EACH
20420-0000 Line X0340 7,300 CUYD
25101-3000 Line X0360 220 CUYD
30306-3000 Line X0380 16,500 SQYD
30801-2000 Line X0400 1,050 CUYD
40201-4700 Line X0420 2,700 TON
40205-3000 Line X0440 28 TON
40501-0000 Line X0460 490 TON
40505-3000 Line X0480 6 TON
40961-0000 Line X0500 2,800 SQYD
41103-0000 Line X0520 14,500 SQYD
REMOVAL OF SIGN
EMBANKMENT CONSTRUCTION
PLACED RIPRAP, CLASS 3
BLOTTER
PRIME COAT
PULVERIZING, 6-INCH DEPTH
ROADWAY AGGREGATE, METHOD 2
HOT ASPHALT CONCRETE PAVEMENT, HVEEM TE
ANTISTRIP ADDITIVE, TYPE 3
OPEN-GRADED ASPHALT FRICTION COURSE
ANTISTRIP ADDITIVE, TYPE 3
CLEARING AND GRUBBING
REMOVAL OF DELINEATOR
14.8% 1,280,810.92$ -17.7% 917,870.00$
Unit Price Amount Unit Price Amount
Pace Contracting RBK Contracting, Inc.
3,740.00$ 8,500.00$
436.16$ 160.00$
163.56$ 420.00$
151,548.00$ 73,000.00$
21,106.80$ 20,900.00$
18,315.00$ 99,000.00$
27,468.00$ 44,100.00$
235,494.00$ 237,600.00$
4,426.24$ 5,180.00$
58,359.00$ 57,820.00$
948.48$ 1,110.00$
336.00$ 280.00$
5,220.00$ 8,700.00$
0.22$ 0.50$
27.26$ 70.00$
27.26$ 10.00$
95.94$ 95.00$
20.76$ 10.00$
26.16$ 42.00$
1.11$ 6.00$
158.08$ 185.00$
87.22$ 88.00$
158.08$ 185.00$
119.10$ 118.00$
0.36$ 0.60$
0.12$ 0.10$
12/2/2015 Page 12 of 20
Project No: NV FTNP LAKE 114(1)
Project Name: Katherine Access Road CQ = "Contract Quantity"
Item No. Quantity Unit
41201-1000 Line X0540 7 TON
60201-1000 Line X0560 50 LNFT
60210-1000 Line X0580 5 EACH
60704-0000 Line X0600 2 EACH (CQ)
60902-1000 Line X0620 680 LNFT
61701-1800 Line X0640 1,690 LNFT
61702-0800 Line X0660 14 EACH
62201-0200 Line X0680 20 HOUR
62201-0550 Line X0700 20 HOUR
62201-0900 Line X0720 20 HOUR
62201-1150 Line X0740 20 HOUR
62201-1300 Line X0760 20 HOUR
62201-2750 Line X0780 20 HOUR
CLEANING CULVERT IN PLACE
BULLDOZER, 70HP MINIMUM FLYWHEEL POWER
BULLDOZER, 160HP MINIMUM FLYWHEEL POWE
MOTOR GRADER
CURB AND GUTTER, CONCRETE, 12-INCH DEPTH
GUARDRAIL SYSTEM G4, TYPE 4, CLASS A STEE
TERMINAL SECTION TYPE TANGENT
DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACIT
BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RA
WHEEL LOADER, 2 CUBIC YARD MINIMUM RATE
TACK COAT GRADE CSS-1, CSS-1H, SS-1, OR S
36-INCH PIPE CULVERT
END SECTION FOR 36-INCH PIPE CULVERT
14.8% 1,280,810.92$ -17.7% 917,870.00$
Unit Price Amount Unit Price Amount
Pace Contracting RBK Contracting, Inc.
4,197.27$ 4,900.00$
6,432.00$ 6,100.00$
8,176.50$ 3,125.00$
763.14$ 4,000.00$
13,341.60$ 18,360.00$
69,374.50$ 33,800.00$
73,032.54$ 35,000.00$
2,834.60$ 2,200.00$
2,398.40$ 2,100.00$
5,015.00$ 3,000.00$
5,287.40$ 3,600.00$
7,140.80$ 5,500.00$
6,541.20$ 3,000.00$
128.64$ 122.00$
599.61$ 700.00$
381.57$ 2,000.00$
1,635.30$ 625.00$
41.05$ 20.00$
19.62$ 27.00$
141.73$ 110.00$
5,216.61$ 2,500.00$
250.75$ 150.00$
119.92$ 105.00$
357.04$ 275.00$
264.37$ 180.00$
327.06$ 150.00$
12/2/2015 Page 13 of 20
Project No: NV FTNP LAKE 114(1)
Project Name: Katherine Access Road CQ = "Contract Quantity"
Item No. Quantity Unit
62201-3350 Line X0800 20 HOUR
62202-1000 Line X0820 ALL LPSM
62301-0000 Line X0840 40 HOUR
62302-1000 Line X0860 40 HOUR
62302-1100 Line X0880 40 HOUR
63301-0000 Line X0900 6 EACH
63308-3000 Line X0920 10 EACH
63309-0100 Line X0940 46 EACH
63313-0000 Line X0960 4,300 LNFT
63316-1000 Line X0980 2 EACH
63403-0400 Line X1000 100 SQFT
63404-0400 Line X1020 140 GAL
63405-0050 Line X1040 6 EACH
HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMU
MATERIALS TRANSFER VEHICLE
GENERAL LABOR
REMOVE AND RESET SIGN
PAVEMENT MARKINGS, TYPE D
PAVEMENT MARKINGS, TYPE D
PAVEMENT MARKINGS, SYMBOLS
SPECIAL LABOR, HIRED TECHNICAL SERVICES
SPECIAL LABOR, HIRED SURVEY SERVICES
SIGN SYSTEM
OBJECT MARKER, TYPE 3
DELINEATOR, TYPE 1
RUMBLE STRIP
14.8% 1,280,810.92$ -17.7% 917,870.00$
Unit Price Amount Unit Price Amount
Pace Contracting RBK Contracting, Inc.
6,323.20$ 3,800.00$
21,804.00$ 5,000.00$
3,706.80$ 2,000.00$
5,232.80$ 7,000.00$
7,849.60$ 7,000.00$
35,976.60$ 3,150.00$
2,125.90$ 3,200.00$
6,519.58$ 1,840.00$
1,505.00$ 860.00$
2,725.50$ 700.00$
2,644.00$ 475.00$
11,447.80$ 9,100.00$
1,962.36$ 600.00$
316.16$ 190.00$
92.67$ 50.00$
21,804.00$ 5,000.00$
196.24$ 175.00$
130.82$ 175.00$
212.59$ 320.00$
5,996.10$ 525.00$
0.35$ 0.20$
141.73$ 40.00$
26.44$ 4.75$
1,362.75$ 350.00$
327.06$ 100.00$
81.77$ 65.00$
12/2/2015 Page 14 of 20
Project No: NV FTNP LAKE 114(1)
Project Name: Katherine Access Road CQ = "Contract Quantity"
Item No. Quantity Unit
63501-1000 Line X1060 ALL LPSM
63502-0700 Line X1080 140 EACH
63502-1300 Line X1100 170 EACH
63502-1700 Line X1120 10 EACH
63503-0300 Line X1140 20 LNFT
63504-1000 Line X1160 385 SQFT
63505-1000 Line X1180 1.6 MILE
63506-0500 Line X1200 1,000 HOUR
63506-0600 Line X1220 300 HOUR
TEMPORARY TRAFFIC CONTROL, TRAFFIC AND S
TEMPORARY TRAFFIC CONTROL, CONE
TEMPORARY TRAFFIC CONTROL, PILOT CAR
TEMPORARY TRAFFIC CONTROL, DRUM
TEMPORARY TRAFFIC CONTROL, WARNING LIGH
TEMPORARY TRAFFIC CONTROL, BARRICADE TY
TEMPORARY TRAFFIC CONTROL, CONSTRUCTIO
TEMPORARY TRAFFIC CONTROL, PAVEMENT MAR
TEMPORARY TRAFFIC CONTROL, FLAGGER
14.8% 1,280,810.92$ -17.7% 917,870.00$
Unit Price Amount Unit Price Amount
Pace Contracting RBK Contracting, Inc.
67,976.15$ 35,000.00$
7,936.60$ 1,120.00$
38,734.50$ 9,350.00$
7,631.40$ 4,000.00$
12,690.00$ 600.00$
12,593.35$ 3,850.00$
2,616.48$ 6,400.00$
75,220.00$ 25,000.00$
42,192.00$ 15,000.00$
56.69$ 8.00$
67,976.15$ 35,000.00$
763.14$ 400.00$
227.85$ 55.00$
32.71$ 10.00$
634.50$ 30.00$
140.64$ 50.00$
75.22$ 25.00$
1,635.30$ 4,000.00$
12/2/2015 Page 15 of 20
Project No: NV FTNP LAKE 114(1)
Project Name: Katherine Access Road CQ = "Contract Quantity"
Item No. Quantity Unit
15101-0000 Line X0020 ALL LPSM
15206-0000 Line X0040 43.000 STA
15210-3000 Line X0060 43.000 STA
15215-3000 Line X0080 4 EACH
15216-2000 Line X0100 43.000 STA
15301-0000 Line X0120 ALL LPSM
15401-0000 Line X0140 ALL LPSM
15501-0000 Line X0160 ALL LPSM
15705-0100 Line X0180 3,000 LNFT
15705-1400 Line X0200 2,700 LNFT
15706-0400 Line X0220 5 EACH
15706-1600 Line X0240 2 EACH
15802-0000 Line X0260 ALL LPSM
SURVEY AND STAKING, DRAINAGE STRUCTURE
MOBILIZATION
SLOPE, REFERENCE, AND CLEARING AND GRUBB
CENTERLINE, VERIFICATION AND STAKING
CONTRACTOR TESTING
CONSTRUCTION SCHEDULE
SOIL EROSION CONTROL, SILT FENCE
SOIL EROSION CONTROL, SEDIMENT LOG
SOIL EROSION CONTROL, SEDIMENT TRAP
SOIL EROSION CONTROL, STABILIZED CONSTR
SURVEY AND STAKING, GRADE FINISHING STAK
CONTRACTOR QUALITY CONTROL
WATERING FOR DUST CONTROL
5.9% 1,181,564.00$ 43.3% 1,598,795.00$
Unit Price Amount Unit Price Amount
80,000.00$ 159,500.00$
2,924.00$ 4,300.00$
1,763.00$ 3,225.00$
1,400.00$ 2,000.00$
2,494.00$ 3,655.00$
50,000.00$ 35,000.00$
33,000.00$ 40,000.00$
5,000.00$ 3,000.00$
10,200.00$ 18,000.00$
21,870.00$ 21,600.00$
9,175.00$ 12,000.00$
3,180.00$ 5,000.00$
49,000.00$ 100,000.00$
350.00$ 500.00$
75.00$
Hooker Creek, Inc. Meadow Valley Contractors dba ACC
58.00$ 85.00$
80,000.00$ 159,500.00$
68.00$ 100.00$
41.00$
5,000.00$ 3,000.00$
33,000.00$ 40,000.00$
50,000.00$ 35,000.00$
8.10$ 8.00$
3.40$ 6.00$
1,590.00$ 2,500.00$
1,835.00$ 2,400.00$
49,000.00$ 100,000.00$
12/2/2015 Page 16 of 20
Project No: NV FTNP LAKE 114(1)
Project Name: Katherine Access Road CQ = "Contract Quantity"
Item No. Quantity Unit
20103-0000 Line X0280 17,000 SQYD
20301-0700 Line X0300 16 EACH
20301-2400 Line X0320 6 EACH
20420-0000 Line X0340 7,300 CUYD
25101-3000 Line X0360 220 CUYD
30306-3000 Line X0380 16,500 SQYD
30801-2000 Line X0400 1,050 CUYD
40201-4700 Line X0420 2,700 TON
40205-3000 Line X0440 28 TON
40501-0000 Line X0460 490 TON
40505-3000 Line X0480 6 TON
40961-0000 Line X0500 2,800 SQYD
41103-0000 Line X0520 14,500 SQYD
REMOVAL OF SIGN
EMBANKMENT CONSTRUCTION
PLACED RIPRAP, CLASS 3
BLOTTER
PRIME COAT
PULVERIZING, 6-INCH DEPTH
ROADWAY AGGREGATE, METHOD 2
HOT ASPHALT CONCRETE PAVEMENT, HVEEM TE
ANTISTRIP ADDITIVE, TYPE 3
OPEN-GRADED ASPHALT FRICTION COURSE
ANTISTRIP ADDITIVE, TYPE 3
CLEARING AND GRUBBING
REMOVAL OF DELINEATOR
5.9% 1,181,564.00$ 43.3% 1,598,795.00$
Unit Price Amount Unit Price Amount
Hooker Creek, Inc. Meadow Valley Contractors dba ACC
9,010.00$ 17,000.00$
336.00$ 800.00$
444.00$ 750.00$
129,940.00$ 204,400.00$
25,300.00$ 24,200.00$
89,100.00$ 57,750.00$
35,700.00$ 52,500.00$
245,700.00$ 310,500.00$
4,200.00$ 5,600.00$
56,350.00$ 75,950.00$
960.00$ 1,200.00$
2,800.00$ 3,500.00$
9,570.00$ 7,250.00$
0.53$ 1.00$
74.00$ 125.00$
21.00$ 50.00$
115.00$ 110.00$
17.80$ 28.00$
34.00$ 50.00$
5.40$ 3.50$
150.00$ 200.00$
91.00$ 115.00$
160.00$ 200.00$
115.00$ 155.00$
0.66$ 0.50$
1.00$ 1.25$
12/2/2015 Page 17 of 20
Project No: NV FTNP LAKE 114(1)
Project Name: Katherine Access Road CQ = "Contract Quantity"
Item No. Quantity Unit
41201-1000 Line X0540 7 TON
60201-1000 Line X0560 50 LNFT
60210-1000 Line X0580 5 EACH
60704-0000 Line X0600 2 EACH (CQ)
60902-1000 Line X0620 680 LNFT
61701-1800 Line X0640 1,690 LNFT
61702-0800 Line X0660 14 EACH
62201-0200 Line X0680 20 HOUR
62201-0550 Line X0700 20 HOUR
62201-0900 Line X0720 20 HOUR
62201-1150 Line X0740 20 HOUR
62201-1300 Line X0760 20 HOUR
62201-2750 Line X0780 20 HOUR
CLEANING CULVERT IN PLACE
BULLDOZER, 70HP MINIMUM FLYWHEEL POWER
BULLDOZER, 160HP MINIMUM FLYWHEEL POWE
MOTOR GRADER
CURB AND GUTTER, CONCRETE, 12-INCH DEPTH
GUARDRAIL SYSTEM G4, TYPE 4, CLASS A STEE
TERMINAL SECTION TYPE TANGENT
DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACIT
BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RA
WHEEL LOADER, 2 CUBIC YARD MINIMUM RATE
TACK COAT GRADE CSS-1, CSS-1H, SS-1, OR S
36-INCH PIPE CULVERT
END SECTION FOR 36-INCH PIPE CULVERT
5.9% 1,181,564.00$ 43.3% 1,598,795.00$
Unit Price Amount Unit Price Amount
Hooker Creek, Inc. Meadow Valley Contractors dba ACC
4,200.00$ 5,250.00$
8,500.00$ 5,000.00$
3,150.00$ 5,500.00$
380.00$ 2,000.00$
21,760.00$ 12,240.00$
33,800.00$ 40,560.00$
35,000.00$ 70,000.00$
2,480.00$ 5,000.00$
1,840.00$ 2,600.00$
2,600.00$ 5,000.00$
3,100.00$ 7,000.00$
4,400.00$ 8,000.00$
2,800.00$ 3,500.00$
170.00$ 100.00$
600.00$ 750.00$
190.00$ 1,000.00$
630.00$ 1,100.00$
20.00$ 24.00$
32.00$ 18.00$
124.00$ 250.00$
2,500.00$ 5,000.00$
130.00$ 250.00$
92.00$ 130.00$
220.00$ 400.00$
155.00$ 350.00$
140.00$ 175.00$
12/2/2015 Page 18 of 20
Project No: NV FTNP LAKE 114(1)
Project Name: Katherine Access Road CQ = "Contract Quantity"
Item No. Quantity Unit
62201-3350 Line X0800 20 HOUR
62202-1000 Line X0820 ALL LPSM
62301-0000 Line X0840 40 HOUR
62302-1000 Line X0860 40 HOUR
62302-1100 Line X0880 40 HOUR
63301-0000 Line X0900 6 EACH
63308-3000 Line X0920 10 EACH
63309-0100 Line X0940 46 EACH
63313-0000 Line X0960 4,300 LNFT
63316-1000 Line X0980 2 EACH
63403-0400 Line X1000 100 SQFT
63404-0400 Line X1020 140 GAL
63405-0050 Line X1040 6 EACH
HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMU
MATERIALS TRANSFER VEHICLE
GENERAL LABOR
REMOVE AND RESET SIGN
PAVEMENT MARKINGS, TYPE D
PAVEMENT MARKINGS, TYPE D
PAVEMENT MARKINGS, SYMBOLS
SPECIAL LABOR, HIRED TECHNICAL SERVICES
SPECIAL LABOR, HIRED SURVEY SERVICES
SIGN SYSTEM
OBJECT MARKER, TYPE 3
DELINEATOR, TYPE 1
RUMBLE STRIP
5.9% 1,181,564.00$ 43.3% 1,598,795.00$
Unit Price Amount Unit Price Amount
Hooker Creek, Inc. Meadow Valley Contractors dba ACC
3,000.00$ 3,000.00$
10,000.00$ 1,300.00$
1,240.00$ 4,000.00$
8,800.00$ 6,000.00$
5,200.00$ 6,400.00$
2,820.00$ 2,250.00$
3,100.00$ 1,500.00$
1,978.00$ 4,140.00$
6,450.00$ 1,075.00$
680.00$ 1,200.00$
2,600.00$ 500.00$
10,640.00$ 11,200.00$
1,980.00$ 750.00$
150.00$ 150.00$
31.00$ 100.00$
10,000.00$ 1,300.00$
130.00$ 160.00$
220.00$ 150.00$
310.00$ 150.00$
470.00$ 375.00$
1.50$ 0.25$
43.00$ 90.00$
26.00$ 5.00$
340.00$ 600.00$
330.00$ 125.00$
76.00$ 80.00$
12/2/2015 Page 19 of 20
Project No: NV FTNP LAKE 114(1)
Project Name: Katherine Access Road CQ = "Contract Quantity"
Item No. Quantity Unit
63501-1000 Line X1060 ALL LPSM
63502-0700 Line X1080 140 EACH
63502-1300 Line X1100 170 EACH
63502-1700 Line X1120 10 EACH
63503-0300 Line X1140 20 LNFT
63504-1000 Line X1160 385 SQFT
63505-1000 Line X1180 1.6 MILE
63506-0500 Line X1200 1,000 HOUR
63506-0600 Line X1220 300 HOUR
TEMPORARY TRAFFIC CONTROL, TRAFFIC AND S
TEMPORARY TRAFFIC CONTROL, CONE
TEMPORARY TRAFFIC CONTROL, PILOT CAR
TEMPORARY TRAFFIC CONTROL, DRUM
TEMPORARY TRAFFIC CONTROL, WARNING LIGH
TEMPORARY TRAFFIC CONTROL, BARRICADE TY
TEMPORARY TRAFFIC CONTROL, CONSTRUCTIO
TEMPORARY TRAFFIC CONTROL, PAVEMENT MAR
TEMPORARY TRAFFIC CONTROL, FLAGGER
5.9% 1,181,564.00$ 43.3% 1,598,795.00$
Unit Price Amount Unit Price Amount
Hooker Creek, Inc. Meadow Valley Contractors dba ACC
20,000.00$ 90,000.00$
2,240.00$ 3,360.00$
18,700.00$ 11,900.00$
550.00$ 250.00$
2,800.00$ 600.00$
15,400.00$ 9,240.00$
2,560.00$ 4,800.00$
34,000.00$ 65,000.00$
23,400.00$ 30,000.00$
16.00$ 24.00$
20,000.00$ 90,000.00$
55.00$ 25.00$
110.00$ 70.00$
40.00$ 24.00$
140.00$ 30.00$
78.00$ 100.00$
34.00$ 65.00$
1,600.00$ 3,000.00$
12/2/2015 Page 20 of 20