This is a technical drawing document prepared by the State of Michigan Department of Technology, Management, and Budget Facilities and Business Services Administration for the Alpena Combat Readiness Training Center (CRTC), in coordination with the Department of Military and Veterans Affairs. The project involves the replacement of backup generators in Building 335 at the Alpena CRTC. The scope of work includes removal of existing 100kW and 135kW generators and associated automatic transfer switches, installation of new Cummins generators (80kW and 100kW models), replacement of automatic transfer switches (225 AMP and 400 AMP units), installation of fuel storage tanks (600-gallon and 700-gallon main tanks with 50-gallon day tanks), load bank equipment for testing purposes, surge protective devices, and associated electrical infrastructure including conduit routing, conductor installations, and control cabinets. The drawings specify demolition and new equipment plans with detailed electrical schematics, operational sequences, and fuel system piping diagrams. All installations must comply with federal, state, and local electrical codes and regulations. The contractor is responsible for cutting and patching as required, verifying existing conditions prior to bidding, and ensuring all existing equipment remains operational upon project completion.
The technical specifications require the contractor to include all costs for materials, labor, and equipment in the bid proposal. Wire sizing standards are established based on voltage and distance requirements, with 120/208V and 277/480V systems specified separately. The project requires coordination of power outages in advance with the owner, and certain demolition work may occur outside regular working hours with premium time costs included in the proposal. Contractor coordination is essential to minimize downtime for existing equipment during automatic transfer switch removal. The design team includes personnel from Sidock Group, Inc., with contact information provided for Mr. Kendziorski at (989) 657-3026. All design documents and materials are identified as exclusive property of Sidock Group, Inc., and reproduction is prohibited without prior written consent. The project drawings indicate this is preliminary construction documentation for bidding purposes.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCALE:
SCHOOLCRAFT
MANISTEE
OCEANA
MUSKEGON
MASON
BERRIEN
GOGEBIC
DICKINSON
MENOMINEE
DELTA
ONTONAGON
IRON
BARAGA
HOUGHTON
KEWEENAW
MARQUETTE
ALGER
ST.
CLAIR
HILLSDALE
CASS ST.
JOSEPH BRANCH
LENAWEE MONROE
GLADWIN
MIDLAND
JACKSON
BARRY
VAN
BUREN
ALLEGAN
KALAMAZOO
OTTAWA
KENT
EATON
CALHOUN
IONIA CLINTON
MECOSTA
OSCEOLA
NEWAYGO
LAKE
ISABELLA
MONTCALM GRATIOT
CLARE
INGHAM
WASHTENAW
LIVINGSTON
SHIAWASSEE
GENESEE
OAKLAND
WAYNE
LAPEER
MACOMB
TUSCOLA
SAGINAW
ARENAC
BAY
SANILAC
HURON
ANTRIM
GRAND
TRAVERSE
WEXFORD
LELANAU
BENZIE
MISSAUKEE ROSCOMMON
KALKASKA CRAWFORD
OTSEGO
CHALEVOIX
EMMET
CHEBOYGAN
MACKINAC
OGEMAW IOSCO
OSCODA
MONTMORENCY
ALCONA
ALPENA
PRESQUE
ISLE
LUCE
CHIPPEWA
LOCATION MAP
NO SCALELAKE
MICHIGAN
LAKE
SUPERIOR
LAKE
ERIE
LAKE
HURON
PANELBOARD,ATS,SPD, LOAD BANK OR FUEL TANK: AS NOTED
DUPLEX RECEPTACLE
VARIABLE FREQUENCY DRIVE
POWER SYMBOLS
NOTE SYMBOLS
ELECTRICAL DEMOLITION PLAN NOTES
POWER PLAN NOTESPx
COMBINATION STARTER; SEE SCHEDULE FOR DETAILS
NONFUSED DISCONNECT; SEE SCHEDULE FOR DETAILS
FUSED DISCONNECT; SEE SCHEDULE FOR DETAILS
DUPLEX RECEPTACLE, GROUND FAULT CIRCUIT INTERRUPTGFI
SPECIAL RECEPTACLE; SEE DRAWINGS
JUNCTION BOXJ
NOT ALL SYMBOLS MAY BE USED
Dx
LIGHTING PLAN NOTESLx
TECHNOLOGY PLAN NOTESTx
A
AFF
AFG
C
EMT
EF
FMC
GFCI
AMPERE
ABOVE FINISHED FLOOR
ABOVE FINISHED GRADE
CONDUIT
ELECTRICAL METALLIC TUBING
EXHAUST FAN
FLEXIBLE METALLIC TUBING
GROUND FAULT CIRCUIT INTERRUPTER
GRC
IG
PVC
R
WP
GALVANIZED RIGID CONDUIT
ISOLATED GROUND
CONDUIT
REMOVE
WEATHERPROOF
ABBREVIATIONS
GENERAL NOTES - APPLY TO ALL SHEETS:
• INSTALLATIONS SHALL CONFORM WITH FEDERAL, STATE, AND LOCAL LAWS,
CODES, ORDINANCES, RULES, AND REGULATIONS WHICH ARE HEREBY MADE A
PART OF THESE CONTRACT DOCUMENTS THE SAME AS IF REPEATED HEREIN.
• CONTRACTOR SHALL INCLUDE IN BID/PROPOSAL COST REQUIRED TO
COMPLETELY AND PROPERLY INSTALL WORK REQUIRED FOR THE PROJECT.
• CONTRACTOR SHALL INCLUDE IN BID/PROPOSAL COST FOR CUTTING AND
PATCHING AS REQUIRED TO INSTALL NEW OR EXISTING WORK, EQUIPMENT OR
SYSTEMS.
• CLEARANCES INDICATED ARE BASED ON BEST AVAILABLE INFORMATION.
CONTRACTOR SHALL VERIFY PIPING, DUCTWORK, ROUTING, AND STRUCTURAL
DETAILS PRIOR TO SUBMITTING A BID/PROPOSAL AND INCLUDE SUCH COSTS
AS REQUIRED TO INSTALL WORK AS SHOWN AND INTENDED.
• ALL POWER OUTAGES SHALL BE COORDINATED AND SCHEDULED IN ADVANCE
WITH THE OWNER.
• WHEREAS PLANS GENERALLY SHOW INDIVIDUAL HOME RUN SINGLE PHASE
BRANCH CIRCUITS, CONTRACTOR MAY RUN UP TO THREE (3) SUCH CIRCUITS IN
A RACEWAY.
• WIRE SIZES: BRANCH CIRCUIT WIRE SIZES SHALL BE BASED ON THE VALUES
INDICATED BELOW
1. 120/208V CABLING FROM PANEL TO THE ELECTRICAL LOAD SHALL BE
ADJUSTED AS FOLLOWS UNLESS SPECIFICALLY NOTED OTHERWISE.
A. 0 TO 100FT: #12AWG MINIMUM
B. 100 TO 200FT: #10AWG MINIMUM
C. 200 TO 250FT: #8AWG MINIMUM
2. 277/480V CABLING FROM PANEL TO THE ELECTRICAL LOAD SHALL BE
ADJUSTED AS FOLLOWS UNLESS SPECIFICALLY NOTED OTHERWISE.
A. 0 TO 150FT: #12AWG MINIMUM
B. 150 TO 250FT: #10AWG MINIMUM
C. 250 TO 350FT: #8AWG MINIMUM
• CIRCUIT NUMBERS SHOWN FOR EXISTING PANELS ARE BASED ON EXISTING
DRAWINGS, SCHEDULES, AND FIELD SURVEY. FIELD VERIFY AS REQUIRED.
• CONTRACT DOCUMENTS CONSIST OF BOTH PROJECT MANUAL AND DRAWINGS
AND BOTH ARE MEANT TO BE COMPLEMENTARY. ANYTHING APPEARING ON
EITHER MUST BE EXECUTED THE SAME AS IF SHOWN ON BOTH.
• SOME ELECTRICAL WORK MAY BE REQUIRED TO BE PERFORMED OFF REGULAR
WORK HOURS. COST FOR PREMIUM TIME SHALL BE INCLUDED IN THE
BID/PROPOSAL.
• ALL EXISTING EQUIPMENT THAT IS TO REMAIN IS INTENDED TO BE
OPERATIONAL AT THE COMPLETION OF THE JOB. THIS CONTRACTOR SHALL
RECIRCUIT WHERE NECESSARY TO ENSURE THIS CONTINUED OPERATION.
FOR SITE OWNED UTILITIES
THIS MATERIAL IS THE EXCLUSIVE PROPERTY OF
SIDOCK GROUP, INC. AND CANNOT BE REPRODUCED,
COPIED, OR USED IN ANY MANNER WITHOUT THE PRIOR
WRITTEN CONSENT OF SIDOCK GROUP, INC. 2022C SH
EE
T
TI
TL
E:
SH
EE
T
ID
EN
TI
FI
CA
TI
O N
NO
PR
O
JE
C
T N
O
FI
LE
N O
./I N
D
EX
C O
D E:
IS
SU
ED
F
O R:
PR
EL
IM
IN
AR
Y
C O
N
ST
R U
C
TI
O N
FI
N
AL
R
EC
O
R D
DA
TE
D R
AW
N
D
ES
IG
N
ED
C H
EC
KE
D
AP
PR
O
VE
D
ST
AT
E O
F M
IC
H
IG
AN
D
EP
AR
TM
EN
T
O F
TE
C
H N
O
LO
G Y, M
AN
AG
EM
EN
T, A N
D B
U D
G
ET
FA
C
IL
IT
IE
S
AN
D
B U
SI
N
ES
S
SE
R
VI
C
ES
A
D M
IN
IS
TR
AT
IO
N
AD
AM
P . L
AR
C
H , R
.A
D
IR
EC
TO
R
DE
SI
G
N
AN
D
CO
NS
TR
UC
TI
O N
DI
VI
SI
O
N
CALL:
PH:
MR. KENDZIORSKI
(989) 657-3026
ALPENA CRTC ENGINEERING
1/
.J
LM
X C
S0
C O
VE
R
S H
EE
T
-B U
IL
D
IN
G
AL
PE
NA
C.
R.
T.
C.
M
UL
TI
PL
E
BL
DG
S- G
EN
ER
AT
O
R
RE
PL
AC
EM
EN
T D
EP
AR
TM
EN
T O
F M
IL
IT
AR
Y
AN
D
V
ET
ER
AN
S
AF
FA
IR
S
AL
PE
N
A C
.R .T
.C
AL
PE
N A, M I
M
RI
M
RI
LR M
RI
-2 9-
REPLACEMENT OF BACKUP GENERATORS
BUILDING 335
ALPENA C.R.T.C.
MICHIGAN AIR NATIONAL GUARD
ALPENA, MICHIGAN
Sheet List Sheet Number Sheet Name
CS000 COVER SHEET - BUILDING 335
E100 DEMOLITION PLAN - BUILDING 335
E200 NEW EQUIPMENT PLAN - BUILDING 335
E300 OPERATIONAL DETAILS - BUILDING 335
Alpena CRTC
Site
ATS
ATS
DP-2
MAIN DISC
LP-2
100KW ATS
135KW ATS
DP-1
100KW
GENERATOR
135KW
GENERATOR
D1
D2
D1
D2
D3
D4
D5
D5
D6 D6
100KW
A.T.S
EXIST.
PANEL
'DP-1'
1000A M.L.O.
100KW
GENERATOR #1
BLDG 319
EXIST.
PANEL
'LP-1'
135KW
GENERATOR #2
EXIST.
MAIN
DISC
FROM
TRANSFORMER
135KW
A.T.S
EXIST.
PANEL
'DP-2'
BLDG 30
FIRE STATION
MAINTAIN CONDUIT AND CONDUCTORS FOR REUSE IF POSSIBLE
120/208V
3PH,4W 120/208V
3PH,4W
120/208V
3PH,4W
ALL EQUIPMENT SHOWN ON THIS SHEET IS EXISTING.
DASHED LINES INDICATE EXISTING EQUIPMENT TO BE
REMOVED. SOLID LINES INDICATE EXISTING EQUIPMENT TO
REMAIN.
EXISTING EQUIPMENT THAT IS TO REMAIN IS INTENDED TO BE
OPERATIONAL AT THE COMPLETION OF THE PROJECT.
RECIRCUIT WHERE NECESSARY TO ENSURE CONTINUED
OPERATION.
EXISTING EQUIPMENT SHOWN ON DRAWINGS IS BELIEVED TO
BE A REASONABLE INDICATION OF THE EXISTING LAYOUT.
EXACT QUANTITY AND LOCATION SHALL BE DETERMINED AT
THE JOB SITE. THE EXISTING DRAWINGS ARE FOR
CONVENIENCE ONLY AND NOT FOR THE BASIS OF BIDDING.
• REMOVE ABANDONED WIRE COMPLETELY TO ITS SOURCE UNLESS NOTED
OTHERWISE. REMOVE ABANDONED RACEWAY WITHIN THE PROJECT AREA AND CAP
STUBS THAT REMAIN. SEAL PENETRATIONS THROUGH FLOORS AND WALLS.
• EXISTING EQUIPMENT THAT REMAINS IS INTENDED TO BE OPERATIONAL AT THE
COMPLETION OF THE JOB. RECIRCUIT WHERE NECESSARY TO ENSURE THIS
CONTINUED OPERATION.
• THE EXISTING EQUIPMENT SHOWN ON THE DRAWINGS IS BELIEVED TO BE A
REASONABLE INDICATION OF THE PRESENT LAYOUT. DETERMINE EXACT QUANTITY
AND LOCATION AT THE JOB SITE. THE EXISTING DRAWINGS ARE FOR CONVENIENCE
ONLY AND NOT FOR THE BASIS OF BIDDING.
• VERIFY ALL DEMOLITION WORK PRIOR TO SUBMITTING A BID/PROPOSAL.
• DETERMINE AND MAINTAIN TRANSIENT SERVICES THROUGH PROJECT AREA AS
REQUIRED.
• SOME REQUIRED DEMOLITION WORK MAY NOT BE INDICATED ON THESE DRAWINGS.
• EXISTING RACEWAYS AND BOXES MAY BE REUSED WHERE FOUND TO BE SUITABLE.
INCLUDE IN BID/PROPOSAL COSTS FOR CUTTING AND PATCHING AS REQUIRED TO
INSTALL NEW OR EXISTING WORK, EQUIPMENT, OR SYSTEMS.
FOR SITE OWNED UTILITIES
THIS MATERIAL IS THE EXCLUSIVE PROPERTY OF
SIDOCK GROUP, INC. AND CANNOT BE REPRODUCED,
COPIED, OR USED IN ANY MANNER WITHOUT THE PRIOR
WRITTEN CONSENT OF SIDOCK GROUP, INC. 2022C SH
EE
T
TI
TL
E:
SH
EE
T
ID
EN
TI
FI
CA
TI
O N
NO
PR
O
JE
C
T N
O
FI
LE
N O
./I N
D
EX
C O
D E:
IS
SU
ED
F
O R:
PR
EL
IM
IN
AR
Y
C O
N
ST
R U
C
TI
O N
FI
N
AL
R
EC
O
R D
DA
TE
D R
AW
N
D
ES
IG
N
ED
C H
EC
KE
D
AP
PR
O
VE
D
ST
AT
E O
F M
IC
H
IG
AN
D
EP
AR
TM
EN
T
O F
TE
C
H N
O
LO
G Y, M
AN
AG
EM
EN
T, A N
D B
U D
G
ET
FA
C
IL
IT
IE
S
AN
D
B U
SI
N
ES
S
SE
R
VI
C
ES
A
D M
IN
IS
TR
AT
IO
N
AD
AM
P . L
AR
C
H , R
.A
D
IR
EC
TO
R
DE
SI
G
N
AN
D
CO
NS
TR
UC
TI
O N
DI
VI
SI
O
N
CALL:
PH:
MR. KENDZIORSKI
(989) 657-3026
ALPENA CRTC ENGINEERING
1/
.J
LM
X E1
D
EM
O
LI
TI
O
N P
LA
N
BU
IL
D
IN
G
AL
PE
NA
C.
R.
T.
C.
M
UL
TI
PL
E
BL
DG
S- G
EN
ER
AT
O
R
RE
PL
AC
EM
EN
T D
EP
AR
TM
EN
T O
F M
IL
IT
AR
Y
AN
D
V
ET
ER
AN
S
AF
FA
IR
S
AL
PE
N
A C
.R .T
.C
AL
PE
N A, M I
M
RI
M
RI
LR M
RI
-2 9-
1/2" = 1'-0"
EXISTING/DEMOLITION PLAN - BUILDING 335
N.T.S.
PHOTO - 100KW GENERATOR
N.T.S.
PHOTO - 100KW ATS
N.T.S.
PHOTO - 135KW GENERATOR
N.T.S.
PHOTO - 135KW ATS
SHEET SPECIFIC ELECTRICAL DEMOLITION PLAN NOTES
D1 REMOVE EXISTING GENERATOR AND ASSOCIATED ACCESORIES ENTIRELY. REMOVE AND PATCH ANY LOCATIONS OF ANCHOR BOLTS WHICH ARE NOT SUITABLE FOR REUSE WITH
NEW EQUIPMENT.
D2 REMOVE EXISTING AUTOMATIC TRANSFER SWITCH ENTIRELY. COORDINATE REMOVAL WITH OWNER TO MINIMIZE ANY DOWNTIME FOR EQUIPMENT ASSOCIATED WITH THIS A.T.S.
D3 REMOVE EXISTING CONDUITS FROM GENERATOR TO A.T.S. ENTIRELY.
D4 RETAIN EXISTING UNDERGROUND CONDUITS FROM GENERATOR TO A.T.S. FOR POSSIBLE REUSE. REMOVE CONDUCTORS.
D5 REMOVE HOUSEKEEPING PAD ENTIRELY. NEW CONTINUOUS PAD TO BE POURED TO REPLACE IT.
D6 REMOVE EXISTING NATURAL GAS LINE BACK TO NEAREST METER POINT AND CAP.
N.T.S.
EXISTING RISER DIAGRAM
N.T.S.
EXISTING NOTES
N.T.S.
DEMOLITION NOTES - APPLY TO ALL DEMOLITION SHEETS
DP-2
MAIN DISC
LP-2
DP-1
NEW 100KW
GENERATOR
NEW 80KW
GENERATOR
P1
NEW 400 AMP
A.T.S #1
NEW 225 AMP
A.T.S. #2
NEW S.P.D. NEW S.P.D.
NEW S.P.D.
100KW
LOAD BANK
80KW
LOAD BANK
LOAD BANK/
PORT. GEN.
CONNECTION
CABINET
LOAD BANK/
PORT. GEN.
CONNECTION
CABINET
P4
P6
P5
P7
P8
P10
P11 600 GALLON
FUEL TANK
700 GALLON
FUEL TANK
P10
P9 P8
P7
P6
P2
P3
E
(EXISTING) (EXISTING)
(EXISTING)
(EXISTING)
P12
50 GAL.
DAY
TANK
50 GAL.
DAY
TANK
P13
P14
P15
LOAD BANK CONTROL PANEL
LOAD BANK CONTROL PANEL
DUPLEX
PUMPS
DUPLEX
PUMPS
P9
NEW
100KW
A.T.S
EXIST.
PANEL
'DP-1'
1000A M.L.O.
NEW 100KW
GENERATOR
BLDG 319
EXIST.
PANEL
'LP-1'
NEW 80KW
GENERATOR
MAIN
DISC
FROM
TRANSFORMER
NEW
80KW
A.T.S
EXIST.
PANEL
'DP-2'
BLDG 30
FIRE STATION
MAINTAIN CONDUIT AND CONDUCTORS IF POSSIBLE FOR REUSE
REPLACE CONDUCTORS IF NECESSARY DUE TO LENGTH, DO NOT SPLICE!
NEW
LOAD
BANK/
PORT.
GEN.
CNTRL.
NEW
LOAD
BANK/
PORT.
GEN.
CNTRL.
NEW
LOAD
BANK
NEW
LOAD
BANK
2-1/2" C. - (4) - 350 MCM + #2 GRD.2-1/2" C. - (4) - 350 MCM + #2 GRD.
(1) 3" C. - (4) - 500MCM CU + 1/0 GRD.
(1) 3" C. - (4) - 500MCM CU + 1/0 GRD.
2-1/2" C. - (3) - 350 MCM + #4 GRD.
120/208V
3PH, 4W
120/208V
3PH, 4W
120/208V
3PH, 4W
NEW
S.P.D NEW
S.P.D
NEW
S.P.D
SURGE PROTECTIVE DEVICE TPD MODEL TK-TTLP-3Y208FL (GENERATOR SIDE)
INSTALL WITH SHORTEST CONDUCTOR LENGTH POSSIBLE.
SURGE PROTECTIVE DEVICE TPD MODEL TK-TTLP-3Y208FL (GENERATOR SIDE)
INSTALL WITH SHORTEST CONDUCTOR LENGTH POSSIBLE.
SURGE PROTECTIVE DEVICE TPD MODEL TK-TTLP-3Y208FL
INSTALL WITH SHORTEST CONDUCTOR LENGTH POSSIBLE.
REDUCE FUSE SIZE TO 300A
REPLACES OVERSIZED 135KW GENERATOR
50 GAL
TANK
LARGE EXTERNAL
TANK (SIZE VARIES)
FUEL VENT
ONLY (1) FUEL LINE SHOWN AS EXAMPLE.
(2) LINES (SUPPLY & RETURN REQUIRED)
PLUS (2) CONDUITS, POWER & CONTROLS
ELEVATION VIEW - TYPICAL FOR BOTH UNITS
CEILING
GRADE
ELECTRICAL TO BE RAN 2' BELOW GRADE
SUSPEND FROM CEILING AS REQUIRED TO AVOID
EXISTING CONDUITS,ETC.
FOR SITE OWNED UTILITIES
THIS MATERIAL IS THE EXCLUSIVE PROPERTY OF
SIDOCK GROUP, INC. AND CANNOT BE REPRODUCED,
COPIED, OR USED IN ANY MANNER WITHOUT THE PRIOR
WRITTEN CONSENT OF SIDOCK GROUP, INC. 2022C SH
EE
T
TI
TL
E:
SH
EE
T
ID
EN
TI
FI
CA
TI
O N
NO
PR
O
JE
C
T N
O
FI
LE
N O
./I N
D
EX
C O
D E:
IS
SU
ED
F
O R:
PR
EL
IM
IN
AR
Y
C O
N
ST
R U
C
TI
O N
FI
N
AL
R
EC
O
R D
DA
TE
D R
AW
N
D
ES
IG
N
ED
C H
EC
KE
D
AP
PR
O
VE
D
ST
AT
E O
F M
IC
H
IG
AN
D
EP
AR
TM
EN
T
O F
TE
C
H N
O
LO
G Y, M
AN
AG
EM
EN
T, A N
D B
U D
G
ET
FA
C
IL
IT
IE
S
AN
D
B U
SI
N
ES
S
SE
R
VI
C
ES
A
D M
IN
IS
TR
AT
IO
N
AD
AM
P . L
AR
C
H , R
.A
D
IR
EC
TO
R
DE
SI
G
N
AN
D
CO
NS
TR
UC
TI
O N
DI
VI
SI
O
N
CALL:
PH:
MR. KENDZIORSKI
(989) 657-3026
ALPENA CRTC ENGINEERING
1/
.J
LM
X E2
N
EW
E Q
U
IP
M
EN
T
PL
AN
BU
IL
D
IN
G
AL
PE
NA
C.
R.
T.
C.
M
UL
TI
PL
E
BL
DG
S- G
EN
ER
AT
O
R
RE
PL
AC
EM
EN
T D
EP
AR
TM
EN
T O
F M
IL
IT
AR
Y
AN
D
V
ET
ER
AN
S
AF
FA
IR
S
AL
PE
N
A C
.R .T
.C
AL
PE
N A, M I
M
RI
M
RI
LR M
RI
-2 9-
1/2" = 1'-0"E200
1 NEW EQUIPMENT PLAN - BUILDING 335
SHEET SPECIFIC NEW EQUIPMENT PLAN NOTES
P1 PROVIDE NEW 6" THICK HOUSEKEEPING PAD WITH DIMENSIONS EXCEEDING GENERATOR PLUS DAY TANK BY 2" ON ALL SIDES.
P2 PROVIDE AND INSTALL CUMMINS C80D6C GENERATOR OR APPROVED ALTERNATE AT THIS LOCATION. POSITION TO ALINE WITH EXISTING WALL LOUVER.
P3 PROVIDE AND INSTALL CUMMINS C100D6C GENERATOR OR APPROVED ALTERNATE AT THIS LOCATION. POSITION TO ALINE WITH EXISTING WALL LOUVER.
P4 PROVIDE AND INSTALL CUMMINS BTPCB, 225 AMP, 4 POLE AUTOMATIC TRANSFER SWITCH OR APPROVED EQUAL P5 PROVIDE AND INSTALL CUMMINS BTPCC, 400 AMP, 4 POLE AUTOMATIC TRANSFER SWITCH OR APPROVED EQUAL
P6 PROVIDE NEW PAD WITH DIMENSIONS EXCEEDING DIESEL TANK BY 2" ON ALL SIDES.
P7 PROVIDE TRENCH MINIMUM OF 2' DEEP FROM LOAD BANK TO CONNECTION CABINET FOR CONDUITS FOR POWER AND MONITORING EQUIPMENT.
P8 FUEL LINES TO BE RAN AT GRADE, NOT BURIED.
P9 ROUTE FUEL LINES AT OR NEAR CEILING IN AN ORDERLY FASHION TO AVOID EXISTING CONDUITS, LIGHTS,ETC.
P10 PROVIDE AND INSTALL FOXFAB FFIS-C3-400-TM-U3-GL-ALU-LB CABINET OR APPROVED EQUAL AT THIS LOCATION.
P11 PROVIDE AND INSTALL SHEET METAL TRANSITION FROM GENERATOR TO EXISTING THRU-THE-WALL-LOUVER. UTILIZE DUCT-MATE SILICON PROFLEX OR APPROVED EQUAL FOR TRANSITION TO SHEET METAL TO
ELIMINATE VIBRATION TRANSMISSION.
P12 PROVIDE AND INSTALL 50 GALLON DAY TANK. CONFIRM EXACT ORIENTATION WITH SUPPLIER PRIOR TO BEGINNING WORK.
P13 PROVIDE AND INSTALL (4) 20 AMP, SINGLE POLE BREAKERS IN EXISTING SPACES TO POWER (2) FUEL SYSTEMS AND (2) LOAD BANK/PORTABLE GENERATOR CONTROL CABINETS.
P14 PROVIDE NEW PAD WITH DIMENSIONS EXCEEDING LOAD BANK BY 2" ON ALL SIDES. PROVIDE AND INSTALL AFTRON LOAD BANK MODEL 4100 100KW LOAD BANK OR APPROVED EQUAL WITH MANUAL LOAD
CONTROL PANEL AS SHOWN.
P15 PROVIDE NEW PAD WITH DIMENSIONS EXCEEDING LOAD BANK BY 2" ON ALL SIDES. PROVIDE AND INSTALL AFTRON LOAD BANK MODEL 4100 75KW LOAD BANK OR APPROVED EQUAL WITH MANUAL LOAD
CONTROL PANEL AS SHOWN.
N.T.S.E200
2 NEW EQUIPMENT RISER DIAGRAM
NOTE: LOAD BANK NOT
SHOWN FOR CLARITY ONLY
1/2" = 1'-0"E200 3 Section 1
600A 3P
400A 3P
DP-1
1000A 120/208V 3P 4W
FROM
TRANSFORMER
3P LOAD
BANK
PORTABLE GENERATOR LUGS
3P
80KW
120/208V
3PH, 4W
GENERATOR
GENERATOR BREAKER
LOAD BANK CONTROL
PANEL
LOAD BANK/
PORT. GEN.
CONNECTION
CABINET
200A 3P
200A 3P
DP-2
400A 120/208V 3P 4W
100A 3P
3P LOAD
BANK
PORTABLE GENERATOR LUGS
3P
100KW
120/208V
3PH, 4W
GENERATOR
GENERATOR BREAKER
LOAD BANK CONTROL
PANEL
LOAD BANK/
PORT. GEN.
CONNECTION
CABINET
EXISTING
TO
FIRE DEPT.
BLDG. 370
SEQUENCES OF OPERATION
AUTOMATIC TRANSFER SWITCH
1. NORMAL - UTILITY POWER AVAILABLE. NORMAL SWITCH IN CLOSED POSITION, EMERGENCY SWITCH OPEN AND UTILITY POWERS LOADS. BYPASS SWITCHES OPEN.
2. EMERGENCY - UTILITY POWER UNAVAILABLE. GENERATOR IS POWERED UP, NORMAL SWITCH OPENED AND EMERGENCY SWITCH CLOSED
EMERGENCY GENERATOR POWERS LOADS. BYPASS SWITCHES OPEN.
3. BYPASS - AUTOMATIC TRANSFER SWITCH CONTACTS DISCONNECTED (DRAWN OUT). MANUAL BYPASS SWITCH IS ENERGIZED. AUTOMATIC SWITCH DE-ENERGIZED
FOR TESTING OR SERVICE.
LOAD BANK/PORTABLE GENERATOR CONNECTION CABINET OPERATION
SEQUENCE OF OPERATION (NORMAL LOAD BANK TEST)
1. MAIN CABINET BREAKER OFF. SYSTEM COLD
2. GENERATOR STARTED MANUALLY FROM GENERATOR PANEL.
3. MAIN BREAKER TURNED ON. SYSTEM POWERS UP AND STATUS SHOWN ON CONTROLLER.
4. SYSTEM ARMED AND TIMED OR CONTINUOUS TEST IS SELECTED.
5. OPERATOR STARTS LOAD TEST VIA "START LOAD TEST" PUSHBUTTON.
6. TEST LOAD IS MODULATED AT LOAD BANK CONTROL PANEL.
7. TEST RUNS UNTIL OPERATOR STOPS OR UNIT TIMES OUT (AUTO TEST MODE.)
8. MAIN BREAKER IS SHUT OFF AND SYSTEM IS COLD AND TEST COMPLETE.
9. IF DURING TEST, UTILITY POWER IS LOST, MAIN BREAKER DISENGAGED INSTANTLY AND FULL GENERATOR POWER OUTPUT AVAILABLE TO BUILDING.
SEQUENCE OF OPERATION (PORTABLE GENERATOR CONNECTION)
1. MAIN CABINET BREAKER OFF. SYSTEM COLD. PORTABLE GENERATOR PLUGGED INTO RECEPTACLE.
2. MAIN GENERATOR BREAKER LOCKED OFF.
3. SELECTOR SWITCH TURNED TO "BACK-UP-POWER" MODE.
4. PORTABLE GENERATOR STARTED.
5. MAIN CABINET BREAKER TURNED ON.
BYPASS ISOLATION
TRANSFER SWITCH
BYPASS ISOLATION
TRANSFER SWITCH
4P SW
4P SW
A.T.S.
B.T.S.
4P SW
4P SW
A.T.S.
B.T.S.
E
N
L
E
N
L
PIPE SIZES
3/8" NPT
1/2" NPT
3/4" NPT
1" NPT
1-1/4" NPT
1-1/2" NPT
2" NPT
3" NPT
A B C D E F G H
B D
C
D D B G
B G H
G
H A
A
ENGINE
1" 24 VDC
1" RETURN
FROM ENGINE
1" SUPPLY
TO ENGINE
SPIN-ON REPLACEABLE
ELEMENT 30 MICRON
FILTER
LEVEL CONTROLLER
DAY TANK
(DOUBLE WALLED)
2" STD VENT
3" EMERGENCY VENT
1" NPT FOOT VALVE IN MAIN STORAGE
MAIN TANK
(DOUBLE WALLED)
FUEL RETURN
FUEL SUPPLY1"
1"
CHECK VALVE
SOLENOID VALVE
BALL VALVE
UNION
NOTE: ABOVE DIAGRAM INDICATES THE MAJOR PIPING ELEMENTS IN THE FUEL SYSTEM FOR REMOTE TANKS.
IT IS NOT MEANT TO DETAIL ALL OF THE INSPECTION PORTS, MONITORING OR CONTROL LOCATIONS.
FOR SITE OWNED UTILITIES
THIS MATERIAL IS THE EXCLUSIVE PROPERTY OF
SIDOCK GROUP, INC. AND CANNOT BE REPRODUCED,
COPIED, OR USED IN ANY MANNER WITHOUT THE PRIOR
WRITTEN CONSENT OF SIDOCK GROUP, INC. 2022C SH
EE
T
TI
TL
E:
SH
EE
T
ID
EN
TI
FI
CA
TI
O N
NO
PR
O
JE
C
T N
O
FI
LE
N O
./I N
D
EX
C O
D E:
IS
SU
ED
F
O R:
PR
EL
IM
IN
AR
Y
C O
N
ST
R U
C
TI
O N
FI
N
AL
R
EC
O
R D
DA
TE
D R
AW
N
D
ES
IG
N
ED
C H
EC
KE
D
AP
PR
O
VE
D
ST
AT
E O
F M
IC
H
IG
AN
D
EP
AR
TM
EN
T
O F
TE
C
H N
O
LO
G Y, M
AN
AG
EM
EN
T, A N
D B
U D
G
ET
FA
C
IL
IT
IE
S
AN
D
B U
SI
N
ES
S
SE
R
VI
C
ES
A
D M
IN
IS
TR
AT
IO
N
AD
AM
P . L
AR
C
H , R
.A
D
IR
EC
TO
R
DE
SI
G
N
AN
D
CO
NS
TR
UC
TI
O N
DI
VI
SI
O
N
CALL:
PH:
MR. KENDZIORSKI
(989) 657-3026
ALPENA CRTC ENGINEERING
1/
.J
LM
X E3
O
PE
R
AT
IO
N
AL
D
ET
AI
LS
BU
IL
D
IN
G
AL
PE
NA
C.
R.
T.
C.
M
UL
TI
PL
E
BL
DG
S- G
EN
ER
AT
O
R
RE
PL
AC
EM
EN
T D
EP
AR
TM
EN
T O
F M
IL
IT
AR
Y
AN
D
V
ET
ER
AN
S
AF
FA
IR
S
AL
PE
N
A C
.R .T
.C
AL
PE
N A, M I
M
RI
M
RI
LR M
RI
-2 9-
N.T.S.E300
1 OPERATIONAL ONE LINE DIAGRAM BUILDING 335
N.T.S.E300
2 FUEL SYSTEM PIPING DIAGRAM
| Sheets |
| CS000 - COVER SHEET - BUILDING 335 |
| 23452 - CRTC Generator Replacements - Bldg 335 - Sheet - E100 - DEMOLITION PLAN - BUILDING 335.pdf |
| Sheets |
| CS000 - COVER SHEET - BUILDING 335 |
| E100 - DEMOLITION PLAN - BUILDING 335 |
| E200 - NEW EQUIPMENT PLAN - BUILDING 335 |
| E300 - OPERATIONAL DETAILS - BUILDING 335 |
| 23452 - CRTC Generator Replacements - Bldg 335 - Sheet - E200 - NEW EQUIPMENT PLAN - BUILDING 335.pdf |
| Sheets |
| CS000 - COVER SHEET - BUILDING 335 |
| E100 - DEMOLITION PLAN - BUILDING 335 |
| E200 - NEW EQUIPMENT PLAN - BUILDING 335 |
| E300 - OPERATIONAL DETAILS - BUILDING 335 |
| 23452 - CRTC Generator Replacements - Bldg 335 - Sheet - E300 - OPERATIONAL DETAILS - BUILDING 335.pdf |
| Sheets |
| CS000 - COVER SHEET - BUILDING 335 |
| E100 - DEMOLITION PLAN - BUILDING 335 |
| E200 - NEW EQUIPMENT PLAN - BUILDING 335 |
| E300 - OPERATIONAL DETAILS - BUILDING 335 |
File details come from the government source that posted it. Updated .