This is a Draft Statement of Work (SOW) for construction services related to roofing system replacement at Mann-Grandstaff VA Medical Center in Spokane, Washington. The project (668-24-103) requires the contractor to replace aged roofing systems in Buildings 1, 2, 3, and 31 with a total performance period of 180 calendar days. The scope encompasses labor, materials, tools, equipment, transportation, supervision, and all services necessary to complete the work in accordance with project drawings and specifications. The contractor must review Hazmat survey reports to identify areas requiring abatement. Work must comply with project specifications and drawings, with this SOW taking precedence in case of conflicts.
Key contractual requirements include: the contractor must establish a secured File Transfer Protocol (FTP) site for all electronic submittals, as VA email servers limit files to 5MB per message; deliver as-built drawings and operation and maintenance (O&M) manuals in hard copy 3-ring binders no later than 30 days after substantial completion; coordinate laydown areas with the Contracting Officer (COR) during pre-construction submittal; conduct assessments to determine existing conditions prior to work inception; and provide all equipment and supplies, as no Government-Furnished Equipment will be available. The SOW references attached project drawings, project specifications, and four Hazmat Survey Reports (668-24-103 HAZ B1, B2, B3, and B31) that address hazardous materials in each building.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sources Sought Past Performance Project Data Form.docx | DOCX document | |
| 668-24-103 HAZ B3.pdf | ||
| Draft Specifications.pdf | ||
| 668-24-103 HAZ B31.pdf | ||
| 668-24-103 HAZ B2.pdf | ||
| 668-24-103 HAZ B1.pdf | ||
| Sources Sought Contractor Information Form.docx | DOCX document | |
| 36C26026Q0507.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK FOR CONSTRUCTION SERVICES
Project No. 668-24-103 Replace Buildings 1,2,3, and 31 Roofing Systems Mann-Grandstaff VA Medical Center Spokane, WA Feb 23, 2026
Attachments to this document include the following. Contact the CO if any items are missing.
· Project Drawings
· Project Specifications
· Hazmat Survey Reports
· 668-24-103 HAZ B1
· 668-24-103 HAZ B2
· 668-24-103 HAZ B3
· 668-24-103 HAZ B31
1. General Provide construction services to include labor, materials, tools, equipment, transportation, supervision, and other services necessary for Project 668-24-103, Replace Buildings 1,2,3, and 31 Roofing Systems at the Mann-Grandstaff VA Medical Center, Spokane, Washington. Total project period of performance shall be 180 calendar days.
2. Scope of Work
2.1. This NRM project will replace aged roofing systems in accordance with the project drawings and project specification. Review Hazmat survey reports for areas requiring abatement.
3. Performance of Work
3.1. Where conflicts exist between this SOW and the project specifications or project drawings, this SOW takes precedence.
3.2. Document transmission.
3.2.1. VA email servers limit file sizes to 5MB per message.
3.2.2. Construction Contractor shall provide a secured File Transfer Protocol (FTP) site to transfer all contract electronic submittals. The contractor shall send a corresponding email to the COR stating a file is ready for review for each electronic submittal FTP upload, an automatic email from the FTP site is sufficient. The FTP site shall be accessible by VA staff using Government Furnished Equipment (GFE).
3.3. As-Built Drawings and Operation and Maintenance (O&M) Manual.
3.3.1. The contractor shall deliver the as-built drawings and owner’s manual to the COR no later than thirty (30) days after substantial completion. O&M are to supplied to the COR as a hard copy in 3 ring binders.
3.3.1.1. Owner’s manual shall contain detailed step by step instruction for operation of all equipment as a system.
3.4. Contractor laydown will be coordinated with the COR during pre-construction submittal process. Any references to laydown areas in the project drawings or specifications are not guaranteed.
3.5. The government does not guarantee the accuracy or completeness of any of the information provided in the attachments to this SOW. The contractor shall make assessments to determine existing conditions prior to the inception of work.