DPW_Waldorf_Campus_Preliminary_Draft_Design_Schedule.pdf
PDF 748 KB Posted
- Solicitation number
- 27-006
- Issued by
- Charles County, Maryland
About this file
This is a preliminary draft design schedule for the Department of Public Works Utilities Waldorf Regional Facility project in Charles County, Maryland. The Board of Commissioners is soliciting proposals from qualified architectural and engineering consultants to provide design services for a new DPW Utilities facility on a 10-acre site located at 2660 & 2690 Old Washington Road, Waldorf, MD 20601. The project involves preparing contract drawings, specifications, and obtaining all applicable permits for site development and construction of approximately 63,000 square feet of building space with on-site improvements. The overall design schedule spans 421 days, commencing with a Notice to Proceed on December 14, 2026, and concluding with the issuance of conformed drawings on July 24, 2028.
The design work is structured in two parallel tracks: Stormwater Management and Civil Site Development (330 days) and Building Design (262 days). The Stormwater Management track includes three sequential steps: Concept Stormwater Management Plan (110 days), Site Stormwater Management Plan (90 days), and Development Service Permit review (130 days). The Building Design track encompasses programming and stakeholder meetings (20 days), schematic design with three concepts and presentation (26 days), design development in three phases at 30%, 70%, and 95% completion with presentations and reviews (123 days), building permit review and approval (93 days), and bidding services including the bidding phase and issuance of conformed drawings (90 days). All design phases are scheduled to conclude by December 14, 2027, with bidding services extending through July 24, 2028.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task Name Duration Start Finish
1 DESIGN SCHEDULE 421 days Mon 12/14/26 Mon 7/24/28 2 Notice to Proceed 1 day Mon 12/14/26 Mon 12/14/26 3 Stormwater Management (SWM) & Civil Site Development Schedule 330 days Tue 12/15/26 Mon 3/20/28 4 Concept Stormwater Management (SWM) Plan (Step 1) 110 days Tue 12/15/26 Mon 5/17/27 9 Site Stormwater Management (SWM) Plan (Step 2) 90 days Tue 5/18/27 Mon 9/20/27 14 Development Service Permit (DSP) (Step 3) 130 days Tue 9/21/27 Mon 3/20/28 21 Building Design Schedule 262 days Mon 12/14/26 Tue 12/14/27 22 Programming 20 days Mon 12/14/26 Fri 1/8/27 23 Programming Meetings with Stakeholder 20 days Mon 12/14/26 Fri 1/8/27 24 Schematic Design 26 days Mon 1/11/27 Mon 2/15/27 25 Schematic Design Development (3 Concepts) 20 days Mon 1/11/27 Fri 2/5/27 26 Schematic Design Presentation 1 day Mon 2/8/27 Mon 2/8/27 27 Schematic Design Selection 5 days Tue 2/9/27 Mon 2/15/27 28 Design Development 123 days Tue 2/16/27 Thu 8/5/27 29 30% Design Development 30 days Tue 2/16/27 Mon 3/29/27 30 30% Design Development Presentation 1 day Tue 3/30/27 Tue 3/30/27 31 30% Design Review 10 days Wed 3/31/27 Tue 4/13/27 32 70% Design Development 30 days Wed 4/14/27 Tue 5/25/27 33 70% Design Development Presentation 1 day Wed 5/26/27 Wed 5/26/27 34 70% Design Review 10 days Thu 5/27/27 Wed 6/9/27 35 95% Design Development 30 days Thu 6/10/27 Wed 7/21/27 36 95% Design Development Presentation 1 day Thu 7/22/27 Thu 7/22/27 37 95% Design Review 10 days Fri 7/23/27 Thu 8/5/27 38 Building Permit Review & Approval 93 days Fri 8/6/27 Tue 12/14/27 43 Bidding Services 90 days Tue 3/21/28 Mon 7/24/28 44 Bidding Phase 80 days Tue 3/21/28 Mon 7/10/28 45 Issuance of Conformed Drawings 10 days Tue 7/11/28 Mon 7/24/28
DESIGN SCHEDULE
Notice to Proceed
Stormwater Management (SWM) & Civil Site Development Schedule Concept Stormwater Management (SWM) Plan (Step 1)
Site Stormwater Management (SWM) Plan (Step 2) Development Service Permit (DSP) (Step 3)
Building Design Schedule Programming
Programming Meetings with Stakeholder Schematic Design
Schematic Design Development (3 Concepts) Schematic Design Presentation Schematic Design Selection
Design Development 30% Design Development 30% Design Development Presentation 30% Design Review
70% Design Development 70% Design Development Presentation 70% Design Review
95% Design Development 95% Design Development Presentation 95% Design Review
Building Permit Review & Approval Bidding Services
Bidding Phase Issuance of Conformed Drawings
H1 H2 H1 H2 H1 H2 H1 H2 H1 2026 2027 2028 2029 2030
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Project: Project1.mpp Date: Fri 7/24/26