DOIT AE Selection Procedure Final.docx

DOCX document 36 KB Posted

Attached to
QBS DOIT Professional Fiber Engineering Services
Solicitation number
21-448DOIT-TELEC-B-19877
Issued by
Illinois

About this file

This document outlines the Illinois Department of Innovation and Technology's (DOIT) Qualifications Based Selection (QBS) procedure for securing an Architectural and Engineering (A/E) firm to provide Professional Fiber Engineering Services under an Indefinite Quantity Master Contract. The QBS solicitation will be published on the BidBuy e-procurement system, where registered A/E firms can submit Statements of Interest (SOI) demonstrating their qualifications, experience, and availability to complete the required work. The selected firm will be awarded a contract for the duration of the term, which is not specified. The QBS and SOI will be evaluated by a Review Team based on criteria such as the firm's technical competence, ability to complete the work in the required timeframe, existing workload, and availability of key personnel. The Consultant Selection Committee will then review the ranked firms and select the most qualified firm for contract negotiations.

The contract will be negotiated between the DOIT Project Manager, Coordinator, and Vendor Management Office. The resulting contract will serve as an Indefinite Quantity Master Contract, under which DOIT will release individual Statements of Work as needed. The SOWs will define the specific project requirements, including location, services, prequalification categories, key personnel, and selection criteria. Pricing and financial terms are not included in the document.

View the file

Other files

File Type Posted
B-19877 - Notice of Award Form~1.pdf PDF
B-19877 QBS Rank Order Selection List~1.docx DOCX document
B-19877 Question and Answer Clean.docx DOCX document
B-19877 Question and Answer.docx DOCX document
BEP ADDENDUM for B-19887.xlsx XLSX spreadsheet
CIT2019877 QBS Professional Fiber Engineering Final Addendum 1.docx DOCX document
Forms B~4.docx DOCX document
Pre Submission Call Invitation - Agenda~2.docx DOCX document
Forms A~3.docx DOCX document
Notice of Electronic Submission Only~25.pdf PDF
B-19877 BEP-VBP Utilization Plan.pdf PDF
B-19877 QBS-SOW Professional Fiber Engineering Services Statement of Interest Form -SOI.pdf PDF
B-19877 Question and Answer 3.docx DOCX document
B-19877 BEP-VOSB Vendor Listing~1.xlsx XLSX spreadsheet
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Illinois Department of Innovation and Technology Notice and Selection of Professional Services Process Purpose This procedure identifies the Illinois Department of Innovation and Technology Agency’s (Agency) method of securing a Firm to provide Agency Specific Indefinite Quantity Master Contract for Professional Fiber Engineering Services. The Agency will be seeking an award with one Architectural/ Engineering Firm for the duration of the subsequent contract term.

Scope This procedure applies to the selection of Firms hired to work for the Agency. Professional Service contracts are solicited and awarded in accordance with the Architectural, Engineering and Land Surveying Qualifications Based Selection Act (30 ILCS 535). Illinois Procurement Code (30 ILCS 500) and the Illinois Joint Committee on Administrative Rules (JCAR) (44 ILL. ADMIN. CODE) are applicable to the Professional Services solicitations and all applicable rights and authority vested therein to the Chief Procurement Office – General Services (CPO-GS) are specifically incorporated into all aspects of these procedures.

Definitions:

Agency:Illinois Department of Innovation and Technology
APO:Agency Purchasing Officer
BEP:Business Enterprise Program
BidBuy:E-procurement system that provides the official public notice requesting SOIs regarding the Agency’s SOW.
Contract Manager:The Contract Manager is responsible for management of the subsequent contract from the QBS in conjunction with the Project Manager.
Coordinator:Agency Unit Manager or designee responsible for compiling the Scorecard (Attachment E) along with all appropriate supporting documentation.
CMS:Central Management Services
CPO:Chief Procurement Officer
CSC:Consultant Selection Committee
DOIT:Department of Innovation and Technology
Firm:Any individual, sole proprietorship, firm, partnership, corporation, association, or other legal entity that shows interest in a potential project by supplying a SOI in response to the Agency’s publication of SOW and is permitted by law to practice the profession of architecture, engineering, or land surveying and provide those services.
IDOT:Illinois Department of Transportation
Job Aid:A tool used by the VMO to complete the required steps in BidBuy. The job aid identifies specific selections with BidBuy for the specific procurement method. Job aid #8 for QBS can be found on the CPO’s website under BidBuy training resources.
Procurement:Agency’s Procurement Section staff as designated by the APO.
Procurement File:A file for each SOW that is maintained by the VMO that contains all material related to review and approval of issuing the SOW as prescribed by 30 ILCS 500/20-155. This file is maintained within BidBuy. This material includes but is not limited to: the basis on which the award is made; all submitted statement of interests; all evaluation materials; score sheets; and written determination, approved by the CPO or SPO, setting forth reasoning for the contract award decision.
Project Manager:The Agency subject matter expert (end user) as designated by the Coordinator to manage the project.
Recommended Ranking:A ranking prepared by the VMO Lead based on Scorecards submitted by each member of the Review Team. The firm with the highest total score will rank 1, second highest score will rank 2, and so on and so forth.
Review Team:The Review Team will consist of the Project Manager and two other staff as designated by the Coordinator.
Schedule:VMO, in consultation with Coordinator, will develop a schedule for each SOW. The schedule will include timelines for each step of the process to be completed: solicitation issued, questions due, questions & answers published, submissions due, responsiveness review, review team completes evaluation, coordinator returns score card to the VMO, meeting with CSC, negotiations begin, and contract execution. The schedule will be incorporated in each solicitation so that it is posted to BidBuy.
Scorecard:A scoring sheet completed by each member of the Review Team to evaluate the SOI.
Secretary:Agency Secretary
SOI:Statement of Interest – A form submitted by the Firm in response to a SOW. The SOI includes all information needed to evaluate a firm.
SOW:Scope of Work – A project-specific document that outlines the tasks to be completed including the required prequalification categories. Each SOW will be part of the BidBuy publication.
SPO:State Purchasing Officer
Summary Score Sheet:Score sheet prepared by VMO Lead that identifies all Firms that submitted SOIs and includes the following items: Past SOW selections (including how many projects each Firm has submitted an SOI for and how many SOWs they were awarded contracts); Verification of Firm prequalification; Verification of Firm disclosure forms; Verification of conformance with the SOW submittal requirements; Results of BEP Review; and Recommended Rankings.

Vendor Management Office (VMO): The VMO is the Agency Procurement Office consisting of procurement staff who manage the procurement activities of the Agency and relationships with contracted Vendors.

Solicitation of the Qualifications Based Selection (QBS) and Statement of Interest (SOI) The Qualifications Based Selection (QBS) procurement method allows Agency to evaluate Architectural, Engineering and Land Surveying (AE) Firms qualifications to provide Professional Fiber Engineering Services.

1. Agency has developed a Qualification Based Selection (QBS) solicitation providing a high-level scope of services which will be provided by the AE Firm through the duration of the subsequent contract. The AE Firm will review and complete the QBS Professional Fiber Engineering solicitation which can be found as an attachment within BidBuy. The AE Firm will complete the QBS in its entirety and submit into BidBuy by the BidBuy QBS Bid Submission Due Date.

2. Statement of Interest (SOI) – The AE Firm shall also submit a Statement of Interest (SOI) expressing an interest in the QBS, see BidBuy attachments, with the QBS solicitation which will be used in coordination with QBS to evaluate individual AE Firms for award.

3. The Contract Manager submits the QBS to the Vendor Management Office (VMO) to determine the BEP goal, collate it into the procurement file, then submit to the APO and SPO for review and approval prior to publication in BidBuy. Agency BEP Coordinator will work with CMS BEP on BEP goal setting form and goal review form attaching to the BidBuy requisition. The review of the QBS and the process of determining a BEP goal can (and should) run simultaneously to reduce the total time of the procurement.

4. Upon approval of the BEP goal, the VMO Lead completes the requisition in BidBuy.

5. After approvals of the Requisition, the VMO will convert to Bid. Upon approval of the QBS draft by the APO and SPO, VMO Lead will submit the Bid for APO approval and SPO to publish.

6. VMO will publish the QBS to BidBuy along with the SOI. An email notification will be sent to AE Firms whom are registered under the BidBuy selected NIGP codes. AE Firms registered within BidBuy for those required NIGP categories will receive notification to the AE Firm BidBuy registered email from the BidBuy website.

7. Per the Procurement code (30 ILCS 535/25), the public notice must be advertised for a minimum of 14 days prior to the bid due date.

8. All questions from prospective Firms pertaining to specific work requirements are submitted to the VMO via email and delivered to the Contract Manager by VMO. Technical questions and answers will be summarized and submitted to VMO by the Contract Manager – these require SPO approval to publish. If any questions prompt changes in the QBS, a revised QBS should be prepared for publication as a part of the Q&A amendment. Procedural questions can be answered by the VMO. Upon the SPO’s approval of the questions and answers, VMO Lead will submit in BidBuy for the SPO to publish. When publishing the questions and answers, there must be a minimum of 72 hours prior to the bid due date. In the event there is not 72 hours, the solicitation due date must be extended.

9. Firms prepare their SOI per the QBS and submit via BidBuy as specified in the solicitation document. The following is a list of guidelines/requirements for SOI submittal:

a. Meet the pre-qualifications in the specific categories as identified in the QBS.

b. Demonstrate availability and appropriate qualifications of key personnel of the firms who will perform the work during the term of the subsequent contract.

c. Identify the Firm’s and /or sub-consultant’s current workload and ability to complete the work in the time required.

d. Show the firm’s financial capability.

e. Identify similar work performed by the firm and/or sub-consultants which illustrates the firm’s qualifications relevant to the specific project.

f. Show location of the firm’s and/or sub-consultant’s office(s) in relation to where the work will be performed.

QBS and SOI Scoring

1. The Review Team signs a Statement of Compliance, Confidentiality, and Conflict of Interest Statement (Attachment A) prior to receiving any QBS and SOI documents submitted in response to the QBS. The Coordinator is not involved in any sort of review of the QBS and SOI documents.

2. VMO reviews each Firm’s QBS and SOI for responsiveness.

3. VMO will complete the Summary Score Sheet (Attachment D), minus the Recommended Ranking, with the initial information found in the QBS and SOI for each responding Firm.

4. VMO submits copies of the QBS and SOIs to the Review Team as well as any other back-up information deemed pertinent at the time for each SOI assigned to the Review Team.

5. The Review Team individually and independently reviews every QBS and SOI determined complete by VMO as assigned and completes a Scorecard.

6. After scoring, the Review Team returns the completed and signed Scorecards and all evaluation materials to VMO.

7. VMO reviews each Scorecard, calculates a total score for each firm, and fills in the Recommended Rankings on the Summary Score Sheet.

Firm Selection

1.Selection is based on: Related experience and technical competence of the personnel and experience of the firms and/or sub-consultants proposed; ability to complete the work in the time required, the contractor’s existing workload, and the commitment and availability of key personnel; and the proposed method of accomplishing the project’s objectives.
2.Each member of the CSC signs the Statement of Compliance, Confidentiality, and Conflict of Interest Statement (Attachment A) prior to receiving documents identified in Item 3 of this section.
3.VMO provides the CSC the following:

a) SOW, any addenda and published questions and answers.

b) Copies of the SOI (as reference material only. The CSC is not required to perform a review of the SOIs).

c) Scorecards for each Firm ranked 1 through 3.

d) Summary Score Sheet with Recommended Rankings.

4.VMO Lead and Agency Procurement Officer convenes a meeting of the CSC.
5.The CSC reviews all material provided and deliberates to select the most qualified Firm. A silent vote is held to rank the firms in order from first to third. Each member of the CSC will complete the Ballot (Attachment B) independently. The APO will collect all Ballots and all evaluation materials from the CSC members.
6.VMO will compile the ballots and complete Attachment C to record the votes. Five points are assigned for each 1st place designation, 3 points are assigned for each 2nd place designation and 1 point is assigned for 3rd place designation. The Agency will enter into contract negotiations with the top ranked firm but if satisfactory contract terms cannot be agreed upon, the Agency will move on to the second and then potentially the third ranked firm.

Contract Negotiations

1.The Project Manager, Coordinator and VMO negotiate a contract with the selected Firm.
2.During the negotiations, the Project Manager compares the list of key personnel, list of sub-consultants and list of BEP/DBE sub-consultants as identified in the SOI to the final contract and documents any changes made and the reasons for them. All changes must be approved by VMO and SPO.

3. Upon written APO approval, the Notice of Award is published to BidBuy.

Statement of Work (SOW)

1.After AE is awarded and the Agency Specific Indefinite Quantity Master Contract is entered into, the subsequent SOWs from the Agency Specific Indefinite Quantity Master Contract are required to be processed within BidBuy as a release off master contract.
2.The parties will work together to develop and process SOWs which include project start dates that ensure there is enough time for plan development, design, review, construction to meet the scheduled completion date of the SOW. The BidBuy releases will include both the SOW and Quote/ Financials of the project.
2.The Project Manager develops a SOW along with accompanying quote for each project that will be released from the Agency Specific Indefinite Quantity Master Contract in BidBuy. This description should include, but is not limited to:
a.Location of work area, including the site address
b.Description of services required
c.Pre-qualification categories required of the Firm
d.Key personnel qualifications required to complete work
e.The minimum information that should be included in the SOI
f.Key dates and information (Due dates, potential site visits, SOW question procedure, schedule for evaluation process etc.)
g.Selection criteria
h.Project Quote/ Financials

ATTACHMENT A

Statement of Compliance, Confidentiality, and Conflict of Interest form https://www2.illinois.gov/cpo/general/Pages/SolicitationandContractTemplates.aspx

ATTACHMENT B

Ballot

Firm
Ranking

CSC member name: _____________________________________ CSC member signature: __________________________________ Date: _________________________________________________

ATTACHMENT C

VOTE TOTALS

FIRM
NO. OF 1ST PLACE VOTES (5 POINTS PER VOTE)
NO. OF 2ND PLACE VOTES (3 POINTS PER VOTE)
NO. OF 3RD PLACE VOTES (1 PONT PER VOTE)
TOTAL POINTS

ATTACHMENT D

SUMMARY SCORE SHEET

Firm
Pre-Qualification
Disclosure Forms
Responsive
# of Past Responsive Submittals
# of Contracts Awarded
BEP Commitment
Recommended Ranking

Yes ☐ No ☐ Yes ☐ No ☐ Yes ☐

Yes ☐

Yes ☐ No ☐ Yes ☐

Yes ☐

Yes ☐ No ☐ Yes ☐

Yes ☐

Yes ☐ No ☐ Yes ☐

Yes ☐

Yes ☐ No ☐ Yes ☐