Lyburn (Maynard) Drainage Project Summary

This construction specification document is issued by the State of West Virginia Department of Environmental Protection (WVDEP), Abandoned Mine Lands and Reclamation division, for the Lyburn (Maynard) Drainage project located in Logan County, West Virginia. The project encompasses construction of a retaining wall and drainage controls for a residential property affected by landslide and drainage issues. Primary work includes installation of sediment control measures, construction entrances, a temporary stream crossing, modular retaining wall installation, drainage infrastructure, and revegetation of disturbed areas. The contractor is responsible for all surveying, layout establishment, material procurement, and delivery. The project requires mobilization and demobilization, site preparation including clearing and grubbing, erosion and sediment control installation, drainage structure construction, unclassified excavation, and revegetation. Key specifications mandate that mobilization and demobilization costs cannot exceed 10 percent of total bid, construction layout costs cannot exceed 5 percent, and quality control costs cannot exceed 3 percent of the total project bid amount. Site preparation costs cannot exceed 10 percent of the total bid.

The contractor assumes responsibility as Co-Applicant #1 under the WV/NPDES Storm Water Construction General Permit (No. WV0115924), requiring completion of required co-applicant documentation prior to notice to proceed issuance. The WVDEP retains responsibility for permit modification and annual renewal fees until final project inspection. All borrow and disposal areas require prior WVDEP approval and compliance with National Environmental Policy Act requirements. The contractor must obtain all necessary permits, including Water Quality Certification and burning permits, and is responsible for costs associated with permit violations or fines resulting from contractor negligence. Payment is structured with mobilization reimbursement split 50/50 (one-half upon contract initiation and one-half upon project completion), while construction layout payment occurs 50 percent upon layout completion and 50 percent upon as-built plan approval. The project requires comprehensive as-built documentation in both digital and paper formats, certified by a licensed West Virginia Land Surveyor, prior to final inspection.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION SPECIFICATIONS

Lyburn (Maynard) Drainage

LOGAN COUNTY, WEST VIRGINIA

STATE OF WEST VIRGINIA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

ABANDONED MINE LANDS AND RECLAMATION

July 2016

TABLE OF CONTENTS

SECTION PAGE

I. SPECIAL PROVISIONS

I. Location/Site Description

II. Scope of Work

III. Borrow (Disposal) Areas

IV. Disposal of Unsuitable Material

V. Permits, Licenses, and Fees

VI. NPDES Stormwater Requirements

VII. Construction Sign

II. TECHNICAL SPECIFICATIONS

1.0 Mobilization and Demobilization

2.0 Construction Layout

3.0 Quality Control

4.0 Site Preparation

5.0 Erosion and Sediment Control

6.0 Revegetation

7.0 Drainage Structures

8.0 Unclassified Excavation

9.0 Modular Retaining Wall

10.0 Utilities

11.0 Traffic Control

Lyburn (Maynard) Drainage

I. SPECIAL PROVISIONS

I. LOCATION / SITE DESCRIPTION

The Lyburn (Maynard) Drainage project is located on Madison Creek (Rt. 10/17) near the community of Lyburn in Logan County, WV. The site consists of a slide and drainage behind a residence. The project will consist of the construction of a retaining wall and drainage controls.

Directions to site:

Directions to Site: From Charleston, take 119S to Logan Exit; Follow Rt. 73 to Rt. 10S;

Cross bridge entering Logan, stay to Right & continue on Rt. 10S for 9.8 miles; Turn

Right onto Rich Creek Road and continue 0.1 mile; Turn Left onto Rich Creek Rd., cross railroad tracks, continue straight onto Madison Creek Road for 2.1 miles (Stay Left at

Guyandotte River Rd); Turn Left & go up driveway at 2125 Madison Creek Rd.

The GPS location is as follows: 37° 46’ 36.70” 81° 57’ 6.40”

II. SCOPE OF WORK

The work covered by the Special Provisions and Technical Specifications consists of furnishing all labor, plant, power, equipment and supplies, and performing all operations necessary for the completion of the project. The Contractor shall perform all operations necessary for:

providing sediment control as shown on the plans;

Install Construction Entrances; provide and install (temporary stream crossing.

(To be removed upon completion);

Construct a modular retaining wall as shown on the plans;

Provide drainage;

Re-grade and re-vegetate all disturbed areas.

The Contractor shall also be responsible for surveying, including establishing construction baseline, measuring and developing all completed quantities on the job, and the ordering, purchase and delivery of any and all materials required for construction or required for development of support areas. The Contractor shall perform all other operations as incidental to the program as specified herein.

III. BORROW (DISPOSAL) AREAS

All borrow (disposal) areas must be approved by WVDEP. Should the Contractor decide to obtain and utilize any borrow areas outside of construction limits, or move material from one property owner to another, unless designated on the plans, the Contractor shall be responsible to obtain from the property owner(s) of the borrow areas, all necessary rights of entry, including rights of entry for WVDEP and OSMRE for inspection purposes. The said rights of entry agreement must state that the property owner(s) indemnify and hold harmless the WVDEP for Contractor’s action for any injury or damages whatsoever resulting from the use of the property.

The Contractor also shall submit a borrow/disposal area reclamation plan for prior approval by WVDEP. The Contractor shall observe the following NEPA compliance schedule relative to selecting and utilizing any off site borrow areas and/or any waste disposal areas.

a. No borrow (disposal) site operations will affect a site listed in, eligible for or proposed to be listed in the National Register of Historic Places.

b. No borrow (disposal) operations will be located within one-quarter mile of any federally listed established or prospective component of the National Wild and

Scenic River System under 16 USC 1274 and 1276.

c. Borrow (disposal) site operations will not cause a significant encroachment within the base floodplain (CE.O. 11988: Floodplain Management).

d. Borrow (disposal) site operations will not be located in or affect a critical habitat of a federally listed endangered or threatened species under 16 USC 1531, et. seq.

e. No borrow (disposal) operations will occur in wetland areas which are designated by appropriate agencies.

f. Borrow (disposal) site operations will be consistent with any approved plans governing ambient air quality.

g. Adherence to these mitigation measures does not relieve the Contractor of the obligation or responsibility to obtain any other federal, state, or local approvals required to use borrow (disposal) areas and conduct such activities.

h. Documentation: Copies of borrow (disposal) site approvals and concurrences will be submitted to the WVDEP prior to the commencement of reclamation activities.

i. Site Monitoring: Borrow (disposal) activities will be monitored by the state to ensure compliance with contractual requirements, applicable federal, state, and local laws, and any permit conditions.

IV. DISPOSAL OF UNSUITABLE MATERIAL

All waste areas shall be obtained in accordance with Special Provisions Section III

(Borrow/Disposal Areas) of these specifications. All unsuitable materials (wood, trash, debris, and garbage) as determined by the Engineer shall be wasted by the Contractor, at his/her expense, outside the limits of work conforming to the requirements of Sections 4.3.8 of these Specifications. Wood may be burned in conformity with Sections 4.3.7 of these

Specifications.

The Contractor shall observe the NEPA compliance schedule relative to selecting and utilizing any off-site disposal areas in accordance with Special Provisions Section III of these Specifications.

V. PERMITS, LICENSES AND FEES

The Contractor shall procure all permits and licenses, pay all charges and fees, and give all notices necessary and incidental to the due and lawful prosecution of the work. Permits required for this project may include but not be limited to: Water Quality Certification from WVDEP and burning permits from WVDNR and WVDEP Office of Air Quality. A copy of the permit/permits as procured shall be furnished to the Owner prior to initiation of the work under this Contract. The WVDEP will obtain the Permits (MM 109 Form) from

WVDOH and NPDES from WVDEP. Contractor shall be responsible for any Stream

Activity Permits necessary to complete the project work.

VI. NPDES STORMWATER REQUIREMENTS

The WVDEP-AML has obtained a Construction Storm Water General Permit for this project from WVDEP Division of Water and Waste Management (WVDEP DWWM). The registration for this reclamation project will be modified to include the Contractor as Co-

Applicant #1, with the WVDEP-AML being Co-Applicant #2. As such, the Contractor shall assume responsibility for compliance with the terms and conditions of the permit including modifications and any future correspondence such as registration renewal invoices, inspection reports, and notices of violation shall be forwarded to the Contractor.

Upon award of the contract, the Contractor shall complete a Co-Applicant #1 signature page and submit the completed form to WVDEP-AML prior to scheduling a Pre-

Construction Conference.

Upon receipt of the completed form, WVDEP-AML will request the WVDEP DWWM to modify the existing NPDES registration for this project to make the Contractor the Co-

Applicant #1 to the permit.

The WVDEP DWWM will notify the Contractor and WVDEP-AML when the successful transfer of registration under WV/NPDES Storm Water Construction General Permit

(No.WV0115924) is completed. A Notice to Proceed will not be issued until the contractor signs the co-applicant form and submits to the Office of Abandoned Mine Lands. Once the transfer has been completed, the WVDEP will continue to be responsible for any modification fees and annual renewal fees incurred up until the date of the final inspection of the project that occurs after completion of construction activities at the site. The

Contractor shall be responsible for any and all costs associated with violations and fines assessed against the project that are a result of the Contractor’s negligence, carelessness, or failure to install permanent controls as part of the work as scheduled.

The Contractor shall apply for a Notice of Termination (NOT) from WVDEP DWWM via the Construction Storm Water website http://www.dep.wv.gov/Programs/stormwater/csw/Documents/Construction upon completion of construction activities at the site. The NOT shall be issued by WVDEP

DWWM upon completion of the project. The Contractor will continue to be bound by the terms and conditions of the permit until the NOT has been approved by WVDEP

DWWM. Once the project is complete, the Contractor will still bear responsibility for the

NPDES registration until a NOT is received from the WVDEP DWWM.

http://www.dep.wv.gov/Programs/stormwater/csw/Documents/Construction

VII. CONSTRUCTION SIGN

1. Work Required.

The work to be performed under this Section consists of providing all labor, material and equipment necessary to install a project sign as indicated on the detail included herein and as specified herein.

2. Materials.

(a) Sign face shall be 3/4" Marine Exterior plywood or aluminum or composite material. Posts and cross-brace shall be No. 2 Grade Pine or Fir, kiln dried and pressure treated.

(b) Hardware:

(1) All hardware shall be manufactured from good, commercial-quality material and meet all applicable ASTM standards.

(2) Spikes and nails shall be common wire-type and shall meet AISI steel specifications 1010 or 1020.

(3) All hardware shall be hot-dip galvanized in accordance with

ASTM A-153.

3 Execution.

(a) Project Sign. The sign board shall be cut to the dimensions shown on the detail herein. The sign shall painted with one (1) coat of primer and two (2) coats of white enamel. All exterior cut edges shall be smooth sanded prior to painting.

All edges shall be double primed. The letters, border and strips shall be painted as shown on the detail drawing. Posts and cross-brace shall be painted with two

(2) finished coats of brown enamel.

The Contractor shall bolt the sign to posts and provide required cross-bracing.

The posts and sign shall be erected and posts set in gravel base, as shown on the drawings. One (1) sign is required and is to be located at the discretion of the

Inspector.

(b) Payment. Payment for the work which shall include installation of the project sign shall be part of the lump-sum bid for "Mobilization".

II. TECHNICAL SPECIFICATIONS

1.0 MOBILIZATION AND DEMOBILIZATION

1.1 Description

This work shall consist of the performance of construction preparatory operations, including the movement of personnel and equipment to the project sites and for the establishment of the Contractor’s offices, buildings and other facilities including the construction of all temporary access roads as necessary to begin work on a substantial phase of the contract. The location of the Contractor’s office to be established shall be approved by WVDEP. It also shall include all demobilization activities involving the removal from the sites of all plant, equipment, supplies and personnel after completion of the work including cleanup of all rubbish and waste materials generated during the construction of this project and restoration of any damage to existing site improvements resulting from the

Contractor’s activities at the site. This item shall also include the installation of the project sign at the beginning of the project and the removal of the sign prior to the Final Inspection.

All equipment and material storage areas shall be approved by WVDEP.

Upon receipt of a notice to proceed, the Contractor shall initiate and complete measures necessary to commence the work. Mobilization shall also consist of delivering to the site and assembling in working order all necessary equipment, materials, and supplies to be furnished by the Contractor to complete the work.

Demobilization shall consist of the removal from the site of all the Contractor’s equipment and materials after completion of the work and cleanup of the site. Work shall be done to the satisfaction of the Regional Engineer.

1.2 Method of Measurement

The method of measurement will be per lump sum.

1.3 Basis of Payment

The bid for “Mobilization and Demobilization” shall be a lump sum and cannot be more than 10% of the TOTAL AMOUNT BID for the project. Partial payments will be as follows:

(a) One-half of the amount bid will be released to the Contractor with the first estimate payable, not less than 15 days after the start of work at the project site.

(b) The final one-half of the amount bid shall be released with the last estimate payable after the work is accepted by the WVDEP and after all Final Inspection submittals are received and approved by WVDEP.

Nothing herein shall be construed to limit or preclude partial payments otherwise provided for by the contract. No deduction will be made nor will any increase be made, in the lump sum mobilization and demobilization item amount regardless of decreases or increases in the final total contract amount or for any other cause.

1.4 Pay Item

Item 1.0 “Mobilization and Demobilization” per lump sum cannot be more than 10% of the

TOTAL AMOUNT BID for the project.

2.0 CONSTRUCTION LAYOUT

2.1 Description

This item consists of furnishing, placing, and maintaining construction layout stakes, (based on the original baselines in the plans), necessary for the proper performance of the work under this contract including borrow/waste areas. It shall further consist of determining the exact units of measure for payment. It also consists of checking and making any field adjustment to the plan alignment, grades and elevations as considered necessary by the Engineer. Additionally, this item shall also include the preparation of

“As-Built” Plans including the Reclamation Plan and any others specifically requested by the WVDEP. All of these “As-Built” Plans shall be provided prior to the Final Inspection

Meeting. This item will be paid according to the following schedule: up to fifty percent of the total bid amount of this item will be released for payment when all required layout work is completed. The remaining 50% will be paid on the final invoice once the As-Builts are submitted and approved.

2.2 Materials

Conventional survey stakes, hubs, batter boards, flagging, templates, straightedges and other devices necessary for laying out all parts of the work.

2.3 Construction Methods

2.3.1 The Contractor shall be responsible for the proper layout of the work. The Owner will provide the Contractor with survey information regarding the baselines and the existing surface features shown on the Construction Drawings. The Contractor shall make all calculations involved and shall furnish and place all layout stakes.

2.3.2 The Contractor shall provide field forces and shall set all additional stakes as needed, such as offset stakes, reference point stakes, slope stakes, grade stakes, stakes for drainage, or other structures, supplementary bench marks, and any other horizontal or vertical controls necessary to secure a correct layout of the work including the re-establishment of the survey and construction baselines (as necessary), as shown on the Construction Drawings.

2.3.3 The Contractor shall be responsible for assuring the layout staking work is in conformance to the lines, grades, elevations, dimensions, and locations shown on the Construction Drawings or as required by the Engineer. The Contractor shall furnish a copy of his/her survey records for review by the Engineer and for the

Owner's permanent file. These records shall be furnished as they are completed during the progress of the work.

Any inspection or review of the Contractor's layout by the Engineer and the acceptance of all or any part of it shall not relieve the Contractor of his/her responsibility to secure the proper dimensions, grades, and elevations of the several parts of the work.

2.3.4 The Contractor shall exercise care in the preservation of stakes and benchmarks, including existing property line markers, and shall have them reset at his/her expense when any are damaged, lost, displaced or removed.

The Contractor shall use competent personnel and suitable equipment for the layout work required and shall provide that it be done under the supervision of, or directed by, a Licensed Land Surveyor registered in the State of West Virginia.

As the survey is completed, the Licensed Land Surveyor shall certify that the site layout is complete for all necessary grades (both cut and fill), location and grades of all ditches, all cross-sections related to cut-fill where grade lines are necessary for construction and or billing. This layout shall include location stakes and cut-fill lines marked on the stakes for each pre-manufactured or formed on site structures (manholes, drop inlets, headwalls, etc.). The layout shall also include centerline stake with cut-fill lines for each channel and any areas of excavation and re-grade. The certified layout and cross-sections surveyed must be submitted to the WVDEP for approval prior to beginning construction for each item.

2.3.5 As-Built plans shall be provided to the WVDEP prior to the Final Inspection

Meeting. The As-Builts shall include two discs each of the plans in PDF and

AutoCAD 2007-2014 format on CD-ROM or DVD and one paper copy of the plans with the same size and scale as contained on the original plans. The As-

Builts Shall include the following:

1. The As-Builts shall show all pay items remaining on site post construction.

2. The As-Builts shall show all horizontal and vertical dimensions of all installed components (i.e. pipes, drop inlets, mine seals, drainage channels, splash pads and manholes) as well as surveyed locations of the installed structures..

3. Cut-fill sections shall have the area of the section marked by the section for easier calculation.

4. The As-Builts shall have the lines on the plans shown in either color or line type to distinguish between our original plan lines, the contractor’s original survey lines and the final grade lines. This will apply for all cross-sections on the project.

5. All waste and borrow areas shown on the As-Builts.

6. All work completed by the Licensed Land Surveyor on the As-Builts must be certified by the Licensed Land Surveyor as to completeness and accuracy of the plan submittal.

7. As-builts must show total quantities for all items on the project. The format shall be in a tabular form.

2.4 Measurement and Payment

Measurement and payment for furnishing, setting, maintaining, and resetting the stakes when necessary, and for furnishing all engineering personnel, equipment, materials, and all incidentals thereto, shall be by the lump sum bid for “Construction Layout”. The lump sum payment also shall include the cost for providing the Engineer pre- and post- construction ground line cross-sections for all disturbed or re-graded areas including borrow areas and

“As-Built” Plans as described herein. Said lump sum bid cannot be more than 5% of the

TOTAL AMOUNT BID for the project. Neither deduction nor increase will be made in the lump sum “Construction Layout” item amount regardless of decreases or increases in the final total contract amount or for any other cause. This item will be paid according to the following schedule: up to fifty percent of the total bid amount of this item will be released for payment when all required layout work is completed.

The remaining fifty percent will be paid on the final invoice once the As-Builts are submitted and approved.

2.5 Pay Item

Item 2.0, “Construction Layout”, per lump sum cannot be more than 5% of the TOTAL

AMOUNT BID for the project.

3.0 QUALITY CONTROL

3.1 Description

This work shall consist of testing for verification that the materials supplied and the work performed are in accordance with these specifications. When there is a discrepancy between the Plans and Specifications on this project the following hierarch of documents shall apply:

1. Any and all addendums that were generated for the project either before or after construction began.

2. Plans shall be the document that shall be used in places where discrepancies occur between the Plans and Specifications.

3. The Specifications shall apply in all areas of agreement with the Plans.

3.2 Materials

3.2.1 The Contractor shall submit a minimum of two (2) copies of shop drawings, catalog cuts and material certifications (as applicable) to the Engineer for all offsite materials to be incorporated into the work. Written approval from the Engineer will be required prior to incorporation of these items into the work.

3.2.2 The Contractor shall submit at least two (2) copies of the results of all tests conducted on in-situ material, concrete and grout to be used in this project.

1. As a minimum, the compaction tests will include moisture content & density tests of the soil in accordance with the provisions of ASTM D698 (Standard

Proctor) field density tests following compaction. A new Standard Proctor will be run when soil type changes occur on site and/or at the direction of the

Engineer or his representative.

2. Soil tests to determine the lime and nutrient requirements of the areas to be re-vegetated.

3. Compressive strength test for grout in accordance with ASTM C109, and for concrete in accordance with ASTM C31 & C39.

3.2.3 Tests Required

Pipe line Compaction Testing for backfill material density

Slope fill Compaction Testing for backfill material density

Soil Test As needed to determine Nutrient tests NPK

Material Certification Manufacture certification on all materials on project

3.3 Construction Methods

3.3.1 The Contractor shall furnish the services of his own testing laboratory or select an independent testing laboratory, as long as the laboratory is under the direct supervision of a Registered Professional Civil Engineer. The laboratory must be approved by the Owner.

The Contractor shall furnish a certified technician to perform the required testing at the project site. The technician shall submit a copy of his certification and a copy of that certification shall be submitted WVDEP at the Pre-Construction Conference.

The technician shall be responsible for chain of custody of any samples that must leave the site.

3.3.2 Testing for compaction, soil nutrient and lime requirements for soil, compressive strength tests for concrete and grout, shall be performed as required by these specifications andor ordered by the Engineer or his representative in writing. The

Engineer will determine the locations and time of any testing herein specified and the need and extent of any testing in addition to that which is herein specified.

3.3.3 The contractor shall be responsible for performing laboratory tests of the coal, mine spoil, and any natural soil to identify the compaction requirements for their use as fill and cover material, respectively. In addition, field density tests shall be performed in accordance with the Construction Specifications. All test results shall be submitted to the Engineer for approval of compaction criteria prior to compacting the fill material and after fill material is placed to verify that the required compaction is obtained.

3.3.4 Only new and first class materials, which conform to the requirements of these

Specifications, shall be used unless specified otherwise. When requested by the

Owner, the Contractor shall furnish a written statement of the origin, composition, and manufacturer of any or all materials (manufactured or produced) that are to be used in the work. The sources of supply of each material used shall be approved by the Engineer before delivery is started. If, at any time, sources previously approved fail to produce materials acceptable to the Owner, the Contractor shall furnish materials from other approved sources.

3.4 Method of Measurement

The method of measurement for quality control work done as described above will be on a lump sum basis.

3.5 Basis of Payment

The quantity of quality control work done will be paid at the contract lump sum price bid for this item. Said lump sum bid cannot be more than 3% of the TOTAL AMOUNT BID for the project. Nothing herein shall be construed to limit or preclude partial payments on this item up to 100% of the bid amount. No deduction or increase shall be made in the lump sum “Quality Control” item amount regardless of decreases or increases in the final total contract amount or for any other cause.

3.6 Pay Item

Item 3.0, “Quality Control”, per lump sum cannot be more than 3% of the TOTAL

AMOUNT BID for the project.

4.0 SITE PREPARATION

4.1 Description

4.1.1 Clearing & Grubbing

Work performed under this section shall include the removal and disposal of all trees, stumps, shrubs and any other vegetation, wood, debris, garbage of any nature from those areas specified below and/or shown on the plans and/or any other areas as approved by WVDEP. This work shall also include the preservation from injury to all vegetation, utilities or other objects to remain as well as all other ancillary work as described.

4.1.2 Temporary Stream Crossing

A temporary stream crossing shall be installed to access this site. The existing driveway and bridge are not to be used for construction. Two (2) 24” pipe culverts shall be installed for construction access as shown on the plans and details. The contractor shall provide all necessary materials, equipment, and labor to install the temporary stream crossing. Stream crossing shall be removed upon completion of the project. Associated cost shall be included in the temporary construction entrance. (See Section 5.2.2) The pipe is considered incidental to the stream crossing entrance and shall be disposed of offsite after project completion.

4.1.3 Gravel Drive Rehabilitation

The Gravel Drive Rehabilitation roads shall be covered with a layer of Class I crusher run stone. In areas that will not support the stone due to soft conditions, stabilization fabric will be required. Re-grading of any areas where stone is not required but inside of the construction limits.

4.1.4 Spill Containment Area

Spill containment measures shall be used for fuel and lubricant storage areas. All containers, barrels, buckets, cans, etc., are to be legally disposed of offsite. Used lubricants are to be disposed of according to state law to minimize pollution to the local surface and ground water supplies. Spills are the responsibility of the

Contractor and need immediate clean up and maintained at no expense to the

State. Fuel tanks manufactured with secondary containment are desirable; the minimum secondary containment shall be 110 percent.

4.2 Materials

4.2.1 Any equipment and construction materials required for clearing, grubbing, grading and stone placement.

4.2.2 Stone to be placed for “Gravel Drive Rehabilitation” shall conform to the requirements for Class 1 Aggregate. The Gravel Drive Rehabilitation shall be covered with a layer of Class 1 Aggregate as shown on the plans or as designated by the Engineer.

4.2.3 The temporary stream crossing shall use 24” Steel casing and #1 stone for the backfill. Both sides of the crossing shall be lined with standard silt fence.

4.3 Construction Methods

4.3.1 The specific areas to be cleared and grubbed are as shown on the Contract

Drawings and are generally described as, but not limited to, those specific areas of excavation, backfill, soil borrow or drainage structure installation.

4.3.2 The Contractor shall clear the site within the limits of the areas to be regraded. The

WVDEP shall exercise control over clearing and shall designate all trees, plants and other objects to be removed or to remain.

4.3.3 Clearing and grubbing shall be completed prior to initiation of earthwork operations only to the extent necessary to complete the work. The Contractor shall confine his operations strictly to required areas. If he clears and grubs beyond the required areas, whether knowingly or accidentally, he shall, at his expense, replant and otherwise restore all areas outside the limit lines to a condition equal to that existing prior to start of work.

4.3.4 All timber eight (8) inches in diameter and larger at stump height shall be saw cut prior to grubbing operations. Timber shall be topped with the branches removed and stacked and stockpiled in an appropriate manner in an accessible location approved by the WVDEP on the property from which it was cut. Timber to be stockpiled shall not be pushed down by equipment prior to being cut nor can it be indiscriminately shoved into a stockpile.

4.3.5 All stumps, roots, buried logs and brush shall be removed. Grass, however, may be incorporated into the resoiling material. Taproots and other projections over 1½ inches in diameter shall be grubbed out to a depth of at least ten (10) inches below the planned subgrade or slope elevation. All holes remaining after the grubbing operation shall have the sides broken down to flatten out the slopes, and shall be filled with suitable materials, moistened and properly compacted.

4.3.6 Cleared and grubbed areas shall be worked such that positive drainage is provided to prevent ponding of water except for the purpose of sediment control sumps as approved by the WVDEP.

4.3.7 All organic material shall be burned completely to ash or otherwise removed from the site and disposed of in a manner approved by the WVDEP. Burning of the combustible material will not be permitted on or near refuse, mine portals or within close proximity to coal seams, residence, structures or utilities. The

Contractor shall obtain all permits and licenses required prior to burning the material. A plan showing the location of material to be burned and all fire control measures to be implemented, including copies of permits and licenses, shall be submitted to the WVDEP’s representative at the site for approval. If a permit cannot be obtained because of the conditions stated above the tree top and stumps can be chipped or disposed of offsite to an approved location.

4.3.8 All other materials generated from required clearing and grubbing operations shall be removed and disposed of by the Contractor. All garbage, construction debris, mining debris, etc., shall be disposed of in approved waste areas or landfills

(disposal tickets must be furnished to WVDEP). It shall be the responsibility of the Contractor to obtain, at no expense to the WVDEP, all necessary waste and borrow areas or landfills for the disposal of waste materials in accordance with any applicable local, state, and/or federal regulations including compliance with

NEPA requirements (See Section VII for NEPA Compliance Schedule). All waste and borrow areas must be approved by the WVDEP and the Contractor must provide a reclamation plan for approval. In addition, for all waste and borrow areas outside the construction limits, the Contractor must obtain from the property owner a right-of-entry agreement in which the property owner indemnifies and holds the WVDEP harmless from any injury or damages whatsoever resulting from the use of the property.

4.3.9 It shall be the sole responsibility of the Contractor to correctly locate and avoid all underground, on-ground, and overhead utilities, facilities and other structures and constructions, and for that purpose, shall employ all necessary precautions and methods to insure avoidance of and damage to such constructions. In the event damage does occur, the Contractor shall notify the affected Owner and the

WVDEP immediately and make or have made all necessary repairs and bear the expense thereof and resulting damage caused thereby.

4.3.10 Should offsite disposal or borrow be necessary, the Contractor shall observe the

NEPA Compliance Schedule as per Section III of the Special Provisions.

4.3.11 Existing site access roads shall provide safe, all-weather access to the site. These existing roads, including stoned and paved roads, shall be maintained during construction and left in a better than or equal to condition. The Contractor is responsible for locating and avoiding all underground and overhead utilities and constructions during access road grading and maintenance.

4.3.12 Stone to be placed for “Gravel Drive Rehabilitation” shall conform to the requirements for Class 1 Aggregate. The Gravel Drive Rehabilitation shall be covered with a layer of Class 1 Aggregate.

4.3.13 The temporary stream crossing shall be constructed as shown on the plans. A

West Virginia Public Lands permit will be required to install the crossing.

4.3.14 Any existing property markers disturbed or removed during construction activities shall be replaced accurately and to an “as good as” or “better than” condition and as approved by the WVDEP. This work will be paid under Section 2.0

Construction Layout of these Specifications.

4.4 Method of Measurement

4.4.1 There shall be no measurement of the “Site Preparation” item as it is a lump sum.

4.4.2 Gravel Drive Rehabilitation shall be by ton based upon weigh tickets from the commercial supplier of the stone that is delivered and placed at the locations identified on the plan drawings.

4.4.3 The Temporary Stream Crossing shall be paid as a lump sum. This shall include all material required, labor and equipment to install and remove at project completion as shown on the plans.

4.5 Basis of Payment

4.5.1 The “Site Preparation” item shall be paid at the bid lump sum price. The amount shall not exceed 10% of the TOTAL AMOUNT BID for each bid. Payment shall be full compensation for doing all the work herein prescribed in a workmanlike and acceptable manner; including the furnishing of all labor, materials, tools, equipment, supplies, and incidental necessary to complete the work. This includes all clearing grubbing and demolition required on the project site.

No deduction will be made, nor will any increase be made, in the lump sum “Site

Preparation” amount regardless of decreases or increases in the final total contract amount or for any other cause.

4.5.2 The “Gravel Road Rehabilitation” item shall be paid per unit bid and shall include the following items, which price and payment shall be full compensation for all materials, labor, equipment and incidentals necessary to perform the work.

4.5.3 The “Temporary Stream Crossing”, item shall be paid per unit and shall include the following items: all materials, labor, equipment and incidentals necessary to perform the work which price and payment shall be full compensation for the work.

4.6 Pay Items

Item 4.1, “Site Preparation”, per lump sum. Cannot be more than 10% of the “Total

Amount Bid” for the project.

Item 4.2, “Gravel Drive Rehabilitation”, per ton.

Item 4.3, “Temporary Stream Crossing”, per lump sum.

5.0 EROSION & SEDIMENT CONTROL

5.1 Description

This item shall consist of furnishing all materials, equipment, labor and incidentals necessary for the installation of Matting, Sediment Control Barrier (e.g. silt fence or super silt fence) structures, and Stabilized Construction Entrances as designated in the Drawings.

Sediment control shall be placed on regraded outslope areas concurrent with construction and prior to revegetation. Additional quantities may be added at the discretion of the

WVDEP.

The CONTRACTOR shall be given an approved erosion and sediment control plan. This plan shall include measures to be utilized for temporary and permanent sediment and erosion control. This plan shall also include the measures as outlined herein. The approved plan does not relieve the CONTRACTOR of his/her responsibility to be in compliance with any and all permits. All costs associated with meeting the federal and/or state regulations shall be the sole responsibility of the Contractor.

NOTE: Sediment Control Measures shall be required on the perimeter of the project site for sediment control in accordance with the NPDES requirements. The silt fence for sediment control shall be place before any construction work begins. This fence shall remain and be maintained during the entire construction process.

The following are the minimum requirements of the NPDES BMP Manual.

VEGETATIVE PRACTICES

Except as noted below, stabilization measures shall be initiated as soon as practicable in portions of the site where construction activities have temporarily or permanently ceased, but in no case more than fourteen days after the construction activity in that portion of the site has permanently ceased.

Where the initiation of stabilization measures by the fourth day after construction activity temporarily or permanently ceases is precluded by snow cover, stabilization measures shall be initiated as soon as conditions allow.

Where construction activity will resume on a portion of the site within 14 days from when activities ceased, (e.g., the total time period that construction activity is temporarily halted is less than 14 days) then stabilization measures do not have to be initiated on that portion of the site by the seventh day after construction activities have temporarily ceased.

Areas where the seed has failed to germinate adequately (uniform perennial vegetative cover with a density of 70%) within 30 days after seeding and mulching must be reseeded immediately, or as soon as weather conditions allow.

Diversions must be stabilized prior to becoming functional.

EROSION & SEDIMENT CONTROL CONSTRUCTION SEQUENCE

Install stabilized construction entrance as shown on site plans.

Install perimeter sediment control devices as shown on site plans.

Clear and grub site.

Provide sediment control for any topsoil stockpiles.

Commence rough grading of site. Continue to maintain and inspect all erosion and sediment controls.

Install additional erosion and sediment controls as shown on site plans.

Fine grade site.

Permanently seed and mulch all disturbed areas within 7 days of reaching final grade and install erosion control wattles.

Upon completion of project including adequate stabilization, remove all remaining erosion and sediment controls.

Erosion Silt Dike - This work shall consist of furnishing, installing, maintaining, and, when required, removal of the Temporary Silt Dike. The dikes shall be used as a continuous line barrier at the toe of slope or R/W line to contain sediment or as a ditch barrier placed perpendicular to the flow of water in a defined drainage ditch to minimize erosion and contain sediment. These dikes shall be installed and located as soon as construction will allow or as directed by the Engineer.

5.2 Materials

5.2.1 Sediment Control Barriers: silt fencing materials and installation shall meet all applicable requirements of the manufacturer’s specifications.

Even with the specific prior approval of the WVDEP, the use of silt fence shall be limited to relativity flat areas and the toe of selected slopes.

5.2.2 Stabilized Construction Entrances shall consist of coarse 3-6 inch stone over a geotextile fabric.

5.2.3 Rolled Erosion Control Product (RECP): The erosion control blankets for slope stabilization, Rolled Erosion Control Products, shall consist of Excelsior Type I

Curlex lining or an approved equal. Wooden stakes shall be 1-½” x 1-½” x 36”.

5.3 Maintenance

5.3.1 During the course of the project, sediment control barriers shall be maintained in sound condition and accumulations of silt which may threaten their effectiveness shall be removed. Silt removed from the sediment control structures shall be taken to an approved disposal area.

5.3.2 The Stabilized Construction Entrance shall be maintained in a condition that will prevent tracking or flowing of sediment onto public rights-of-way. This may require periodic top dressing with additional stone as conditions demand and repair and/or cleanout of any measures used to trap sediment. All sediment spilled, dropped, washed or tracked onto public rights-of-way must be removed immediately.

Wheels on all vehicles shall be cleaned to remove sediment prior to entrance onto public rights-of-way. If washing is required, it shall be done on an area stabilized with stone and which drains into approved sediment trapping device. If the street is washed, precautions must be taken to prevent muddy water from running into waterways or storm sewers.

At a minimum, all erosion and sediment controls on the site will be inspected at least once every seven calendar days and within 24 hours after any storm event of greater than 0.5 inches of rain per 24-hour period.

All controls should be cleaned out when sediment reaches one half the sediment capacity of that control.

Inspection and maintenance records must be kept onsite.

5.4 Installation

5.4.1 Sediment Control Barrier:

Silt Fence: Fence posts shall be a minimum of 36" long driven 16" minimum into the ground. Where ends of geotextile fabric come together, they shall be overlapped, folded and stapled to prevent sediment bypass. Silt Fence shall be inspected after each rainfall event and maintained when bulges occur or when sediment accumulation reached 50% of the fabric height.

5.4.2 Stabilized Construction Entrance: A stabilized construction entrance shall be required at the access point of the construction site. The stabilized construction entrance shall consist of filter fabric and a minimum of six (6) inches of 3” to 6” stone. The stone entrance shall be a minimum of seventy (70) foot long and twelve

(12) foot in width. This stone construction access must conform to the detail drawings shown in the plans.

5.4.3 Rolled Erosion Control Products (RECP): At the top of slope, anchor the RECP’s according to manufacturer’s recommendation. Securely fasten all RECP’s to the soil by installing stakes/staples at a minimum rate as shown by manufacture’s recommendation. For the most effective RECP installation use stake/staple patterns and densities as recommended by the manufacturer. For adjacent and consecutive rolls of RECP’s follow seeming instructions detailed in the Plan or by manufacturer’s recommendations. Additional wooden stakes shall be 1-½” x 1-½” x 36” staked at 2’ c-c at the top of each roll of matting.

5.5 Removal

Upon completion of the project including adequate stabilization, all temporary erosion and sediment controls shall be removed from the site, including but not limited to water breaks, water break outlet protection, check dams and silt fencing.

The site should be left with a clean/neat appearance and any disturbed areas shall be revegetated. Rock outlet protection for permanent drainage structures shall not be removed once the project is complete.

5.6 Method of Measurement

5.6.1 The method of measurement for “Silt Fence” installation and maintenance in conformance with the specifications and accepted by the WVDEP shall be on a per linear foot basis to include stakes, all necessary materials, supplies, labor and equipment for installation and maintenance including sediment removal and disposal.

5.6.2 The method of measurement for “Stabilized Construction Entrance” installation and maintenance in conformance with the specifications and accepted by the WVDEP shall be on per ton and shall be based upon weigh tickets from the commercial supplier of the stone that is delivered and placed at the locations identified on the plan drawings. This item shall include all necessary materials, stabilized fabric, supplies, labor and equipment for installation and maintenance including periodic top dressing with additional stone and removal at completion of the project work.

5.6.3 The method of measurement for “Rolled Erosion Control Products” installation and maintenance in conformance with the specifications and accepted by the WVDEP shall be on a per square yard basis to include all stakes/staples, all necessary materials, supplies, labor and equipment for installation and maintenance including repairing any damaged slopes, rills and replacing matting, as described under the maintenance section.

5.7 Basis of Payment

5.7.1 Silt Fence payment shall be based on the contract unit price bid for the following items, which price and payment shall be full compensation for all materials, labor, equipment and incidentals necessary to perform the work. Additionally, payments shall constitute full compensation for any required maintenance, sediment removal and disposal.

5.7.2 Stabilized Construction Entrances payment shall be based on the contract unit price bid for the following items, which price and payment shall be full compensation for all materials, labor, equipment and incidentals necessary to perform the work.

Additionally, payments shall constitute full compensation for any required maintenance including periodic top dressing with additional stone and removal at completion of the project work.

5.7.3 Rolled Erosion Control Products payment shall be based on the contract unit price bid for the following items, which price and payment shall be full compensation for all materials, labor, equipment and incidentals necessary to perform the work.

Additionally, payments shall constitute full compensation for any required maintenance, slope repair, matting replacement and disposal.

5.8 Pay Items

Item 5.1, “Silt Fence”, per linear foot.

Item 5.2, “Stabilized Construction Entrance”, per ton.

Item 5.3, “Rolled Erosion Control Product”, per square yard.

6.0 REVEGETATION

6.1 Description

This work shall cover all operations incidental to the establishment of vegetation within the limits of construction as shown on the Drawings and any other areas as approved by the

WVDEP. This work also includes the furnishing and the application of fertilizer, agricultural limestone and mulch and the furnishing and sowing of seed, all in accordance with these Specifications and as designated herein.

No areas outside the limits of construction shall be disturbed without prior approval from the WVDEP in order to ensure that Right-of-Entry has been obtained.

Any areas outside the limits of construction, disturbed by the Contractor shall be re-vegetated by the Contractor at no expense to the WVDEP.

6.2 Materials

6.2.1 Fertilizer

The commercial fertilizer to be used shall consist of 10-20-20 grade of uniform composition and furnished in standard containers. These containers, in accordance with applicable state and federal laws, must be clearly marked with the following information:

a. Weight

b. Name of Plant Nutrients

c. Guaranteed Nutrients Percentages

Fertilizer shall be applied at a minimum rate of 1,000 lbs/acre. Fertilizer shall be applied immediately to all areas reaching final grade.

6.2.2 Lime

The lime to be used will be an agricultural grade pulverized limestone containing a minimum of 75% total carbonates or calcium carbonate equivalent. Fineness will be such that no less than 70% will pass through a #100 sieve and 100% will pass through a #20 sieve.

Lime shall be applied immediately to all areas requiring seeding reaching final grade by 1 of the 2 methods listed in Section 6.2.1, “Fertilizer”.

6.2.3 Seed Mixtures

The variety of grass and legume seed furnished for the project shall bear a tag, in accordance with applicable state and federal laws, with the following information listed:

1. Lot Number

2. Seed Producers Name

3. Percent Purity

4. Percent Germination

5. Date of Germination Testing

6. Weed Seed Content (should be <0.25% by weight)

All leguminous seed shall be inoculated with the specified strain of rhizobia which shall be a pure culture of bacteria selected for maximum vitality. No rhizobia shall be used which has passed the expiration date on each package. The inoculant shall be applied at five times the recommended rate except when used in a hydroseeding mixture when the rate will be ten times the recommended rate.

6.2.3.1 Temporary Seed Mixture

All stockpiles or other disturbed areas which will require further disturbance in which the additional disturbance will be delayed for a period of two (2) weeks or longer shall be vegetated according to the following guidelines.

SPRING SUMMER FALL WINTER

Variety of 3/15-5/15 5/15-8/15 8/15-10/15 10/15-11/15

Seed -----------------lbs/acre---------------------

Annual Ryegrass 40 40

(Lolium multiflorum)

German Millet * 40

(Setaria italica)

Cereal Rye

(Secale cereale) 170

*Do not use Japanese Millet

All areas to be temporarily seeded which are to be re-disturbed shall be fertilized with 500 lbs/acre of 10-20-20. All areas reaching final grade to be temporarily seeded shall be fertilized according to Section 6.2.1. Lime shall be applied according to Section 6.2.2 and mulched according to Section

6.2.4.

6.2.3.2 Lawn Seed Mixture

Existing lawn areas disturbed by construction shall be reseeded using the following mixture:

Rate Seed Minimum Specifications lb/1000 sq. ft. Variety 0% Purity %Total Germination

0.45 Red Fescue 98 85

(Pennlawn)

0.90 Kentucky Bluegrass 85 75

0.70 Merion Bluegrass 90 75

0.20 Annual Ryegrass* 95 85

*Use Annual Ryegrass only in mixtures seeded after August 1 and prior to May 15.

6.2.3.3 Permanent Seed Mixture

Permanent vegetation shall be established on all areas reaching final grade or other areas not likely to be destroyed by further construction activities.

Any areas which reach final grade between March 15 - May 15 or August

15 - October 15 shall be seeded with the appropriate temporary seed mixture according to Section 6.2.3.1. These areas shall then be reseeded with a permanent seed mixture, without Annual Ryegrass, during the next defined seeding period according to this section. The actual date of permanent seeding will require the Engineer's approval.

SPRING FALL

Variety of 3/15 - 5/15 8/15 - 10/15

Seed * --------------lbs/acre----------

Orchardgrass 30 30

(Dactylis glomerata)

Birdsfoot Trefoil (1) 15 15

(Lotus corniculatus)

Red Clover 10 10

(Trifolium pratense)

Annual Ryegrass (2) 25 25

(Lolium multiflorum)

Spring Oats 35 0 or

Winter Wheat 0 90

(1) Herbaceous legumes must be treated with the appropriate bacterium before seeding. On areas which are steeply sloping (steeper than 1.7:1) or slide prone, substitute Crownvetch (Coronilla varia) at 20 lbs./acre for

Birdsfoot Trefoil.

(2) Use Annual Ryegrass only in mixtures seeded after August 1 and before

May 1.

*Use only certified “blue tag” seed. Seed-rate suggested is for pure live seed

(PLS) in lbs/acre.

*For shaded areas add the following quantity of seed to the standard mix:

Lawn Seed Mixture Add 4…