This is a technical memorandum from GEOLABS, INC., a geotechnical engineering firm, submitted to AECOM dated June 16, 2026, in support of the Intersection Improvements at Bayfront Highway project located on the Island of Hawaii. The memorandum provides geotechnical recommendations for the design and installation of cast-in-place concrete drilled shaft foundations to support new street light poles for the project. The analysis is based on structural loading information provided by the project structural engineer, including axial loading of 1 kip, shear loading of 2 kips, bending moment of 32 kip-feet, and torsional loading of 2.5 kip-feet. GEOLABS recommends installing 24 or 30-inch diameter drilled shafts extending 15 to 25 feet below finished grade, with drilled shaft lengths governed primarily by moment loading demand and the depth of basalt rock formation, requiring a minimum rock socket of approximately 5 feet into basalt when encountered. The memorandum includes detailed tables of ultimate compressive load capacities for various light pole locations along Hawaii Belt Road and Kamehameha Avenue, ranging from 215 to 270 kips depending on shaft diameter and subsurface conditions.

The technical assessment addresses lateral load resistance calculations using LPILE analysis software, with lateral deflections ranging from 0.03 to 0.09 inches and maximum induced moments between 38 and 45 kip-feet at various depths. Foundation settlement is estimated at less than 0.5 inches, with significant elastic settlement expected upon load application. The memorandum emphasizes critical construction considerations, including the need for proper drilling techniques, appropriate equipment to penetrate difficult subsurface conditions (dense cobbles, boulders, and basalt formations), and adherence to concrete placement specifications using tremie methods with low-shrink concrete at 7 to 9-inch slump. GEOLABS requires on-site representation during drilling and installation operations to observe subsurface conditions and confirm compliance with recommendations, particularly regarding hole preparation and concrete placement completion within 24 hours of drilling.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GEOLABS, INC. TECHNICAL

Geotechnical Engineering and Drilling Services MEMORANDUM

94-429 Koaki Street, Suite 200 • Waipahu, Hawaii 96797

Telephone: (808) 841-5064 • E-mail: hawaii@geolabs.net Hawaii • California

DATE: June 16, 2026 @ 4:43 PM W.O. No.: 8467-00 TO: AECOM FROM: John Chen/Taylor Onizuka ATTN: Ms. Jessica Samura NO. OF PAGES: 4 SUBJECT: Intersection Improvements at Bayfront Highway Light Pole Drilled Shaft Foundation Recommendations E-MAIL: Jessica.Samura@aecom.com COPY TO: Blum@kaihawaii.com File / Original

This technical memorandum presents our geotechnical recommendations in support of the light pole drilled shaft foundation design for the Intersection Improvements at Bayfront Highway project on the Island of Hawaii.

Based on the information provided, we understand that it is desired to design a cast-in-place concrete drilled shaft foundation system to support the proposed new street light poles based on the design criteria provided by AASHTO LRFD Bridge Design Specifications 9th Edition, 2020. The project structural engineer provided the following structural loading information for the foundation design analysis.

STRUCTURAL LOADING INFORMATION

Street Light Pole

Axial Loading 1 kip

Shear Loading 2 kips

Bending Moment 32 kip-foot

Torsional Loading 2.5 kip-foot

Based on the provided structural load demands and the subsoil conditions encountered at the project site, we recommend installing a 24 or 30-inch diameter drilled shaft foundation extending to 15 to 25 feet below the designed finished grade to support the new street light pole.

It should be noted that the drilled shaft lengths are governed and determined by the moment loading demand.

The load-bearing capacities of the drilled shafts will depend largely on the surrounding soil and the relative depth of the basalt rock formation within the bearing strata. If basalt rock is encountered, the drilled shafts should extend to achieve a minimum rock socket of about 5 feet into the basalt formation. Our recommendations pertaining to the drilled shaft capacities and estimated lengths are presented in the table below.

Intersection Improvements at Bayfront Highway Page 2 Light Pole Drilled Shaft Foundation Recommendations W.O. 8467-00 June 16, 2026

GEOLABS, INC.

Hawaii • California

ULTIMATE COMPRESSIVE LOAD CAPACITIES OF DRILLED SHAFT FOUNDATIONS

Light Pole Location

Drilled Shaft Diameter (inches)

Subsurface Conditions

Drilled Shaft Length

(feet)

Ultimate Compressive Load Capacity

(kips)

Hawaii Belt Road

10 ft Surficial Fill 15 (min.5-foot rock socket) 215

Surficial Fill 25 75

Kamehameha Ave Volcanic Ash 25 140

Hawaii Belt Road

10 ft Surficial Fill 15 (min.5-foot rock socket) 270

Surficial Fill 20 75

Kamehameha Ave Volcanic Ash 20 140

Lateral Load Resistance

The lateral load resistance of drilled shafts is a function of the stiffness of the surrounding soil, the stiffness of the drilled shaft, allowable deflection at the top of the drilled shaft, and the induced moment in the drilled shaft. The lateral load analyses were performed using the program LPILE, which is a microcomputer adaptation of a finite difference, laterally loaded deep foundation program originally developed at the University of Texas at Austin. The program solves deflection and bending moment along a deep foundation under lateral loads as a function of depth. The analysis was carried out with the use of non-linear “p-y” curves to represent soil moduli. The lateral deflection was then computed using the appropriate soil moduli at various depths.

Based on the provided structural loads and the subsurface conditions encountered during our field exploration, we performed the lateral load analyses for the drilled shaft foundations.

The results of our analyses are summarized in the table below. The project structural engineer should verify the drilled shaft structural capacity for the calculated induced stresses.

Intersection Improvements at Bayfront Highway Page 3

LATERAL LOAD ANALYSES FOR STREET LIGHT POLE

(24-INCH DIAMETER DRILLED SHAFT FOUNDATION)

Light Pole Location

Lateral Deflection

(inches)

Maximum Induced Moment

(kip-feet)

Depth to Maximum Moment

(feet)

Hawaii Belt Road

(min.5-foot rock socket) 0.06 39 6.6

25 0.09 38 4.6

Kamehameha Ave 25 0.05 39 4.8

NOTE: Lateral load analysis based on concrete compressive strength of 4,000 psi and a minimum of 1% longitudinal steel reinforcement.

LATERAL LOAD ANALYSES FOR STREET LIGHT POLE

(30-INCH DIAMETER DRILLED SHAFT FOUNDATION)

Light Pole Location

Lateral Deflection

(inches)

Maximum Induced Moment

(kip-feet)

Depth to Maximum Moment

(feet)

Hawaii Belt Road

(min.5-foot rock socket) 0.03 45 10.0

20 0.07 38 4.8

Kamehameha Ave 20 0.03 40 5.0

NOTE: Lateral load analysis based on concrete compressive strength of 4,000 psi and a minimum of 1% longitudinal steel reinforcement.

Foundation Settlements

Settlement of the drilled shaft foundations will result from elastic compression of the shaft and subgrade response of the foundation embedded in the soils encountered at the site.

The total settlement of the drilled shaft is estimated to be less than 0.5 inches. We believe that a significant portion of the settlement will be elastic and should occur as the loads are applied.

Intersection Improvements at Bayfront Highway Page 4

Drilled Shaft Construction Considerations

In general, the performance of drilled shafts depends significantly upon the contractor's method of installation and construction procedures. The following conditions would have a significant effect on the effectiveness and cost of the drilled shaft foundations.

The load-bearing capacities of drilled shafts depend, to a significant extent, on the friction between the drilled shaft, the surrounding soils, and the basalt formation. Therefore, proper construction techniques, especially during the drilling operations are important. The contractor should exercise care in drilling the shaft holes and in placing concrete into the drilled holes.

The thickness and hardness of the basalt formation may vary significantly across the project site. Our drilling exploration also encountered dense layers of cobbles and boulders near the surface along Hawaii Belt Road. Therefore, some difficult drilling conditions likely will be encountered and should be expected. The drilled shaft subcontractor will need to have the appropriate equipment and tools to drill through these types of natural obstructions, where encountered. The drilled shaft subcontractor will need to demonstrate that the proposed drilling equipment (and coring tools, where appropriate) will be capable of installing the drilled shafts to the recommended depths and dimensions.

We recommend concrete placement by the tremie method during drilled shaft construction. A low-shrink concrete mix with a high slump (7 to 9-inch slump range) should be used to provide close contact between the drilled shafts and the surrounding soil/rock. The concrete should be placed in a suitable manner to reduce the potential for segregation of the aggregates from the concrete mix. In addition, the concrete should be placed promptly after drilling (within 24 hours after drilling the holes) to reduce the potential for softening of the sides of the drilled hole.

It is imperative for a Geolabs representative to be present at the project site to observe the drilling and installation of the drilled shafts during construction. Although the drilled shafts are designed primarily based on skin friction, the bottom of the drilled holes should be relatively free of loose materials prior to the placement of concrete. Therefore, it is necessary for Geolabs to observe the drilled shaft installation operations to confirm the subsurface conditions.

CLOSURE